Welcome to the general Timeline. Here, all updates and events will be posted. Date, description and source, with a link if possible, must be provided. Timeline sections in any other articles (such as the SN articles) should only refer to this page.

Events and activities are assigned to the days according to local time.

This page should be kept in a manner that it is search-friendly (CTRL+F).

Abbreviations[]

  • B: Super heavy booster number [new designation]
  • BN: Super heavy booster serial number (first stage of the rocket)
  • CH4: (Liquid) methane
  • COPV: Composite overwrapped pressure vessel (black helium tank for tank pressurisation)
  • FST: FutureSpaceTourist
  • GSE: Ground support equipment, including ground tanks
  • HPU: Hydraulic pressure unit (on booster)
  • IT: Integration tower (for catching boosters and stacking starship)
  • LN2: Liquid nitrogen
  • LOX: Liquid oxygen
  • LR: Liebherr crane
  • MSIB: Marine safety information bulletin
  • NET: No earlier than [+date] (but very likely later)
  • NSF: NASASpaceflight
  • OLM: Orbital launch mount
  • OLS: Orbital launch site (the east part of the launch site)
  • PB: Power bay or comms building (at the far east of the OLS)
  • PPS: Propellant production site (prop prod site)
  • QD: Quick disconnect (arm)
  • RB: Raptor boost
  • RC: Road closure (prim and sec - primary and secondary)
  • RC: Raptor Center (same as raptor boost, but with gimballing capability)
  • RSN: Raptor engine serial number
  • RVac: Raptor vacuum engine
  • S: Ship (upper stage) [new designation]
  • SH: Starhopper
  • SF: Static fire
  • SN: Starship serial number (upper stage of the rocket)
  • SoLS: Suborbital launch site
  • SPMT: Self propelled modular transporter
  • TFR: Temporary flight restriction (for flight tests, issued by FAA)
  • TPS: Thermal protection system heat shield tiles (hexagonal black tiles)
  • TVC: Thrust vector control, by engine gimbal; hydraulic or electric

2021[]

December 2021[]

Date Description Source Link
31.12.2021 Scaffolding continued being removed from OLS, IT

Standard TFR up to 10000 feet renewed for January 2022

30.12.2021 OLM work continued

B4 prepared for lifting; QD disconnected (retracted and hatch closed); lifted by LR11000X and lowered onto a transport stand (engines spotted: RB28, RB29, RB30, RB 31, RB32, RB13, RB16, RB12, ... RB33, RB14, RB4, RB20, RB5, RB7, RB??, RB28); secured on stand

Wide bay construction work continued

Nosecone at production site with orange line markings

S24 common dome spotted

Unknown covers/"dog house" structures painted grey at production site

Load spreader and LR11000X disconnected from B4; B4 moved towards landing pad

OLS, IT: Scaffolding being removed

New RCs for January 4–6 (10am-6pm)

NSF

Mary

LabPadre

[1]
29.12.2021 SN20/S20 venting early morning

B4 hooked to LR11000X

OLM work

SN20/S20 flaps tested

SN20/S20 Static fire #4 and scrubbed attempt

RC for today extendet until 8pm

S21 tank section moved into mid bay (again)

NSF

Mary

LabPadre

[2]
28.12.2021 SN20/S20 Scrubbed static fire attempt

S21 nosecone still being worked on, S22 nc barrel section (5-rings) in front of it

Wide bay construction continued

LN2 deliveries to SoLS tank farm

Tent 3 nosecone work continued

Fabrication stand moved

S21 tank section still waiting outside mid bay

Stair assembly next to high bay continued

B7 fwd tank #3 section (3-ring) spotted; cmn dome barrel without dome

Two unknown "dog houses" or covers still at production site

OLM work continued

B4/OLM igniter test #5?

Alert notice issued for SN20/S20 static fire attempt

FAA: PEA issuing delayed until February 28

NSF

Mary

LabPadre

[3]
27.12.2021 B7 aft #4 ring barrel (4-ring with lead-ins) lifted into high bay and stacked with LOX section; now 16 out of 23 rings tall

Wide bay: Parts and beams delivered; construction work continued (preassembly of level 5&6 uner way)

Coil of stainless steel delivered

Ship mid-LOX tank section spotted in tent

LR11000X moved towards B4/OLM

OLM work continued

LN2 delivered to OLS tank farm

Alert notice and NOTMAR issued for SN20/S20 static fire attempt

B4/OLM two ignitor tests [vid 28]

NSF

Mary

LabPadre

[4]
26.12.2021
25.12.2021
24.12.2021
23.12.2021 Work on nosecones in tent 3 continued (one with old design, one with new design)

S21 tank section still waiting outside high bay, possibly being scrapped

Wide bay: Level 5&6 preassembly continued

B7 in high bay 12 rings tall [B7 according to NSF]

OLM work continued

SN20/S20 TPS tiles placed over the crane attach points "this could be for a full up test of the heat shield during a static fire" [NSF]

LN2 delivery to OLS tank farm

Stair assembly continued next to high bay (not clear if for high bay)

S22 nosecone barrel section (5-ring) [cf. Dec 19] in windbreak "It looks like this could be repurposed for another cargo door pathfinder"

B4/OLM igniter tests at 19:49 and 22:27

NSF

Mary

LabPadre

[5]
22.12.2021 B4 cryo proof test #3

[B7/B8?] fwd section lifted off sleeving stand, moved into tent 1

Coil of stainless steel delivered

Highbay stair assembly continued

Wide bay: level 5&6 first corner section preassembly on its way

Deliveries to production site: beams and flexible pipes

[B7/B8?] section lifted into high bay for stacking (4-ring with lead-ins)

[B7/B8?] 8-ring tank section (LOX and cmn dome) lifted by bridge crane; stacked onto the 4-ring section [add: B7]

S21 tank section moved out of mid bay once again; crane attached, lifted off transport stand near high bay

Stand moved to production site by SPMT

Nosecone [pathfinder] with new design now being scrapped

S21 nosecone moved out of high bay, tank section unhooked from crane after being placed on a shorter stand

NSF

Mary

Nic

LabPadre

[6]
21.12.2021 Piling work has already begun at Pad 39, pad and earth work [WAI]

Roberts Road (Florida based facility used in 2020, together with cidco rd): more area cleared, work on building extension work continued; LC49 proposed according to NASA [WAI]

B4 cryo proof test #2

Chopsticks work

B7/B8 stacking in high bay began [add: B7]

Work outside high bay: Staircase construction

Wide bay work continued

B2.1 test tank in structural test stand: closeup

Ship fwd section moved (3-ring, sleeved)

B7/B8 aft dome section sleeved (4-ring segment, 2 rings stiffeners; smaller rings [???]; 33 engines) and lifted from sleeving stand; 3-ring booster fwd dome sleeve with 2-rings stiffeners in front of it

Booster fwd dome attached to crane, lifted onto sleeving stand [likely B7/B8], sleeved with the 3-ring booster fwd dome sleeve

The new booster thrust puck stored outside tents

RC extended until 8pm

NSF

Mary

Nic

LabPadre

[7]
20.12.2021 B4 scrubbed testing

B2.1 all ropes connected to hydraulic pistons at the structural test stand

Booster common dome moved into mid bay (4-ring with lead-ins and stiffeners)

High bay: construction work outside, beams erected, possibly for an elevator [?]

S21 nosecone in

Ship nosecone barrel section (5-rings!!) [S22/S23/S24?]

Wide bay construction continued; level 2 wall covers continued to be added; work on completing beam structure on level 3&4

LN2 storage tank lifted and positioned at PPS

33 Raptor thrust/aft dome lifted onto sleeving stand [B7/B8] [add: B7]

LN2 delivery to OLS tank farm

OLS tank farm work continued: red and orange parts lifted into place

OLM work continued

Chopsticks work continued

Work and painting on a fence at landing pad

Booster dommon dome section spotted in high bay [add B7]

NSF

Mary

Nic

LabPadre

Below
19.12.2021 S21 tank section moved into high bay; moved back into mid bay later that day [???] NSF

Mary

Nic

LabPadre

[8]
18.12.2021 Black pillars still at production site

Wide bay: Fourth level 3&4 corner segment attached an lifted by LR11000 and installed

Booster fwd section in front tents

Ship section spotted in high bay (nc barrel section from yesterday?)

B2.1 work continued

Delivery if metal parts to launch site [SL-04, LN-2]

SN20/S20 work at engine section

Drilling rig working at the OLS tank farm

Chopsticks work continued

Purging of CH4 buffer tank

Raptor 2.0 engine test in McGregor on a horizontal test stand [Adam Cuker, confirmed by Elon Musk]

S21 moved into high bay at around 7pm

B2.1 stress tested; Remedios road closed

NSF

Mary

Nic

LabPadre

[9]
17.12.2021 Rocket garden at PPS: B5, BN2.1, B2.1, SN15, B6, SN16

B2.1 work continued

Sheriff at Remedios ave

B4 cryo proof test on OLM

PBI crane lowered and rose again near wide bay

Wide bay work continued; beams added between the newly added segments, finishing work on fourth corner segment of level 3&4 on ground

Nosecone barrel section in high bay

Booster methane sump delivered

S21 rolled out of mid bay; tiles not completely added, some broken or missing; aft flap mounting rig not yet installed; work platfrm on top has been removed some time ago

S22 inside mid bay at least 10 rings tall

SN15 aft flap inner skin has been removed

SN20/S20 work in engine section

Today's RC extdended until 5pm

Elon Musk tweets; video of B4 gimbal test (center engines)

McGregor: Raptor 2 engine test at 5:33 pm on horizontal test stand for about 2m24sec

NSF

Mary

Nic

LabPadre

Cuker

[10]
16.12.2021 Wide bay: second corner segment of level 3&4 lifted by LR11000 and installed and later disconnected; beams added between the two corner segments; third corner segment attached to LR11000 and lifted later

Nosecone cage (max Q test rig) moved by two SPMTs

SN15 work on one aft flap

B2.1 work continued; ropes lowered ("These are likely to be used to pull down the cap while the tank is filled and pressurized")

B6 work continued

Tall black stand? (column/pole) spotted at the production site

LR11000X lifted load spreader

SN20/S20 work on engine section, parts added [heat shields for Raptors?]

B4 remained connected to QD; work on a cover attached to aft section

QD arm work continued

Booster thrust puck accidentally delivered to launch site (third one for 13 inner engines), possibly for B9?; developed since first one spotted in early October (recesses bigger, [11] structural weaving increased - less weight) [WAI]

MaxQ testing cage moved to PPS/Sanchez site

Today's RC canceled

New RCs for Dec 23, 27-30 (10am-6pm)

NSF

Mary

Nic

LabPadre

[12]
15.12.2021 McGregor: Raptor engine test at 8:43 pm

Starhopper (SH) marine radar removed, new antenna mounted

Chopsticks work continued, cables attached near the hydraulic piston; later the green cables and piston has been removed; wires fed into the chopsticks

OLS tank farm: vertical LN2 tank venting, venting from a GSE equipment between GSE2 and GSE7

SN20/S20 work at the ex attach points

B4 still attached to LR11000X; OLM and B4 work continued; later detached from crane

Concrete work between launch site and hwy 4 continued; I beams added, likely for a new wall

Wide bay: level 3&4 section moved by LR11000

Single ring moved to scrapyard

B6 test tank moved to PPS, moved next to SN15, SN16, B5

Lines installed on the structural test stand (for B2.1)

NASA is preparing to conduct environmental assessments to develop a proposed new launch site, LC49, at Kennedy Space Center [NASA]

NSF

Mary

Nic

LabPadre

Cuker

[13]
14.12.2021 LR11000 disconnected from wide bay segment that has been installed yesterday; hooked to another corner segemtn of level 3&4 that has been finished; screws tightened; new beams delivered

S21 nosecone work continued in front of high bay, some tape has been removed

Structural test stand cap lifted onto B2.1 test tank (the one with the tank like top, has some heavy orange ropes on it, "can crusher cap")

Grinders used on one of SN15s aft flap

S24 common dome spotted (4-ring! instead of 3-ring!!)

OLM work continued, booster QD hood closed; later opened and likely connected to B4, work around QD

B4 work on OLM continued; ship QD arm likely to hold on booster

SN20/S20 some tiles are brown; cable attached on lower section onto TPS tiles; attach points being removed!; work at engine section

OLS tank farm LN2 tank venting (GSE1), some venting from detanked CH4 buffer tanks; LN2 deliveries

NSF

Mary

Nic

LabPadre

[14]
13.12.2021 OLM: welding work

B4 work on aft section (QD plate) ahead of lifting

B4 lifted onto OLM by LR11000X and installed carefully (engines spotted: RB28, RB29, RB30, RB31, RB32, RB13, RB16, RB12, RB18, RB15, RB17, RB3, RB6 RB33, RB14, RB4, RB20, RB5, RB7); all holddown clamps extended one by one manually; RB engine disconnect spotted

Booster stand moved away

Concrete forms prepared at launch site north of landing pad

SN20/S20 two red/orange boxes installed

Work on a funny looking structure at production site

S21 nosecone section moved towards high bay, tiles work continued

Wide bay: finished corner segment of level 3&4 lifted by LR11000 and installed

NSF

Mary

Nic

LabPadre

Marcus House

[15]
12.12.2021 Ship fwd dome lifted on sleeving stand

Booster aft dome sleeve in front tents

B6 test tank worked on in high bay

B2.1 work continued: strengthening? ring added around the lower part of the test tank

OLM: Scaffolding staircase removed as the fix staircase has been finished (the top part is a spiral staircase); much work

Hydraulic piston still hanging loose from Chopstick extension

Compressed nitrogen trailer at landing pad

OLS a lot of venting south of tank farm berm

LR11000X moved towards OLM

B4 moved towards OLM, likely to be lifted soon

OLS tank farm: testing [?], some venting from around the LOX subcoolers

B4 connected to LR11000X late in the night

NSF

Mary

LabPadre

[16]
11.12.2021 Pad work in front of OLS tank farm continued: concrete poured

B4 unhooked from load spreader (without having moved), LR11000X moved

OLM: Booster QD work continued

OLS, IT: Ship QD work continued

SN20/S20 Work on a cover above QD; nosecone hatch closed

S21 nosecone work continued, horizontal beam added between nc and nc barrel section

Work on the two LN2 storage tanks at PPS

SoLS pad Ship QD at PPS

Wide bay level 3&4 work continued

B2.1 work continued at PPS

Nosecone with TPS attachment point in tents 3

Ship aft aerocover moved

Hwy4 roadwork between launch and production site continued (since several weeks major work)

NSF

Mary

Nic

LabPadre

[17]
10.12.2021 OLS, IT: More pipes lifted into place

OLS tank farm: Earth and concrete work continued

B4 still hooked to LR11000X, not moved yet

Transport stand parts delivered moved from launch site

SPMT with heavy counterweights moved to launch site

Barrel section in front of tent 3 (the one hooked to crane) is S22 thrust section

B6 test tank moved into high bay

B2.1 work continued

Wide bay construction work continued

New RCs for December 15–16 (10am-6pm) and 17 (8am-2pm)

OLM: New lights have been installed; QD tested (hood retracted, QD moved foreword)

NSF

Mary

LabPadre

[18]
09.12.2021 OLS tank farm: venting from horizontal CH4 buffer tank and vertical LN2 tank; work on the LN2 tank; work on concrete pad; multistage pump prepared and lifted into place near LOX subcoolers (into the ground?); LN2 delivery

Chopsticks work continued, new part (hydraulics?) added at the downward facing stabilisation extension

SN20/S20 work on engine section and through access hole

OLM work continued

S21 nosecone TPS tiles work continued

Barrel section with lead-ins (the same from yesterday) still hooked to crane outside tent 3

SN23 (S23) nosecone hooked to crane outside tents [not the same as the scrap nosecone from previous days?]

Booster aerocover spotted at production site

Wide bay construction work continued

B6 test tank work continued

RC for December 13 canceled

Ship QD (likely for suborbital pad) spotted near the starbase sign (RGV)

FCC application for radio communications with Ship and Booster for the orbital flight test granted for the requested window from 20 December 2021 until 1 March 2021; Purpose: "Experimental orbital demo and recovery test of the Starship test vehicle..."

NSF

Mary

Nic

LabPadre

[19]
08.12.2021 Ship aft section out of tents (hooked to crane), as well as scrap dome

B6 test tank work near wide bay construction site

Wide bay work continued; panels being installed on level 3&4 (preassembly)

S21 nosecone TPS tiles work continued

B5 unhooked from bridge crane; B5 moved out of high bay to the booster display stand recently constructed (located at PPS next to SN15 and SN16; engine production is confirmed to be slower than booster productin, so either B5 is being retired or on a waiting position)

B2.1 work at PPS

Scrap nosecone (the one with fewer panels) again spotted outside tent 3

OLM work continued

B4 connected to load spreader [not two days ago?], work on COPVs

SN20/S20 flaps still remained open

LN2 delivered to SoLS

RC for December 10 canceled

NSF

Mary

Nic

LabPadre

[20]
07.12.2021 Booster QD hood lifted onto OLM and installation began

OLM work continued

OLS, IT work continued

Earth work in front of OLS tank farm

B4 work continued

Delivery of some part wrapped in blue cover

SN20/S20 work through access hole

LN2 delivered to SoLS tank farm

Wide bay work continued

Dome delivered to production site

B2.1 is back at PPS

S21 tank section work in mid bay through access hole

S21 nosecone TPS tiles work continued

B6 common dome section with lead-ins hooked to crane; booster fwd dome section spotted near it, also attached to crane; both later detached from crane; fwd dome attachedto another crane, stacked onto B6 common dome; B6 apparently now a test tank with B6 common dome and a booster forward dome

RC for December 8 and 9 canceled

New intermittent RC for December 8 (9.30am-11.30am)

NSF

Mary

Nic

LabPadre

[21]
06.12.2021 Wide bay construction work continued: panels added on level 1, level 3&4 cross wall segments nearly fully added

Liquid nitrogen tank delivered to the PPS

S22 fwd dome section lifted into mid bay

Wide bay beams and parts delivered

Electrical equipment delivered (ABB)

B2.1 prepared for rolling back, then rolled back to production site

OLS tank farm GSE1 venting again

OLM construction work continued, especially on QD

LR11000X moved

OLS, IT work continued

SN20/S20 work on engine section

Booster QD hood has been delivered to launch site last night

B4 connected to LR11000X

RC for December 7 canceled; as well as today's

New RCs for December 10 (8am-2pm) and 13, 14 (10am-6pm)

NSF

Mary

Nic

LabPadre

[22]
05.12.2021 OLM work continued, especially on booster QD and lower exterior pipes

Chopsticks work continued

OLS tank farm work on pipe insulation

B2.1 prepared to move, SPMT moved towards test tank

Outriggers removed from LR11000X, moved to the production site

Ship leg skirt and fwd dome seen in front tents

Booster fwd dome section in front of tents, as well as barrel sections

NSF

Mary

LabPadre

[23]
04.12.2021 B5 hooked to bridge crane again; has all the aft section hardware installed already, but no covers yet installed

Nosecone with old design spotted in tent 3 with flap attachment rig installed

Booster barrel section moved into tent

S22 fwd dome section moved into tent

Earthwork at the PPS

Wide bay level 3&4 preassembly work as well as level 1&2 panels continued to be added

SN20/S20 work on extended flaps; fuelling adapter closeup; engine section worked on

B4 work on aft section continued

Concrete work at west side of the OLS tank farm

OLM work continued (NSF calls it OLP) as well as work on chopsticks

Booster load spreader moved to launch site, unloaded by LR11000X (LabPadre name: Marvin) (first job since crane was built)

NSF

Mary

Nic

LabPadre

[24]
03.12.2021 SN20/S20 fwd and aft flaps have been opened (Starship Gazer)

Work on a steel cable roll near SN16; thrust rams for Rvac engine thrust simulation spotted at PPS

Platform raised at PPS, Grove crane moved Panels being added to wide bay (RGV); level 3&4 work continued (preassembly); more beams delivered

Nosecone test stand (cage/rig) moved to scrapyard on two SPMTs

Delivery of a red/black structure to production site "343 ton cap"

S21 Nosecone TPS tiles work contineud

S22 fwd dome section shown outside tents

B2.1 Cryo Proof Test

GSE1/Shell5 venting; as well as GSE on OLS tank farm

LN2 delivery to OLS tank farm

OLS, IT: Ship QD work continued; also from the new offloading area at the old landing pad

Insulated pipe moved around near GSE5 at launch site

LC-39A at Cape Canaveral Kennedy Space Center: Work has begun with the Starship mount being dismantled (spotted on satellite pic by Harry Stranger); Elon Musk confirmed that "Construction of Starship orbital launch pad at the Cape has begun"[25] and that it "Will have similar, but improved, ground systems & tower to Starbase"[26].

B5 rolled out of highbay for a few minutes before rolling back in again

B4: Aerocovers for both hydraulic power units were installed

NSF

LabPadre

[27]
02.12.2021 SN20/S20 fwd and aft flaps tested and opened at 12:40

RC for today extended until 10pm

Unfinished domes spotted outside the tents

S22 fwd dome section spotted in front of tents

Wide bay construction work continued

S21 nosecone TPS tiles work continued

Work on a new structure in front of tents (looks like a hood; for Ship QD?)

Wide bay beams delivered to PPS/Production site

B2.1 cryo proof test

B5 unhooked from gantry crane in high bay

B4 raceway cover continued to be added (Kevin Randolph)

NSF

Mary

LabPadre

[28]
01.12.2021 OLS: South berm work continued; work on chopsticks

LOX delivered to the OLS tank farm

B4 COPV covers being installed

GSE4 test tank moved south

Wide bay work continued (level 1&2 vertical beams, level 3&4 preassembly)

S21 nosecone TPS tiles, red tape added

High bay rooftop bar work continued

Scrap smooth nosecone shown

Booster cmn dome section/sleeve shown in a tent

SN20/S20 aborted static fire attempt

SN20/S20 header tank test

B2.1 cryo proof test, possibly also puck shucking; the first time OLS tank farm was used for testing

New RCs for December 7–9 (10am-6pm)

NSF

Mary

Nic

LabPadre

[29]

November 2021[]

Date Description Source Link
30.11.2021 S21 LOX header tank downcomer lifted into mid bay for installation in S21 (the_denks)

RC for today canceled

OLM: Insulation added to pipes, meaning that they have been certified and ready to use

Prototype nosecone made with fewer panels now for scrap Wide bay beams assembly for level 3&4 continued; level 1&2 installation of small vertical beams continued; progress after some sort of a pause

Dome moved to scrapyard

SN20/S20 work on TPS tiles; all tiles have been replaced or repaired except those near the header tank vent; work on the engine section

S21 nosecone TPS tiles work continued

Chopsticks work continued

OLS tank farm work con GSE piping continued

B4 work near COPVs, raceway covers continued to be installed

SN20/S20 aft section work continued

GSE4 test tank moved southwards on landing pad (Starship Gazer)

Booster display stand under construction next to SN15 and SN16 at PPS (to the south west, RGV)

S23 nosecone (next generation) spotted by Starship Gazer

Alert notice for SN20/S20 static fire attempt isssued to residents; as well as NOTMAR posted

NSF

Mary

Nic

LabPadre

[30]
29.11.2021 RC for today canceled

New RCs for December 2, 6 (10am-6pm) and December 3 (6am-12pm)

OLM and chopsticks work continued OLS, IT; NE upper column now also with scaffolding installed

SPMT moved to SoLS; parts moved to landing pad near GSE4; then went to production site

Earth work at landing pad

LN2 delivery to SoLS

Wide bay construction continued; small vertical beam installation began

S21 tank section work in mid bay continued

S21 nosecone TPS tiles: new tapes added

Booster common dome section (sleeve?) spotted in a tent

S22 fwd dome section (sleeve?) spotted

NSF

Mary

Nic

LabPadre

[31]
28.11.2021 Launch site: pipes delivered, likely to OLS tank farm

B4 work near the COPVs

LN2 delivery to OLS tank farm; cone-like shaped item delivered

S21 nosecone TPS tiles work continued

Booster QD hood work continued at production site

Scrap fwd dome spotted

SN20/S20 work near aft flaps

OLS, IT: NW upper column scaffolding installed

Chopsticks work continued

Ship fwd dome spotted in front of tents

B6 common dome section hooked to flipping jig and flipped; methane transfer pipe appears to be plugged [?]

NSF

Mary

LabPadre

[32]
27.11.2021 SN20/S20 work continued through access hatch and on engine section

OLS tank farm work on pipe insulation

OLM work continued

B4 work continued

OLS, IT: upper SE column part fully covered with scaffolding

S21 aft flap alignment jig fully installed on one side (other side not visible)

Booster quick disconnect (QD) hood at launch site painted black

S21 nosecone TPS tiles work continued, especially around flap; label spotted: "Attention do not move flap"

Flip rig attached to a crane infornt of production tents

Booster common dome section flipped [likely B7?]

Standard TFR renewed for December (still 10000 ft)

NSF

Mary

Nic

LabPadre

[33]
26.11.2021 Fwd dome spotted outside tents

OLM venting spotted again; announced on loudspeakers

Barrel section moved

LN2 delivered to OLS tank farm

OLS tank farm work continued on GSE pipes

Helium delivered

NSF

Mary

LabPadre

[34]
25.11.2021 Thanksgiving in US - not much work
24.11.2021 S24 common dome sleeve? spotted

OLM work continued

Concrete work between OLS tank farm and hwy 4

OLS tank farm: GSE plumbing being insulated, berm work continued

B4 work on engines, raceway cover and aft section continued

S21 nosecone TPS tiles work continued; some tape removed

S21 tank section in mid bay worked on

Raptor gimbal joints spotted

S22 stacking has begun in mid bay; cmn dome section identified; next to S21

Ship flap delivered; aft flap aerocovers spotted at the production site

NSF

Mary

Nic

LabPadre

[35]
23.11.2021 Ship fwd dome still outside tent; new jig next to it [S23?]

S21 nosecone TPS tiles work continued; many tapes around the flap

Wide bay work continued; Bigge crane has been lowered, now lifted again; several beam parts being assembled on ground; many more beams delivered

Ship [S22?] fwd dome section with many TPS tiles worked on

S21 tank section work in mid bay continued

Ship QD mechanism (star-shaped adapter and pipes) installed onto the QD arm

Chopsticks work continued

B4 work on some areocovers

Concrete torn up at OLS; earth work; rebar tied for new pad

OLS tank farm: inspection?

NSF

Mary

Nic

LabPadre

[36]
22.11.2021 OLM work continued; Booster QD extended; welding on circumfering pipe

Chopsticks worked on

Landing pad: parts relocated

LN2 deliveries to OLS tank farm and SoLS tank farm

SN20/S20 work on cables leading to raceway continued as well as on engine section

Wide bay work continued (third level installation hasn't begun yet); beams on ground being worked on

Rebar laid near high bay [?]

Work on booster QD hood at production site

S21 tank section worked on in mid bay

NSF

Mary

Nic

LabPadre

[37]
21.11.2021 OLM work continued; gas vented (likely Nitrogen used to purge GSE plumbing)

Earth work near landing pad

SN20/S20 work on engine section continue

S21 nosecone work on TPS tiles continue, more tapes added

Booster common dome sleeved [B6?]; second booster common dome sleeve moved near it

B5 work continued

Booster quick disconnect (QD) hood for OLM spotted, which will shield the booster QD from the exhaust plume

Ship quick disconnect (QD) spotted

NSF

Mary

LabPadre

[38]
20.11.2021 LN2 delivered to OLS tank farm

OLS tank farm: Work on connection the new horizontal CH4 tanks to tank farm continued

SN20/S20 and B4 (inspection) work

OLM work continued

Wide bay work continued; some beams being preassembled before lifting

Nosecone moved inside tent 3; nosecone barrel section with therman blankets spotted

S21 nosecone work continued, more tapes added

Booster common dome now on sleeving stand

B5 welding of the two sections

New Starship segment [S22?] spotted next to S21

NSF

Mary

Nic

LabPadre

[39]
19.11.2021 Ship fwd dome and booster cmn dome in front of tents

S21 nosecone TPS tiles inspected

Aerocovers staged for installation on S21; some tiles on it

B5 LOX tank lifted onto a transport stand

SN20/S20 work around cabling on aft section

LOX delivered to SoLS tank farm

OLS, IT: winch jutty received side walls for protection

OLM and IT work continued (also on chopsticks)

Road work at the entrance to the OLS tank farm

OLS tank farm: New black boxes installed near the orange and red pistons

Deliveries to production site

S21 nosecone green tape affixed; aft section prepared for aft fin installation

B5 methane tank section load spreader attached lifted by bridge crane and stacked onto LOX section (final stacking)

Wide bay construction work continued

SN20/S20 fwd and aft flaps tested

New RCs for 29 November - 1 December (10am-6pm)

NSF

Mary

LabPadre

[40]
18.11.2021 OLM work continued; work on a new circumfering pipe

LOX delivery to OLS tank farm

Wide bay beams accidentally delivered to launch site

QD arm work continued

SN20/S20 aft section work continued

B4 preparation work around aft section continued

LN2 delivered to SoLS tank farm

Concrete torn up between OLS tank farm tanks and Hwy4

B5 methane section moved in high bay

More wide bay beams delivered to production site

Scrap stainless steel sheets shown

S21 tank section worked on in mid bay

S22 cmn dome lifted into mid bay

NSF

Mary

Nic

LabPadre

[41]
17.11.2021 Elon Musk Presentation

S21 nosecone construction and TPS tiles work continued

S22 cmn dome work continued; extra vent with strange nozzle added (Potentially for a new thruster configuration?)

Wide bay construction work continued; more beams delivered

S21 work in mid bay continued

Fwd dome caps spotted

Deliveries to production site (some sort of pistons, new I-beams for wide bay)

OLM work continued

B4 inspection work

SN20/S20 work at engine area

Earth work at the launch site continued

OLS, IT: Some scaffolding removed

Elon Musk announced significant update for engine, basically a new engine: "A complete design overhaul is necessary for the engine that can actually make life multiplanetary. It won't be called Raptor."

RCs for November 18–19 canceled

Elon Musk presentation [see article]

NSF

Mary

Nic

LabPadre

[42]
16.11.2021 RC for November 17 canceled

OLM work continued

Chopsticks work continued

LOX deliveries to OLS tank farm continued

Section of flexible pipe spotted at OLS tank farm

Landing pad has received piping from OLS tank farm, possibly for more fuelling truck adapters

Landing pad/hwy4 berm removal continued

LN2 delivered to SoLS tank farm

Wide bay construction continued

Work on high bay construction elevator

S22 cmn dome section shown (3-ring, TPS tiles, lead-ins)

S21 nosecone TPS tiles worked on

Booster methane manifold spotted

Parts inventory at the production site shown

Unknown tubular part still at the production site, first spotted on September 19

Dome knuckle panels spotted

NSF

Mary

Nic

LabPadre

[43]
15.11.2021 FAA estimate: Environmental Review and permitting process would be completed by December 31; Transcripts from public hearings posted

COPVs loaded onto a flatbed

Wide bay construction work continued

Small pipes and rebar delivered to production site; as well as several trucks with beams [possibly for wide bay]

B5 scaffolding installed at the top of LOX section in preparation of stacking; transport stand moved into high bay

SPMTs moved crane mats away from launch site

Chopsticks worked on

OLM work continued in several areas (plumbing, wiring, QD, stairs)

Berm between landing pad and hwy 4 began to be removed

SN20/S20 aft flaps tested

NSF

Mary

Nic

LabPadre

[44]
14.11.2021 OLS, IT: Work continued (rails, piping on QD arm)

Wide bay: work on LR11000 boom top

S21: new black plate spotted on the hull, just left above the QD area

Nosecones with the new design (single segments) spotted in tent 3

B7 "fwd dome stiffened barrel" 3-ring sleeve spotted

COPV aerocover moved

Booster aerocover (for COPV's) frame spotted

OLM: Work on new permanent staircase began (behind one pillar)

NSF

Mary

LabPadre

[45]
13.11.2021 B6 aft section (sleeved?) shown, work on it

Booster aft tank #5 spotted [Label looks like B7]

S21 nosecone work continued

-Y FWD aero cover delivered (-Y is the ship's starboard side)

Stair sections being stacked in high bay

Grove GRT8100 moved

Ship fwd dome sleeve with thermal blankets spotted in tent

SN20/S20 work in engine area

OLS tank farm: Daily LOX deliveries continued

Chopsticks work continued

NSF

Mary

Nic

LabPadre

[46]
12.11.2021 SN20/S20 Perburner test and Static Fire #3 (first one with all six engines, more tiles lost)

B2.1 on structural test stand ("cancrusher", closeup of thrust test setup) and GSE4 moved from PPS to launch site

NSF introduced new channelcam

S21 nosecone TPS tiles worked on

RCs for November 15–16 canceled

New RCs for November 17–18, 22-23 (10am-6pm) and November 19 (6am-12pm)

NSF

Mary

Nic

LabPadre

[47]
11.11.2021 S21 nosecone work continued

S23 aft dome sleeve (3-ring) spotted

B6 fwd dome sleeve hooked to crane, lifted and sleeved with fwd dome

S21 in mid bay: preparation work for aft fin installation

LR11000-P1300: according to NSF, both the boom and the jib have been extended by 6 meters

BN2.1, GSE4, B2.1 and SN15 shown at PPS; workers prepared concrete forms at PPS near them

OLS tank farm: Berm extension work continued

QD arm work continued

Cable supply reel for chopsticks not yet unspooled fully

Wide bay work continued; LR11000 is inside it

Alert notice delivered to residence for possible SN20/S20 static fire on 12 November

"Elon Musk will give a 30mins Starship presentation to the 1st Space Studies Board / Board on Physics and Astronomy" on 17 November 2021, 6pm EST

NSF

Mary

Nic

LabPadre

[48]
10.11.2021 OLS work continued at several areas (as always)

OLS tank farm: new equipment delivered

B4 COPV Covers installation finally began

Berry crane, Grove GMK 6350L, left launch site, drove to production site

SoLS tank farm venting

LOX deliveries to OLS tank farm continued

OLM work on booster QD

OLS, IT: work on QD arm

Ship aft dome sleeve (3-rings, lead-ins, TPS tile attachment points) moved at production site

Wide bay work continued

B2.1 work continued

B5 work in high bay continued

S21 nosecone TPS tiles worked on

RC for November 11 canceled

RC for today canceled

New RCs for November 16–18 (10am-6pm)

New RC for November 12 (6am-2pm)

NSF

Mary

Nic

LabPadre

[49]
09.11.2021 B5 thrust section lifted in high bay

S21 nosecone disconnected from crane; work continued

Two forward domes and a booster fwd sleeve (B6, yesterday) at the production site: as well as a Ship common dome and an aft sleeve and two pipes for methane transfer tube

LR11000 (Buckner) assembly at production site near wide bay

Grove GJMK7550 crane moved

Grey crane part delivered to production site as an addition to the old LR11000 crane (extension of the jib)

Grove, Manitowoc RT 9130E-2 crane drove to PPS

Wide bay construction work continued

LR11000 lifted its boom at the production site

Main cable reeving for chopsticks continued; reached draw works but spool has not yet been unwound completely

B4 work at the fwd section

SN20/S20 work at aft section

Apollo robot dog from Boston Dynamics spotted; new arm and SpaceX themed paint

OLS berm werk continued

OLS, IT plumbing lifted

B5 LOX section stacked on thrust/aft section

NOTMAR posted for November 10, Alert notice issued for potential SN20/S20 static fire

NSF

Mary

Nic

LabPadre

[50]
08.11.2021 Main steel cable installation began (unloading from the spool, pulled through the system by the pulling cable)

LR11000 with disassembled boom and counterweights moved to production site

LR11000-X moved; lifted other crane parts on truck (likely for the other LR11000)

OLS Tank farm: hose removed from a shell

Container wall construction at the production site

B5 work in high bay continued

B6 fwd sleeve shown (3-rings, vertical stiffeners, holes for grid fins)

Wide bay construction work continued; first two levels nearing completion

S21 nosecone welding work; nosecone still attached to crane

New robot arm delivered

Crew dragon Endeavour reentry visible over Starbase

RC for November 9 canceled

NSF

Mary

Nic

LabPadre

[51]
07.11.2021 LR11000 disassembly continued; parts moved to production site

S21 in mid bay now 16 rings tall; stacking of tank section complete

Fwd dome sleeve with TPS mounts spotted inside tent 3 (4-rings with lead-ins)

S21 nosecone stacked on nosecone barrel section; TPS tile rows on nosecone are labelled

OLM work continued

Chopsticks: Cable reeving began. Small help cable pulls up the pilote rope that will then pull the main cable through the system.

NSF

Mary

Nic

LabPadre

[52]
06.11.2021 Two Raptor engines with SpongeBob drawings delivered to launch site RC78, RC79?

Wide bay construction work continued

S21 nosecone prepared for lifting, attached to crane

LR11000-X moved

SN20/S20 aft section work continued

OLS, IT: Work continued on the rails for the catch arms; Chopsticks work continued

LR11000 boom lowered, disassembly began, counterweights removed

LR11350 disassembly continued

Unknown Raptor engine delivered to launch site

NSF

Mary

Nic

LabPadre

[53]
05.11.2021 SN20/S20 equalized pressure by venting ambient air; work on it continued

LR11000-X assembly finished; counterweights added; boom and jib lifted

Raptor engines delivered to launch site (unknown number)

OLM elevator completely removed Wide bay construction work continued

Stair sections lifted in high bay

S21 engine section (5-rings, with lead-ins) moved to mid bay; lifted into mid bay

New RCs for November 11, 15 (10am-6pm), 12 (6am-12pm)

LR111350 disassembly continued; cabin and engine sections left launch site

RC58 delivered to launch site

NOTMAR issued for November 9

NSF

Mary

Nic

LabPadre

[54]
04.11.2021 Windy, rainy weather

LN2 and LOX deliveries to OLS tank farm

LR11000-X assembly continued

B4 aft section work continued

Dump trucks off LBJ boulevard

S22 nosecone barrel section; 5 rings tall and 3.6 mm steel according to label!!

Blue Origin lost lawsuit against NASA over HLS lunar lander contract with SpaceX

NSF

Mary

Nic

LabPadre

[55]
03.11.2021 B7? fwd tank #2 spotted

Wide bay construction work continued; more vertical beams (likely for wall attachment) added; first outwards facing beams for (similar to high bay) added

Black booster stand (the one with triangles) shown off Rocket Rd

B2.1 work continued near gate A3 (NSF confirms the other one to be BN2.1)

LR11000-X more parts delivered; assembly continued

RC74 delivered to launch site and unloaded; prepared for installation on B4

LR11350 more parts left launch site

SN20/S20 work on TPS tiles near aft flap

Chopsticks: More conducts installed

QD arm: piece lowered onto it

OLM elevator disassembly began, work looking to slowly conclude

Container was construction at launch site

B4 work on fwd section

RC for November 4 canceled

NSF

Mary

Nic

LabPadre

[56]
02.11.2021 Crane moved back to production site

LR11000-X more parts (counterweights, boom and jib sections) delivered to launch site and unloaded; stacking continued

B4 fwd section worked on

OLS, IT and chopsticks work continued

PPS: More sidings added to staircase segment: two segments moved from PPS to high bay area by SPMT

Starship aft flap aerocover spotted

Booster fwd section outside the tents

Wide bay construction: More beams added

B2.1 testing preparations continued

S21 work in mid bay continued; work platform erected

Raptor engine spotted in scrapyard (unknown SN)

S22 mid-LOX section still outside tents, no TPS tiles attached yet

RC for November 3 canceled

NSF

Mary

Nic

LabPadre

[57]
01.11.2021 RC for today canceled

B2.1 preparation work for testing continued at PPS

Wide bay construction work continued; more beams delivered

PPS: Staircase work continued

S22 common dome section (sleeved, with methane header tank and lead-ins) spotted

S22 mid-LOX section (4-rings): thermal blanketing attached

Chopsticks work continued; linear actuators visible

OLS, IT: Work on chopstick rails

OLM work continued; control panel "COPV load" shown

LR11350 disassembly continued

LR11000 cleaned

FAA environmental review public comment phase now closed

RC for November 2 canceled

New RCs for November 2–4 (10am-6pm) and November 8–10 (10am-6pm)

NSF

Mary

Nic

LabPadre

[58]

October 2021[]

Date Description Source Link
31.10.2021 LR11350 disassembly continued

B4 work continued

Chopsticks work continued

More pipes lifted and installed on OLS, IT

LOX deliveries to OLS tank farm; 50th delivery truck of LOX

Launch site delivery turned around and unloaded at PPS "Atlas Copco"

SN20/S20 work continued, especially in engine area

B2.1 work continued at PPS, work through access hole

NSF

Mary

LabPadre

[59]
30.10.2021 LR11000-X more parts delivered to launch site, ballast unloaded from a truck; assembly continued

Common dome outside tents

S21 nosecone work continued

Unknown Raptor engine moved into tent

S22 mid LOX section spotted outside tent 1

B2.1 work on booster test stand continued

LR11350 "Frankencrane/Kong" disassembly of boom

B4 work on Raptor engines shield (TPS) looks complete [?]

Chopsticks work continued

QD arm work continued

SN20/S20 work around engines continued; all engines have been installed (RVac5, RVac6, RVac7, RC81, RC?, RC?)

S22? aft dome section flipped

R57 delivered to launch site

NSF

Mary

Nic

LabPadre

[60]
29.10.2021 New LR11000 parts in SpaceX custom design delivered to the launch site [to be called LR11000-X on this wiki or some suggested the community name BBC for "big black crane"]

Assembly of LR11000-X began

OLM work continued

Chopsticks work continued, downward facing extension on both arms added

Perlite expansion furnaces shown

Plumbing work on horizontal CH4 tanks at OLS tank farm continued

B4 aft section work continued

SN20/S20 Rvac6 installed, Rvac7 waiting for installation; later Rvac7 installed as well

Wide bay construction picking up the pace, more beams lifted into place

B2.1 work on test stand continued

Booster fwd sleeve and fwd dome in front of tents

NSF

Mary

LabPadre

[61]
28.10.2021 Chopsticks have swung for the first time after the actuators have been installed

Wide bay beams unloaded; at least 5 beams now erected

Nosecone in the scrapyard sliced into pieces

Chopsticks work continued

B4 work continued near common and forward dome, as well as on aft section

SN20/S20 work at engine section continued

Booster test stand has raptor gimbal joints which will attach to B2.1 on each of its RC mounting point

Work on a tent entrance

Hwy4 repair work at production site

Crane mats delivered to production site

B2.1 moved towards booster test stand at PPS by SPMT, lifted and removed from transport stand, lowered onto booster test stand

4-ring barrel section moved to scrap yard

Wide bay construction: more beams lifted, cross-beams began to be added

Rvac6 (label: "SN6")and Rvac7 (label: RV7") moved form production site to SN20/S20 at the launch site; Rvac6 lifted into aft section for first fit check, lowered again

RC for October 29 canceled

NSF

Mary

Nic

LabPadre

[62]
27.10.2021 OLM and OLS, IT work continued

Perlite sacks at OLS tank farm for further insulation

RB33 delivered to launch site [for B4]

B4 Raptor heat shield work continued, the big aerocovers now next to it [RGV]

S21 work continued in mid bay

Booster fwd dome section outside tents [sleeved?]

B5 work in high bay continued

LR11350 ballast lowered; boom lowered later, potentially for the last time

Raptor gimbal joints lifted into booster test stand; these are mounted to hydraulic cylinders which simulate Raptor engine thrust

Wide bay beams continued to be delivered

Standard TFR renewed for November, still 10000 ft

NSF

Mary

Nic

LabPadre

[63]
26.10.2021 RC for today canceled

Booster fwd section spotted outside tents [label B4/B6 fwd dome??] PPS staircase assembly continued

B2.1 test tank work continued

"Dump truck pulls stuck truck carrying crane parts free"

Ship thrust simulator: parts removed

Booster test stand work at PPS

S21 in mid bay at least 7-8 rings tall, work through hatch; mass simulator plate installed

Wide bay construction work continued, new parts (beams) delivered

Crane parts stored at the PPS, some crane parts loaded onto a truck and left boca chica

LN2 truck at PPS

S21 nosecone TPS tiles work continued

Many flatbed trucks waited at Starbase sign

SN20/S20 has now 3 SL and one Rvac engine installed

Chopstick hydraulic actuator lifted for a fit check and lowered back down later

OLS, IT work continued; some crews working at the top of the tower

B4: Insulating foam added around the COPVs and QD plate; work on raptor heat shield (TPS) continued; work con raceway

Crane parts and chopstick stand structure left launch site

OLS tank farm: LOX heat exchangers tested, first venting

RC for October 28 canceled

NSF

Mary

Nic

LabPadre

[64]
25.10.2021 OLS tank farm: LOX deliveries (some from Sanchez site/PPS); Perlite expansion furnaces and hoppers shown in video for first time

SN20/S20 work in engine area continued

B4 work continued

OLS, IT work continued in several areas; cable track (the travelling cable for chopsticks) attache to upper right carriage arm

B6 aft dome on sleeving stand, ready for sleeving

Methane transfer tube for booster moved

Crane rigged for wide bay beams (yellow bigge crane)

Wide bay: more beams lifted

Ship [S22/23?] leg skirt spotted in tent 3, a cutout is visible for the quick disconnect plate

B2.1: parts added to grid fin cutouts

S21 work in mid bay

Chopsticks support structure moved away from launch site

New RCs for October 28 (10am-6pm), 29 (6am-12pm), November 1 (10am-6pm)

NSF

Mary

Nic

LabPadre

[65]
24.10.2021 Booster aft dome lowered onto sleeving stand [B6/B7?]

B2.1 work continued

Chopsticks/Carriage: Large pulley attached (diameter at least as big as a human)

LOX delivered to OLS tank farm

OLS tank farm: piping work towards horizontal tanks continued; now three different pipes visible

SN20/S20 work continued, aft section and in engine area

B4 work continued; TPS installation for Raptor engines continued; some work around COPVs

PPS: Staircase segments assembly continued

S21 nosecone rolled out of tent 3, at least 3 nosecone still inside

Ship fwd dome with label

B9 thrust puck delivered and unloaded, this is the first one for 13 engines (10+3) instead of only 9

Booster methane transfer tube (downcomer) delivered (two parts) [add Dec: not first one; first one see early Oct, likely for B7/B8]

NSF

Mary

LabPadre

[66]
23.10.2021 HLS nosecone began to be scrapped; lowest rings cut off

B2.1 (not same as BN2.1) work continued

RB32 delivered to production site

Ship aft dome sleeve in front of tents

S21 nosecone and nc barrel section still missing some few tiles

Wide bay construction work has continued

B4 and SN20/S20 worked on

Chopsticks/carriage: some minor work

QD arm moved towards tower

Two raptor engines loaded onto truck, likely back to McGregor; on identified as RB2

Catch arms carriage travelling block installed and disconnected from crane (7.49pm)

S21 fwd section stacked on common dome section in mid bay

NSF

Mary

Nic

LabPadre

[67]
22.10.2021 Two Raptor engines delivered to launch site; some left

PPS work on staircase sections continued

Booster aft tank#5 and #3 spotted [B6?, signs look like B4 and B5]

B2.1 work continued

3-ring barrel section outside tent 1

Two RC and one RB engine loaded onto raptor van

B4 work on aft section and engines continued; start of thermal protective cover installation

Plumbing work to new horizontal CH4 tanks at OLS tank farm continued

LR11350 disconnected from chopsticks/carriage which now sit on a jut like part that sticks out from the tower column

PPS: two more staircase segments loaded onto SPMT

Wide bay: first sturctural beam lifted

NASA worm logo removed from HLS mock up

SN20/S20 three RC installed late in the eventing/early next morning

NSF

Mary

Nic

LabPadre

[68]
21.10.2021 Delivery to SoLS tank farm (LN2 tanker)

SN20/S20 work continued

Plumbing attached to new horizontal taks at OLS tank farm

Grove GMK6300L-1 crane (Berry) moved to launch site

B4 work at top continued, as well as in the engine sections (new thermal protection)

Red support structure for chopsticks/carriage disassembled

LR11000 moved from OLS tank farm to landing pad

B2.1 work continued

Wide bay: beams prepared/rigged for assembly

S21 fwd dome section work

B5 aft tank #5 (LOX section, 4-rings, no lead-ins) moved

Header tank panels spotted at the production site

High bay rooftop bar work continued

Raptor 2 engine factory contstruction progress at McGregro [Reagan Beck]

SN20/S20 Static fire #1 (Rvac5) and #2 (Rvac5 and SL raptor)[69], at least 8 tiles lost during fires [see vid 22]

NSF

Mary

Nic

LabPadre

[70]
20.10.2021 Alert notice for today issued, but RC for today canceled

OLS, IT: Single skate removed and reinstalled Carriage arms opened for installation on OLS, IT [unclear when]

Chopsticks/carriage lifted from red structure by LR11350, crane rotated; lowered to correct height, installation on OLS, IT began

B4 new framing around the Raptor engines, possibly part of the new thermal protection system mentioned by Elon Musk

B2.1 work continued

Another hydraulic actuator moved to launch site, possibly for chopsticks

Two stair sections moved from PPS next to high bay

Wide bay construction; beam attached to white/blue Atlas crane (PBI)

NOTMAR for October 21 issued

FAA second public hearing for environmental assessment draft

NSF

Mary

Nic

LabPadre

[71]
19.10.2021 Evaporator at SoLS tank farm in action after SN20/S20 test

New dome on sleeving stand

B2.1 work through hatch outside mid bay

SN16 work/inspection at hatch

S21 nosecone and nc barrel section look nearly ready

Chopsticks and carriage rigged for a test lift; lifted and rigging adjusted for balance

SN20/S20 work around/in aft section

Hydraulic actuator delivered to launch site "rod side proofed, smile"

B4 work on raceway

CH4 horizontal tank (the second one) and cryo tank shell #7 (final one) rolled out to OLS tank farm

Work on GSE2 befor covering it

New RCs for October 21 (5pm-12am), 25, 26 (10am-6pm)

Alert notice issued, but later RC for tonight canceled

NOTMAR issued for SF on October 20

Shell #7 attached to LR11000 and lifted over GSE2 at OLS tank farm; the 8 tanks now complete

NSF

Mary

Nic

LabPadre

[72]
18.10.2021 LR11350 rotated towards carriage/chopsticks

Alert notice issued to Boca Chica residents for possible SN20/S20 static fire today between 4pm-1am (later corrected to 5pm-midnight); NOTMAR issued

Cryo tank shell #8 CH4 [according to label] moved from PPS to OLS tank farm (9:37-10:41), bumpers installed on the bottom inside of the shell, attached to LR11000, lifted and put over GSE8 on the most south western position

New intermittent RC for October 19 (9:30-11:30am)

OLS tank farm work continued, especially on newly delivered horizontal tank

Ship aft dome sleeved [S22?], then removed from sleeving stand

Large methane tank at PPS cleaned

PPS: Staircase work continued

PBI Manitowoc 12000 being readied at the new wide bay area, another white-blue crane already there

Raptor gimbal joints spotted

Rigging work for chopsticks/carriage; attached to LR11350

B4 work continued on its top; hydraulic power unit sled wrapped in plastic, possibly in preparation for installing aerocover

OLS tank farm: venting from ground pipes

SN20/S20 preburner test of Rvac5, vents around nosecone! [vid 19]

SN20/S20 no big apparent damage to TPS, most tiles missing were missing before test [vid19]

FAA first public hearing for environmental assessment draft

NSF

Mary

Nic

LabPadre

[73]
17.10.2021 LR11350 detached from chopsticks

Crane detached from S21 nosecone barrel section

B5 construction in high bay continued

Yellow grove crane RT915OE moved to PPS

Several LOX (yellow label) and LN2 (green label) trucks at PPS

LR11000 moved back to OLS tank farm after having lifted one catch arm to the carriage

Perlite delivered to OLS tank farm

OLS, IT: Carriage linear bearing "skate" lifted onto the tower, reinstallation began; they allow the carriage anch chopsticks to move up and down the tower; likely all skates installed this day; cable carrier [?] installed as well; a wheel spotted below the QD arm [when installed?]

Carriage welding work

B4 work continued in several areas

SN20/S20 work in skirt area

LR11350 more crane counterweights added

One of the two large tanks (for LCH4) moved from PPS to OLS tank farm

LR11000 lifted crew in a basket

OLS tank farm: First ever LOX delivery; at least 4 tankers

SN20/S20 work through upper hatch

Cocoa facility: Mk2 nosecone being dismantled

NSF

Mary

LabPadre

[74]
16.10.2021 Starbase driving tour

The chopsticks are now fully attached to LR11350 only

Grove crane delivered to launch site

NSF

Mary

[75]
15.10.2021 B2.1 [?] hybrid test tank still outside mid bay

Forward dome caps delivered; "NIPPON STEEL Stainless Steel Corporation, Yawata, made in Japan"

Raptor engines that have been moved to production site yesterday were now loaded onto raptor van (RC62, RC72, RC74)

Methane transfer tubes "downcomers" delivered (two)

OLS tank farm work continued

CH4 boil-off buffer (horizontal storage tank at OLS tank farm) constantly venting (likely LN2); "CH4 boiloff goes into buffer tanks, gets slowly condensed in Blu, goes back into buffer tanks, and returns to main storage tanks once depressurized." [The_Denks]

B4 work continued in different areas

SN20/S20 work under aft skirt continued, as well as through top hatch

Wide bay foundation work continued, many I beams ready and moved around

PPS: Booster thrust simulator work continued

Barrel section moved into tent 1

Shift aft dome outside tents

New intermittent RC for October 18 (9.30-11.30am)

LR11000 detached from second catch arm

Two Raptor engines delivered to launch site

NSF

Mary

Nic

LabPadre

[76]
14.10.2021 S22 comm dome sleeve (3-rings) outside of tents

Starship aft dome in a tent [S22?]

Barrel section with TPS tiles attachment points moved around

S21 nosecone and nc barrel section TPS installation continued

I beams unloaded from a flatbed near wide bay foundation

PPS: crane attached to a booster transport stand

New Starship thrust puck spotted at production site

PPS: Work on stairs continued

Manitowoc 12000 crane rolled back to production site

OLM work continued

Plate compactor lifted onto berm (near the tunnel)

Raptor engines removed from B4, 5 engines visible

More perlite sacks delivered to OLS tank farm; work on OLS tank farm piping continued

SN20/S20 work inside aft skirt continued

Booster thrust puck spotted at the ground tracking station

Yellow triangular shaped structure and pipes delivered to production site

RC62, RC72, RC74 moved back to production site

SN20/S20 scrubbed static fire attempt

NSF

Mary

Nic

LabPadre

[77]
13.10.2021 Overpressure notice for today's SN20/S20 static fire attempt issued

B5 first grid fin installed during night; a second one was installed later Assembly of catch/stack arms "chopsticks" and carriage continued

OLS tank farm: work on the pad north of GSE tanks; work on piping continued

Perlite delivered and unloaded at OLS tank farm; "Perlite is an insulating layer between the cryo shell and GSE tank". Kilns at the OLS tank farm expand the material into low density insulation

SN20/S20 work in the aft skirt area ahead of potential static fire

Grove GMK7550 counterweights moved to production site

RC for today cancelled, SN20/S20 static fire NET Thursday

Hybrid test tank moved out of mid bay, NSF calls it B2.1 [confusing]

S21 fwd section in tent 3 TPS tiles installed [also see yesterday]

COPV covers for booster aft section at production site

Header tank panels spotted at production site

Pulley cable spool lifted on to OLS, IT and installed to dead anchor

New RCs for October 18–20 (5pm-12am)

Today's RC cancelled

NOTMAR posted for October 14 for potential SN20/S20 static fire; Alert notice issued

NSF

Mary

Nic

LabPadre

[78]
12.10.2021 Both catching arms installed, main pin fully lowered at about 2:16 am

Raptor engines moved from launch to production site

B5 stacking continued; CH4 tank now 13 rings tall and thus completely stacked

S21 nosecone TPS work continued

S21? nosecone barrel section (the one that has been standing there since a long time) TPS installation

RB11 and RB27 loaded onto raptor van at production site

Tent 3: 4-ring barrel section with a lot of TPS tiles attached [vid 13 labelled S21 fwd section]

Wide bay foundation work continued; new blue crane on the site

Chopstick work continued

Dirt moved around at launch site, possibly for a berm?

B4 work on aft section

SN20/S20 work continued on aft section, Rvac5 installation completed

B5 first grid fin installed

NOTMAR posted for October 13 (5pm-12am)

NSF

Mary

Nic

LabPadre

[79]
11.10.2021 Second chopstick (catch/stack arm) moved from its construction area on the landing pad towards the OLS

More Raptor engines removed from B4, e.g. RB27 visible; furthermore RB11 and RC79 and another with invisible SN

Wide bay foundation work continued

More high bay windows ready for installation

S21 nosecone TPS tiles installation has progressed

3-ring barrel section near sleeving stand

Booster aft section with installed COPVs spotted in a fabrication tent [B6?]

Braided hose delivered to production site

S22 [sic! it's S21] in mid bay likely 6-7 rings tall

Catch/stack arm "chopstick" #2 attached to LR11000, lifted and rotated, moved into position next to the first arm on the red structure for installation on carriage system ahead of lifting on tower

Rigging on cables between arm 1 and LR11350 adjusted in order to level it

Two out of likely 12 skates/linear bearing lifted to OLS, IT (column facing the OLM); the carriage will be installed on them; they will allow the carriage to slide up and down the tower

Rvac5 engine installed on SN20/S20

SoLS/landing pad earth and concrete work continued

16:42:29 the second skate fell down from the tower; scaffolding damaged

RC for October 12 cancelled

NASA document: explaining how they intend to use the WB-57 aircraft for monitoring Starship re-entry, they target a reentry observation opportunity near March 2022

Chopsticks moved into position inside carriage near midnight

NSF

Mary

Nic

LabPadre

[80]
10.10.2021 Raptors delivered to launch site (Rvac and Sea level/RC)

Rvac6 spotted in a production tent

PPS: Staircase production continued

S22 common dome section in tent 1 (3-ring)

Single ring in front of tent (the one with a hole spotted last week)

Ring section collapsed in high winds

Green crane parts? delivered to production site, origin unknown

Cable carrier moved to launch site; possibly for the chopsticks "as it allows cables to neatly connect to moving parts", "provides power, data and hydraulics to the catching arms"

OLS tank farm work continued, especially on piping

Chopsticks: both arms will be attached with the same pin; second arm moved towards carriage

NSF

Mary

Nic

LabPadre

[81]
09.10.2021 B5 stacking continued; 3 out of 3 sections stacked

OLS tank farm: more plumbing installed near GSE2; new equipment delivered that looks like the one that has been installed yesterday

Catch/stack arms "Chopsticks" prepared to lifted, moved under LR11350 and attached to it; lifted and flipped/rotated into correct position; lowered adjacent to carriage system

OLS, IT work continued

More Raptor engines loaded onto truck

LR11000 crane began to move away from OLS tank farm, towards landing pad, likely to help with chopstick installation

Barrel section with TPS tiles (some empty spots) (3-rings with lead-ins) hooked to crane in front of mid bay, possibly for S21?; another 4-ring section in front of mid bay

Stand moved around at production site

Wide bay foundation work continued

S22 cmn dome section seen

S21 common dome moved into mid bay

Steel cladding added to a container wall

NSF

Mary

Nic

LabPadre

[82]
08.10.2021 S21 nosecone TPS heat shield tiles installation continued, red tape added to the top, some tape on the flap TPS tiles

Starship aerocover spotted, likely for aft flap

Deliveries to production site

High bay rooftop bar work continued

Ground fabrication building expansion work continued

Wide bay foundation work continued, pins/points for columns spotted

Starship thrust simulator with six hydraulic rams at PPS?

PPS: Ship aft skirt test article worked on again

OLS tank farm: New equipment lifted into place near the eastern LOX subcoolers; welding work on some pipes

Raptor engines loaded onto truck at launch site, RC58, RB26 visible; at least to other on pad

Crane basket moved at production site

Earth work at the launch site

OLS, IT: QD arm operational under own power for the first time

NSF

Mary

Nic

LabPadre

[83]
07.10.2021 LR11350 disconnected from carriage system on red stand; work on it continued

Loadspreader attached to LR11000

Catch/stack arms "Chopsticks" work continued

LN2? delivered to OLS tank farm

OLS tank farm: work on/around the ground piping

GSE8 tank rolled out to OLS tank farm, attached to LR11000 crane, lifted and placed onto final empty stand at the most south-western slot; only two shells now remaining to be rolled out

Pin (likely at the connection point to the chopsticks) placed into carriage for fit check, then removed

OLS, IT: work continued, more pipes lifted into place

Concrete forms for new wide bay delivered

PPS: funny looking black tank rolled around

SN2 shown behind scrapyard

S21 nosecone work continued; progress on TPS installation marginal; as well as on barrel section

New ship fwd dome on sleeving stand [the one seen on October 5?]

Work on high bay rooftob (bar) continued

Wide bay foundation work continued

SPMT spreader bars moved to build site

RC for October 11 cancelled

NSF

Mary

Nic

LabPadre

[84]
06.10.2021 New booster thrust puck for 13 engines [B5/B6?] lifted from truck

S22 cmn dome being worked on on the sleeving stand

B5? grid fin moved into tent 1

Booster thrust puck moved out of tent 2, then moved back into the tent again

Ship aft dome moved into tent 3

S22 cmn "comm" dome sleeve (3-ring) placed on a stand

B5 fwd section stacked in high bay (currently 6 rings?)

Second huge propellant storage tank delivered to PPS

S22 cmn dome section sleeved

Single ring section outside tents (near fwd dome), hole cut into the side

Delivery of different parts to production site

B5 fwd CH4 tank section now likely 9 rings tall; more sections ready

Wide bay foundation work continued

PPS: Stair enclosing work continued

OLM work continued

OLS, IT: welding work

Carriage system for chopsticks attached to LR11350, then lifted and flipped to a vertical position; then lifted higher, crane moved forward and the carriage system was placed on the red stand/hurdle structure [great closeup]

RCs for October 7 and 8 cancelled, new RCs for OCtober 12-14 (5pm-12am) and for October 7 (11am-1pm)

NSF

Mary

Nic

LabPadre

[85]
05.10.2021 OLS tank farm: Work on GSE2 and ground piping continued; grey horizontal tank lowered into place behind the west LOX subcoolers (near the white tanks that have been added recently)

OLM work continued, painting

OLS, IT work continued, including on the QD arm (there is a work platform on the arm)

B4 work continued, especially around the aft section with the QD ports and COPVs

Concrete poured south of landing site

New red structure (two big "hurdles") assembled between OLM and OLS tank farm bunker, look like a temporary structure; a tall one and a smaller one

LN2 delivered to SoLS tank farm

Booster thrust puck with old 9 engine design shown

PPS: Stair construction continued with walls beginning to be added

PPS: Concrete work

Wide bay work continued with concrete poured into place for foundation

Barrel section near tent disconnected from a crane

B5 fwd #4 section spotted (4-ring with lead-ins)

B6 fwd #2 section spotted (3-ring "triple stack")

B6 aft #5 section spotted (4-ring, "4.0mm")

S22 cmn dome on sleeving stand; a fwd dome in front of it

B5 grid fins shown

High bay work continued with more windows being lifted and installed

Mid bay: Hybrid booster-ship tank construction continued; B fwd section and B aft sleeve with S thrust puck

Booster fwd section spotted in a tent [B5/B6?]

Heat exchanger place next to ground fabrication building

Nosecone [S21?] work in tent 3 continued, TPS tiles being attached

Steel cladding added to a container wall

Huge Liquid Methane tank delivered to Starbase on two SPMTs led by a truck, accompanied by a small convoy; power lines had to be removed in order to let it pass [to PPS]

Booster [B5/B6?] thrust puck with 13 engine mounts delivered for booster with new 33 engine design (3, 10, 20 vs 1, 8, 20)

NSF

Mary

Nic

LabPadre

[86]
04.10.2021 Deliveries to production site

B5? fwd section prepared for stacking, attached to crane

Ground fabrication building addition worked on

High bay rooftop bar work continued

Booster thrust simulation stand work at PPS, possibly preparing transport

Booster 3-ring fwd section [thought to be B5?] stacked on the booster sleeve with ship thrust puck for unknown reason

OLM work continued, especially around booster QD system

OLS, IT: work continued; work on the possible carriage system rails

B4 work continued; workers on top of the fwd dome; work on one of the long pipes (tightening screws); inspection

OLS tank farm: work via crane basket lifted by LR11000

The small diameter tank in high bay could be, together with the 33? hole ring segment, part of a "header tank" or separate tank for the booster that would be used for boost back and landing due to slosh (WAI)

NSF

Mary

Nic

LabPadre

Wai

[87]
03.10.2021 Two large crates loaded onto truck

OLM work continued

LR11350 crane shortened; later raised in the new configuration without jib but still with power boom

OLS tank farm: work at the top of GSE2 tank continued

SN20/S20 work in aft section

B4 worked on in several areas with man lift goint up to the top, orange "AVI" bags near the top of the line

Catch/stack arms "chopsticks" and carriage system work continued

LN2 delivered to SoLS tank farm

GSE8 still waiting in front mid bay for roll out

LR11000 disconnected from Shell #3

SN20/S20 aft flaps opened during flap test [vid 04]

OLS, IT: welding work [vid 04]

NSF

Mary

Nic

LabPadre

[88]
02.10.2021 Booster thrust sleeve (3-ring) with ship thrust puck spotted, unclear use

New Liebherr LTR1220 crane spotted at production site

Concrete forms used for wider high bay/wide bay shown

Tubular part first spotted on September 19 still at production site

S21 4-ring section in mid bay waiting for stacking to begin

Fwd dome spotted inside tent 1

Delivery of a cabin and a ring segment with 33 holes

PPS: currently seven stair segments nearing completion

Rigging attached to a crane (GTC-900 Mantis)

OLM work continued

B4 work continued with man lifts up to the top; work on the center lines

OLS tank farm: Shell #3 lifted by LR11000 and placed over GSE6; the most southwestern stand now empty for GSE8; work on GSE2 strengtheners continued

Booster thrust puck delivered [B5?, B6?]

NSF

Mary

Nic

LabPadre

2Yky0pPk
01.10.2021 SN20/S20 venting

LR11350 disassembly continued

SN20/S20 thrust ram removed from engine section/pad B

RB29, RB30, RC80 engines delivered to production site and unloaded

Ship fwd section spotted in front of tents (4-ring)

Catch/stack arms "chopsticks" and carriage system work continued

OLS tank farm: Work inside shells #5 and #6 [?]

Ship [S21?] cmn dome with TPS tiles attachment points and CH4 header tank spotted

S21 nosecone work continued, second aft flap installed

Crane counterweights delivered to production site

RC for October 4 cancelled

New RCs for October 2 (12.01-1am, intermittent), 07 (5pm-12am), 08 (6-12pm), 11 (5pm-12am)

NSF

Mary

LabPadre

[89]

September 2021[]

Date Description Source Link
30.09.2021 OLS, IT work continued

OLM work continued

LN2 delivery to OLS tank farm

OLS tank farm: GSE2 tank work continued; work in shell #5

LR11350 "Frankencrane/Bluto" lowered; likely needed for a bridge installation somewhere else

Insulated piping delivered to launch site "DXS1 cryoproof XC, Orbital"

Dog walking around

Bearings installed to Catch/stack arms "chopsticks" for transport; lines/pipes installed to carriage system

B4 work around the skirt area continued and hull

PPS: Stair work continued

B5 fwd dome section moved into high bay

B5 grid fins ready for installation

S21 nosecone and nosecone barrel section TPS tiles installation; first fwd flap installted to nosecone

B6 cmn dome section (3-ring with stiffeners and hole) spotted

RC for today cancelled

FAA: Public comment period for environmental assessment extended to November 1, Public hearing moved to October 18 and 20 at 5pm

NSF

Mary

LabPadre

[90]
29.09.2021 New RCs for September 30 (5pm-12am), October 1 (6am-12pm), October 4 (5pm-12am)

OLM work continued; it is suggested that the OL platform includes a system of 20 QD systems that will absorb the outer booster engine chill so the cold vents don't damage the hold down clamps and other structures

OLS tank farm: Ventilation hose coming out of Shell #5, workers inside

Catch/stack arms "Chopsticks" and carriage system work continued

SN20/S20 work continued ahead of testing

LOX delivery to SoLS tank farm

LN2 delivery to OLS tank farm

Shipping container painted black

B5? fwd section (3-rings with stiffeners) outside high bay

Large black pipe outside high bay

Barrel section (3-rings with lead-ins) moved out of high bay

Concrete trucks at PPS

S21 Nosecone TPS tiles installation continued inside tent 3

B5 cmn dome section worked on in high bay; LOX section is hooked to bridge crane

High bay rooftop work continued

New barrel section with tile attachment points spotted

Work on structure behind mid bay continued

SN20/S20 cryo proof test

New future ship/booster test stand foundation spotted near the current location of B4

B5: Two grid fins spotted

NSF

Mary

Nic

LabPadre

RGV

[91]
28.09.2021 S21 nosecone TPS tiles installation continued

3 Raptor engines loaded onto truck (two gimbaling, one fix)

Wide high bay "Wide bay" foundation work continued; concrete poured

Work on the five stairs at PPS continued

Cement truck cleaned at cleaning facility

Toy trucks spotted on flatbed

OLM construction continued

RCs for today and September 29 changed to 3pm-12am

SN20/S20 testing scrubbed

Michael Sheetz: SpaceX is working with Dr. Saul Perlmutter at UC Berkeley on a space based telescope that would be launched by Starship. They could launch satellites that have 10 times the resolution of the Hubble.

RC for today canceled

NSF

Mary

Nic

LabPadre

Michael Sheetz

[92]
27.09.2021 Crew raised in a basket over cryo shells at OLS tank farm

LR11000 still attached to shell #3 at OLS tank farm

OLM work continued

OLS tank farm: LN2 delivery continued; Shell #1 huge venting

B4 work at upper LOX tank

OLM work continued

SN20/S20 prepared for testing; thrust simulator has been installed earlier; work around the quick disconnect fitting

Catch/stack arms work continued

High bay glass panel installation and rooftop work continued

Wide high bay foundation work continued

Rig moved

Possible methane transfer tube "downcomer" delivered

Barrel section with lead-ins [S21?] spotted in mid bay

Welding robot delivered

SN20/S20 pneumatic (ambient) proof test (some TPS tiles lost) and cryo proof test

10000 ft TFR extended for October

NSF

Mary

Nic

LabPadre

[93]
26.09.2021 S21 aft section outside tents (5 rings and lead-ins; thrust and skirt sections)

S21 nosecone TPS installation continued

B5 fwd #4 section (4-ring and lead-ins) spotted

S21 cmn "comm" dome section (3-ring) spotted; previously slated for S22

Catch/stack arms "chopsticks" and carriage system work continued

LN2 deliveries to OLS tank farm continued

B4 rolled away from OLM

SN20/S20 worked on

LOX delivery to SoLS tank farm

High bay: more class panels installed at rooftop bar

LR11000 detached from Shell #5 at OLS tank farm; attached to Shell #3

NSF

Mary

LabPadre

[94]
25.09.2021 Grove GMK 7550 crane moved to launch site; extra parts on SPMT

PPS: stair production continued

Dome sleeving stand hooked to crane

Methane header tank outside tents for weeks now

GSE8 seems to be more or less ready for roll out

LR11350 and load spreader attached to B4

Two horizontal white tanks transported to OLS by two SPMTs; installed at OLS tank farm, south from GSE tanks and shells

B5? fwd section inside production tent spotted, with stringers (vertical supports)

Catch/stack arms work continued

B4 lifted off from the OLM/pad by LR11350, likely not to damage the booster during installation of catch/stack arms on OLS, IT; carefully placed onto booster stand

Common dome section flipped [?]

LR11350 detached from B4

NSF

Mary

Nic

LabPadre

[95]
24.09.2021 S21 barrel sections with TPS tiles attachement in progress spotted

Blue booster COPV cover [B4/B5?] spotted

Thrust puck shucker (center engine thrust simulator) rolled out to launch site

B4 workers at the top

RC for today cancelled

Booster stand rolled out to launch site for B4

Cryo tank shell #5 lifted at 10.35am and put over GSE1 by LR11000; touched ground at 11.15am

RC for Monday changed to 3pm-12am

S21 nosecone TPS installation continued in tent

RVac puck shucking equipment for SN20/S20 returned to launch site, installed under Ship on test stand B, with center engine thrust pucker

LR11350 lifted a loadspreader towards B4 ahead of destacking from OLM

Catch/stack arms "Chopsticks" and carriage work contineud

Large pipe spotted in front of high bay [B5 downcomer?]

A small diameter tank spotted in high bay next to B5

B5 lifted in high bay to facilitate further stacking operations [vid 25]

NSF

Mary

LabPadre

Starship Gazer

[96]
23.09.2021 SN20/S20: cryo pipes installed to test stand [?]

S21 fwd dome sleeved

S21 fwd flaps spotted

S21 4-ring barrel section with TPS blankets spotted

OLM work continued, more venting from GSE5/#1

QD arm extension lifted by LR11350 and installed on OLS, IT by 12.30 pm

Catch/stack arms and carriage system work continued

PPS: stair construction continued

Deliveries at production site

Foundation work for wide high bay continued, rebar laid

LN2 deliveries from PPS to OLS tank farm

PPS: Crane attached to the center engine thrust simulator, which uses hydraulic rams to simulate Raptor engine thrust during proof tests

SN17 aft dome scrapping continued

Cryo tank shell #5 lifted to remove the SPMTs; SPMTs moved back to production site

OLS tank farm: Cryo test at around 9.20 pm

QD arm extension unhooked from LR11350

NSF

Mary

LabPadre

RGV

[97]
22.09.2021 GSE8 rolled out of mid bay

RC for today cancelled

New RCs for 27–29 September (5-11pm)

S21 fwd dome on sleeving stand, 4-ring barrel section connected to crane

LN2 deliveries to OLS tank farm continued

OLS tank farm venting: testing for first time; GSE5/#1 (LOX) tank tested with nitrogen (cryo proof test?)

Deliveries to launch site

Catch/stack arms work continued

OLM: flexible feeding pipes installed to quick disconnect system

SN17 aft dome scrapping continued: dome cut out

Foundation work for wider high bay continued

PPS: nitrogen production for OLS tank farm [?]

NSF

Mary LabPadre

[98]
21.09.2021 S21 nosecone receiving thermal blankets ahead of TPS tile installation

S21 mid LOX section with lead-ins and a lot of TPS tiles installed spotted

QD arm extension attached to LR11350 and another crane and flipped upright

Many deliveries to launch site: red steel parts and helium

Unused nosecone next to scrapyard likely to be scrapped

B4/B5/B6?? fwd dome sleeve spotted (3-ring with strengthening/enforcement)

B4/B5/B6?? aft tank #3 segment spotted (4-ring)

Delivery of some red equipment to production site

Black pipe sticking out of high bay

The columns wrapped in blue sheets now called "industrial columns for chemical processes" [the ones delivered on and around July 19?]

PPS: stairs being built within grey T-bar structure; at least four under construction

CH4 delivery to propellant plant (PPS)

Stormy weather arrived

Catch/stack arms and carriage system work continued as rainfall began

SoLS work; all available space used for storage and work

SN17 thrust section at scrap yard, not looking very good

GSE5 LOX tank venting; likely cryo proof test performed with LN2

NSF

Mary

Nic

LabPadre

[99]
20.09.2021 More LN2 deliveries for OLS tank farm

New intermittent RC for today (9-10:30am) QD arm extension moved to launch site, arrived at 9:50 am

Load spreader from LR11000 attached to cryo tank shell #5 at 10:40am (will be lifted over GSE1)

RC for September 21 cancelled

GSE1 bottom hatch closed as well and scaffolding removed

Catch/stack arms and carriage system work continued; parts painted black

Red blocks with cross beams delivered to launch site

GSE4 modifications continued

Unused nosecone at production site, some TPS tiles have been installed

Foundation work for new wider high bay continued, SN17 aft section (with thrust dome & thrust puck from inside) visible at scrapyard

GSE8 still in mid bay, reaedy to roll out soon, pipes have been installed

Fwd flap aerocover with TPS tiles attachment points visible spotted; different types of pins/points: some with a round head, some with a pointed head

Unknown, long rusty tube remained at production site

NSF

Mary

Nic LabPadre

[100]
19.09.2021 OLS tank farm: LN2 (liquid nitrogen) delivered!! [at least three trucks], cryo fluid moved through the pipes

OLS tank farm: GSE2 work continued

B4: RC67 continued to be removed (raptor installation platform has been used for first time); returned to production site

Catch/stack arms and their carriage system work continued

RC64 delivered to launch site; installed on B4 via installation platform and Tesco Hi-Lift later (11.25am)

SN20/S20 work under aft section

Nosecone with TPS attachment points in tent 3

Unknown strcuture (some sort of long pipe) spotted in front of high bay

Remedios Rd still closed [?]

Rvac engine moved at production site

Ship cmn dome still on sleeving stand

Rvac and another Raptor engine moved back to launch site

OLM: cryo hose attached as part of QD system

B5 stacking continued, now 20 rings tall LOX section

NSF

Mary

LabPadre

[101]
18.09.2021 Concrete poured for new wider high bay

SN17 thrust dome section being scrapped

GSE4 had a smaller grey vertical tank attached to its side

Ship [S21?] aerocover delivered

B5 stacking continued; 16 rings tall and a new 4-ring segment prepared in high bay

Ship cmn dome on sleeving stand

OLS tank farm: GSE1 and GSE2 work continued

OLM work continued

Catch/stack arms "chopsticks" work continued

SPMT arrived at launch site

Starship 4-ring barrel section spotted with TPS mounts and white covering [what's the name for it?]

B4: Raptor engine RC67 removed

Temporary RC of Remedios Rd due to "small tank testing" from 12pm to 12am [vid 19]

NSF

Mary

LabPadre

[102]
17.09.2021 B5 fwd dome moved into production tent; stacking of LOX section continued, now 16 rings tall

Methane transfer tube [S21?]delivered to production site (downcomer)

Cryo tank shell #5 rolled to the launch site [according to label slated for GSE1, LN2]

Possible raptor installation platform (stair tower) rolled out to launch site together with shell #5

OLS, IT: hardware lowered from the top of the tower; LR11350 auxiliary hoist seems to be operational again

OLM work continued

Catch/stack arms (chopstick) and carriage work continued; big rail installed on one of the arms

Possible QD arm extension work continued; more lines and cables have been installed

Two new stair towers under construction at PPS?

GSE4 work at PPS continued; likely new adapters installed on the top of the dome

SN20/S20 work continued (access hatch open, work inside)

FAA: draft environment assessment for starship/superheavy launches from Starbase. Public comment period ends at October 18

NSF

Mary

LabPadre

[103]
16.09.2021 Possible QD arm extension work continued

High bay rooftop bar construction continued

Grove RT 913 OE-2 crane moved down hwy4

B5 stacking in high bay; now at least 12 rings [?] tall LOX section

Deliveries to production site; aerocovers for new Starship delivered [S21?]

B4 and OLM intense work continued

3-ring barrel section moved outside the tents

New grey T-bar structure with stairs assembled at PPS

Lift placed into a 4-ring barrel section

Foundation work for wider high bay continued

Nosecone with TPS tile attachment points spotted inside tent 3

GSE8 work in mid bay continued

GSE8 unused fwd dome (2-ring and scrapped dome) moved outside on a stand (it was seen inside the tent at the beginning of the month)

Roll of steel cable delivered

SN20/S20 work inside the aft section

OLS tank farm: GSE1 hatch closed [actually earlier], GSE2 hatch closed too

Catch/stack arms (incl carriage) work continued

New intermittent RC for September 17 (9.30-11.30am)

SpaceX McGregor: Now 5 Raptor test stand bays available; foundations for new Raptor 2 factory spotted

NSF

Mary

Nic

LabPadre

Chris Bergin

[104]
15.09.2021 Deliveries to production site

OLM work continued

OLS, IT work continued (as every day; a lot of pipes have been installed)

B4 prepared for testing

OLS tank farm: some work on GSE bunker

Catch/stack arms work continued; third and fourth carriage system extension has been added

SN20/S20 work continued; manlifts up at access hatch; TPS work continued as well, some markings and missing tiles in the aft area; Raptor engine installation

B5 stacking in high bay continued; now apparently 12 rings tall

Possible QD arm extension work continued

PPS: GSE4 test tank worked on at the top

Foundation work for new wider high bay continued; much rebar and concrete plates prepared

New nosecones spotted in tent 3

GSE8 now fully stacked in mid bay, pipe installation continued

RC for September 17 canceled

New RCs for September 22, 23 (5-11pm), 24 (6am-9pm)

NSF

Mary

Nic

LabPadre

[105]
14.09.2021 SN20/S20 hatch opened for work; TPS tiles looking nearly fully repaired

LR11350 crane worked on, taking advantage of the storm; lifted again later

Carriage system for "Chopsticks" (stack/catch arms) work continued

Coil of stainless steel delivered

Possible QD arm extension work continued, other side received some sort of cap (instead of adapter) as well

Ground fabrication building expansion work continued

GSE8 tank aft dome section (dome+3-ring sleeve) flipped

B5 stacking in high bay seems to have continued (another LOX tank section?)

GSE8 tank in mid bay: more pipes installed

Foundation work for new wider high bay continued

Barrel section with TPS tile attachment points in scrapyard

B5 fwd tank section #2 (3-ring stack) in front of tents

GSE8 aft section moved towards mid bay; later hooked to crane outside mid bay and lifted into it for final stacking

S21 (potentially?) cmn dome and a methane header tank spotted

S21 cmn dome sleeve (4-ring section) spotted

B5 fwd dome sleeve moved (with dome)

S21? cmn dome has been placed on sleeving stand

OLS tank farm: GSE1 access hatch closed after 4 month of work

NSF

Mary

Nic

LabPadre

[106]
13.09.2021 Tropical storm Nicholas impacted Boca Chica

RC for public safety during storm

LR11350 has been lowered, possibly to anticipated high winds [but not LR11000]

Booster transport stand shown in vid

Barrel sections at production site: some are likely for B5

Possible QD arm extension work continued, adapter [?] added on one side

B5 cmn dome section and aft #2 section stacked in high bay by bridge crane; now likely 8 rings tall [actually already yesterday]

Robot inspected a barrel section in a tent

OLS tank farm: work continued; GSE1 and GSE2 access hatches still open

New RCs for September 17 (6am-12pm), 20, 21 (5-11pm)

New intermittent RC for September 14 (3-5pm)

NSF

Mary

Nic

LabPadre

[107]
12.09.2021 Catch/stacking arm work continued overnight and during the day

OLS, IT: work continued overnight

B5 thrust dome sleeve flipped at 2:01am

B5 fwd section now sleeved, put on a stand

The extended arms (U+L shapes) now being called carriage system by NSF; according to NSF, the chopsticks will be attached to the carriage

Possible QD arm extension work continued, more lines installed, together with some pneumatics

B6 cmn dome sleeve spotted (4-ring section)

Old nosecone spotted outside of tents, may be scrapped soon

B4 and OLM work continued, QD system has been retracted

SN20/S20 TPS tiles work continued; hatch was closed

B5 cmn dome section and aft #2 section stacked in high bay by bridge crane; now 8 rings tall

NSF

Nic LabPadre

[108]
11.09.2021 B5 fwd dome sleeved with 3-ring (enforced) section

Robotic welders spotted on a flatbed

Possible QD arm extension work continued; many lines and pipes have now been installed on it

Raptor engines [Big chongus and FULL SEND] delivered to production site

GSE8 work in mid bay continued

Foundation work for new wider high bay continued

Work on nosecones in tent 3

Loadspreader moved down Remedios ave

SN20/S20 work on TPS tiles seems quite complete by now, a few missing on the top of the nosecone, especially around the crane attachment points

Scaffolding stored and staged at launch site

New claw arms spotted, yet unclear if these are for catch system or QD arm [u-shaped pieces added to one of the L-shaped structures near the catch arms]

Work on stack/catch arms continued

S22 cmn dome sleeve has apparently been spotted [L2?]

B4 and LR11350 detached

NSF

Nic

LabPadre

Marcus House

[109]
10.09.2021 Rvac engine arrived at launch site at 1:36 am; fitted on SN20/S20 at 4:22 am

Liquid nitrogen truck at PPS again

Foundation and earth work (excavations) for new wider high bay continued

SN6 aft dome scrapping continued

GSE8 work in mid bay continued; hooked to crane; outside pipes still to be installed

Possible QD arm extension work continued

B5 fwd dome sleeve flipped at 9:16 am

B5 fwd dome placed on sleeving stand [B5 fwd dome sleeve right behind the yellow crane in the video]

B5 cmn dome moved into high bay

OLS, tank farm: GSE cryo tank shell #6 lifted at 9:54 am, placed over GSE7 at 10:47 am; red protective balloons used during stacking process

B4 and OLM work continued

Unknown equipment left launch site

SPMT with a black ring at the OLS tank farm

4th perlite kiln delivered to launch site

NSF

Stephen

LabPadre

[110]
09.09.2021 Liquid nitrogen delivery to PPS continued (at the PPS, there are two big and one smaller horizontal white tank next to the refinery)

PPS: Work on prop prod plant continued; also, new storage areas are being built under the solar panels next to hwy4

Foundation work for new wider high bay continued; rebar being laid and concrete poured; in the background SN6 aft dome (4-ring barrel section with dome) lied around and being scrapped, looking very damaged

SN2 work being done (was a test tank, now acting as a water tank)

Possible QD arm extension work continued

OLS tank farm: work on GSE1, GSE2 and GSE7, where LR11000 lifted a work platform

Catch and stack arms work continued

B4 and OLM work continued

OLM; earlier this month, brackets have been attached to a leg of the OLM, similar brackets on another leg were used for water pipes

GSE pipes lifted into place at launch site near landing pad [?], pieces of insulated pipes being connected

OLM: Quick disconnect extended towards booster at 10:11 am

RC for September 10 canceled

New intermittent RC for September 13 (9-11am)

NSF

Stephen

Nic

[111]
08.09.2021 SN20/S20 damaged TPS tiles replacement continued, most marked tiles have been replaced or repaired; work in the engine bay

Catch/stack arm work continued; pneumatic or hydraulic lines have been installed (they will likely control small actuators along the arm)

Foundation work for new wider high bay continued

Liquid nitrogen transfer at PPS

GSE8 work in mid bay continued

Work on possible QD arm extension continued

B4 lifted onto OLM/platform by LR11350 (following outer engines identified: RB12, RB18, RB15, RB17, RB3, RB6, RB2 RB27?, RB4, RB20, RB5, RB9, [RB25?, RB26?], RB19, RB21, RB24, RB11, RB12); touch down at around 11:52 am; secured onto platform

OLS tank farm: GSE7 work through work platform lifted by LR11000

OLS, IT: tower work continued at several points

SN20/S20 work continued in several areas

NSF

Stephen

Nic

LabPadre

[112]
07.09.2021 B5 aft dome sleeved early in the morning

B4 was removed from bridge crane in high bay at 1:02 am

B4 rolled back to launch site; (roll out started at 8:04 am, hwy4 at 8:18, arrived at launch site at 9:34 am)all 29 Raptor engines appear to have been installed; but there are no thermal insulation coverings around the engines

B4 hooked to LR11350 crane

GSE8 fwd dome (sleeved) hooked to crane; moved to mid bay and stacked onto the rest of the current stack

OLM work continued

SN20/S20 work on TPS tiles continued; coloured labels slowly getting less

Foundation/earth work for new wider high bay continued

NSF

Stephen

Nic

LabPadre

[113]
06.09.2021 Work on Raptor engine at launch site ahead of installation on SN20/S20

SN20/S20 work near/through access hatch

Booster [B5?] aft dome ready for sleeving on the stand

Barrel sections with TPS tiles attachment studs spotted

Possible QD arm extionson work continued

B4 work in high bay continued

SPMT moved towards high bay/B4 for transporting it to launch site later

Cryo tanker truck at PPS; venting from the huge horizontal tanks

B5 aft dome barrel section ready for sleeving; flipped at 2:47 pm

GSE8 in mid bay

Foundation/earth work for new, wider high bay continued

SN20/S20 Raptor engines being installed (RSL); work on TPS tiles continued, now blue and turquoise markings appeared

Catch arm work continued

OLS tank farm: GSE1 work continued (this tank will hold liquid nitrogen, LN2)

Engine driven welders loaded onto a truck

NSF

Nic

Stephen

LabPadre

[114]
05.09.2021 SN20/S20 work under skirt ahead of Raptor installation

SN20/S20 TPS tiles replacement continued

Catch arm work continued

Delivery of huge brown pipes at production site

B5? dome section (4-ring) prepared for flipping

B4 work in high bay continued

NSF

Stephen

LabPadre

[115]
04.09.2021 SN20/S20 work on aft section (manlifts going up under skirt) continued as well as on TPS tiles; more work through the access port

Catch arm work continued

OLM work continued

Compressed gas tube moved into position at OLS tank farm (bunker area) (typically used for helium or nitrogen storage)

OLS tank farm: GSE tank work continued (on GSE1)

Foundation/earth work for new "wider" high bay continued

Old flap storage shown, likely a flap for SN17 spotted

Raptor engine unhooked in one of the tents

QD arm extension work continued

B4 work at its aft area in high bay

OLS, IT: work continued

3 Raptor center engines delivered to production [sic!, launch] site [vid 05]; identified as RSN73, RSN78, RSN69

NSF

Stephen

Nic

LabPadre

[116]
03.09.2021 SN20/S20 work continued

OLM/platform work continued

B4 work in high bay continued

Cryo tank shell #6 rolled out to OLS tank farm (to be put over GSE7) and arrived at 9:38 am, now three remaining shells at PPS; load spreader and LR11000 attached to shell #6 at around 10:30 am

Barrel section with access port spotted in a tent

Foundation and earth work for new "wider" high bay continued

Delivery to production site

The possible QD arm extension begins to take shape, seems to get some sort of gripping mechanism, likely to stabilise the booster/ship on the launch pad

Unknown fwd dome spotted, parts of top appear to have been cut off

New intermittent RC for September 10 (9:30-11:30am)

NSF

Nic

LabPadre

[117]
02.09.2021 OLM work continued during the night; a lot of welding

SN20/S20 TPS tiles work continued

Barrel section with unusual reinforcment on middle ring (3-ring with lead-ins) spotted in tent

New structure possibly for QD arm extension (or catch arm segment) worked on

B5? aft dome spotted

GSE8 fwd dome put on sleeving stand and later sleeved with a 2-ring barrel section

B4 still in high bay, work looks rather finished

Cryo tank shell #7 unhooked from yellow crane, now ready for transport

New high structure being built at production site; it could be a Raptor installation platform

LTM 1350–6.1 packed up for return after it helped installation of QD-arm on OLS, IT

Foundation/earth work for new "wider" high bay continued

GSE8 tank now identified in mid bay

Tent 3: nosecone in production with an aerocover, this might be a test as usually the flap is installed first

QD arm work on OLS, IT continued

SN20/S20 prepared for upcoming cryo tests

Catch arms (also used for stacking Starship) work continued

New intermittent RC for September 7 (7:30-11:30am)

OLS tank farm: GSE cryo shell #1 (most north-eastern) fully filled with Perlite insulation, lines removed [????]

NSF

Mary

Nic

LabPadre

[118]
01.09.2021 GSE7 has been placed next to GSE2 by LR11000; later crane was detached at 10:30 am

OLS tank farm: work on LOX subcoolers continued; piping

Catch arms work continued; one of them has been flipped onto its side ahead of installation

OLS, IT work continued (as every day)

OLM work continued

Possible QD arm extension work continued

Foundation work for new wide high bay continued

Stainless steel ring moved to scrapyard

B5 [?] common dome sleeved (4-ring)

New intermittent RC for September 3 (7:30-10:30am)

RC for September 2 canceled

NSF

Mary

Nic

LabPadre

[119]

August 2021[]

Date Description Source Link
31.08.2021 SN20/S20 still awaiting testing on Pad A; work on TPS tiles continued

Catch arm work continued; one catch arm has been flipped at 2 pm

OLS tank farm: GSE1 work continued

Plumbing work near the LOX subcoolers (grey horizontal tanks)

GSE4 test tank rolled back to production site; to PPS

QD arm installation continued

GSE7 rolled out to OLS, arrived at OLS tank farm at 10:27 am; load spreader attached (by LR11000) at 12:59 pm; GSE7 lifted at 3:57 pm, touched down at 5 pm next to GSE2

B4 work continued near interstage and grid fins

Tent assembly continued

Concrete placing boom in front of OLM;

OLM booster quick disconnect

New intermittent RC for September 2 (3-5pm)

RC for September 1 cancelled

Standard TFR renewed, higher than previous (10000 ft), ending on September 31

NSF

Mary

Nic

LabPadre

[120]
30.08.2021 OLS Tank farm: work around the base

OLS, IT: QD arm installation continued

Cach arm work continues (Also called the chostick arm, chopsticks or catch & stack arm)

OLM: work on QD equipment

LTM 1350–6.1 soon ready

B4 work in high bay continued

Beams delivered to production site

GSE7 work looking finished

New tent under construction [!] (north of where they're building the new high bay)

QD arm extension being worked on

New intermittent RC for September 1 (8am-12pm)

NSF

Nic

LabPadre

[121]
29.08.2021 QD arm lifted by LR11350 and installed on segment #5 of OLS, IT; attachment points are on the upper cross beam of segment #4 and middle cross beam of segment #5

Catch arm work continued, some welding

SN20/S20 work continued

Unknown items delivered to production site

GSE7 tank work outside mid bay continued

B4 work in high bay continued; engine RB5 moved into high bay for installation

Work on QD arm continued; detached from LR11350 at 3.45 pm; later first actuation test started at 5.25 pm

OLM construction work continued

NSF

Mary

Nic

LabPadre

[122]
28.08.2021 New intermittent RC added for August 31 (8am-12pm)

New structure at production site; looking like the QD for OLM [?] GSE7 tank work outside of mid bay; nearly all pipes have been installed now

B4 Raptor engines continued to be added

OLS tank farm: Work continued, work on GSE1

Hwy4 work in front of launch site [new slope grading?]

Catch arm work continued

QD arm, now fully painted black, prepared for lifting onto OLS, IT; work on the arm's hinge area; later the arm was moved towards LR11350, hooked to crane, lifted above ground and reoriented

SN20/S20 work on TPS tiles continued

New LTM 1350-6.1 crane configuration changed

Inspiration4 astronauts flew low over Starbase

NSF

Mary

Nic

LabPadre

[123]
27.08.2021 S21 aft dome section (3-ring and dome) flipped in front of tents; inside of dome clearly visible

LTM 1350–6.1 raised its jib; now higher than LR11000 [?]

B4 work, especially at the aft section, continued in high bay; RB2, RB27 and RB4 spotted on B4; also some center Raptor [RC] engines have been spotted outside high bay

S21 nosecone barrel section moved; a label on it indicates that it is made of 3.6mm steel [!!!!]

Booster inner engine thrust simulater (Triangle-stand) work has continued; same stand was used for BN2.1 testing, as well as part of the nosecone test rig (new info according to NSF)

Pipe stands delivered to production site

SN15 and the moon shown

GSE7 in mid bay; unknown 6-ring section right to it [GSE8?, S21?, B5?]

Nosecones being worked on in tent 3

GSE7 rolled out of mid bay

OLS, IT: scaffolding lowered by LR11350; QD arm actuator installed at 5.30 pm

OLM work continued

Catch arm work continued

QD arm work continued, being painted black; later moved towards OLS, IT

SN20/S20 work continued

Hwy4 work continued; "Manual Checkout Cart" arrived at launch site

Mobile crane form Bigge moved to launch site

NSF

Mary

LabPadre

Austin Barnard

[124]
26.08.2021 S21 aft section (3-ring sleeve with dome) on stand, not yet flipped

OLM work continued; Quick disconnect for booster installed (for loading propellant into booster) [the structure spotted on August 19 and 21?]

OLS tank farm: more pipes added around propellant subcoolers (the grey horizontal tanks)

Catch arm work continued

QD arm work continued

New black steel structure delivered to build site

New wider high bay: Earth work continued for foundation

New smooth nosecone work in tent 3 continued

B4 work in high bay continued

SN20/S20 work continued

Cryo tank shell #3 disconnected from LR11000

NSF

Mary

Nic

LabPadre

[125]
25.08.2021 New intermittent RC for August 26 (9.30-11.30 am)

New 4-ring barrel section spotted made of 3.6mm steel (0.36mm less?)

B4 work continued; aerocover truss added on external COPVs, aerocovers will mount to these and protect the COPVs from aerodynamic forces during flight

B4 Raptor installation continued; RB4 spotted

According to NSF, the new smooth nosecone is made of 2 rows of strech formed steel, whereas previous cones were made of 3 rows of stamped steel

Two 4-ring barrel sections with lead-ins outside production tents

OLM work continued

OLS, IT: Stairs removed by LR11350

OLS tank farm: GSE1 work continued

Catch arm contstruction proceeded; use of truss section unclear

QD arm work continued

SN20/S20 TPS tiles work continued, still a lot of red labels; new red labels added near aft flap

GSE4 test tank cryogenic proof test; According to NSF, the reason was to validate construction methods used for the OLS tank farm

OLM: Booster quick disconnect delivered to launch site and lifted onto OLM

Unknown 4-ring section lifted into mid bay at 11:05 pm [GSE8?, S21?, B5?]

NSF

Mary

LabPadre

[126]
24.08.2021 GSE8 fwd dome on sleeving stand; sleeved with 3-ring section

B4 work in high bay continued

New structures delivered this week (with black beems) still at production site

Coil of stainless steel delivered

Raptor engines prepared for roll out to OLS

Insulated plumbing loaded for transport to OLS

S21 nosecone barrel section (seen already yesterday, 4-ring) in tent 3 spotted

Work on new wider high bay "super hb" foundation continued

Work on new smooth nosecone continued

Triangle-stand now called "Booster inner engine thrust simulator" by NSF

GSE7 in mid bay, pipes partly attached

New ship or tank section with lead-ins spotted in mid bay [GSE8 or S21??]

Pipes delivered to production site

OLM work continued

OLS, IT: work continued, more pipes being added; "The concrete fill pipe has been extended to columns of section 2 of the OLIt meaning Section 1 columns are now filled with concrete"

OLS tank farm: work on GSE1 continued through upper access hole

Catch arm work continued

QD arm work continued, more pipes installeed

Raptor installation on B4 in high bay continued; RB26, RB6, RB27 spotted

Circumhorizontal arc over Boca Chica

NSF

Mary

LabPadre

spoilt-sport

[127]
23.08.2021 GSE4 [test tank?] rolled out to launch site, arrived at 10.23 am

RC for August 24 canceled

OLS, IT: Work continued

QD arm work continued

Catch arm work continued

OLM work continued

New structures spotted at production site

New orange production robots delivered to production site

Tent 3: 3 nosecones and one barrel section visible

PPS: Cryo tank shell #7 still attached to crane, looks more or less finished

GSE4 test tank [?] rolled out to launch site; towards SoLS Pad A

SN20/S20 TPS tiles work continued

Three Raptor engines delivered in front of high bay; RB17 and RB20 spotted; engines likely began to be installed

Smooth new nosecone section still missing a piece

RC for August 24 canceled

NSF

Mary

LabPadre

[128]
22.08.2021 OLM welding work

Cryo tank shell #3 remained attached to LR11000

Catch arm work continued; a lot of scaffolding around it

SN20/S20 still with a lot of labels on TPS tiles

QD arm work continued; more feeding pipes installed

GSE7 apparently fully stacked in mid bay

Black painted triangle-stand now called "Thrust sim stand" by NSF; work on it continued

Ring section spotted, marked "Not for flight use*

Smooth nosecone work continued

OLS, IT: work continued; QD arm hinges visible

S21 fwd flap "flap py - studded" arrived at tent 4

NSF

Mary

LabPadre

[129]
21.08.2021 B5 aft dome booster section spotted (3-ring)

New black structure at build site [see vid 19]

Nosecone section outside tent 2 (lowest nc ring)

More concrete torn out for new wider high bay foundation

New "smooth" nosecone spotted with fewer panels spotted

GSE7 attached to crane in mid bay

SpaceX cat spotted

OLS, IT work continued; possible QD arm attachment point spotted on the south-west side, left of OLM RGV on segment #5

Catch arm work continued

B5? fwd tank #2 booster section (3-ring with lead -ins) spotted

Plumbing transported from build site to OLS

QD and catch arm work continued

LR11000 and load spreader attached to cryo tank shell #3 at most southwestern position; to be lifted over GSE6

B6? thrust puck spotted

NSF

Mary

LabPadre

RGV

[130]
20.08.2021 S21 sleeved aft section lifted off from sleeving stand

Small GSE tank stacked with GSE4 aft section (3-ring and dome) and GSE4 fwd section (1-ring and dome); purpose unknown

Concrete north of high bay broken up, presumably for new wider high bay ("Super high bay")

Work on triangle-stand continued

Additional parts lowered into 4-ring stack at PPS

Work on grey circular booster test stand continued

New stand (simple, black, circular) constructed

OLM work continued; water deluge nozzles spotted between hold down clamps of OL platform RGV]

QD arm strengthened; line boring a quick disconnect arm hinge

Catch arm work continued

LR11000 moved to OLS tank farm

OLS, IT: work continued

OLS tank farm: new equipment/pipes installed

RB24 engine delivered

Small GSE tank work continued

New intermittent RC for August 23 (9–11.30am)

NSF

Mary

LabPadre

RGV

[131]
19.08.2021 I-Beam transported at build site

S21 aft dome sleeve (3-ring) spotted

GSE4 aft section on a stand (sleeved with dome, 3-ring, with lead-ins)

Work on triangle-stand continued, painted black

Two raptor engines delivered [RC]

B4 work in high bay continued

Catch arm work continued, more upwards facing pipes attached; work on catching mechanism

QD arm work continued; readied for installation on OLS, IT

OLM work

OLS tank farm: pipe work

SN20/S20 still attached to LR11000, still a lot of green and red labels on TPS tiles

S21 aft dome prepared for lifting; lifted on stand; sleeved with 3-ring aft stack

New structure with black beams at the build site

SN20/S20 disconnected from LR11000 at 3.08 pm

Cryo delivery (nitrogen) to OLS tank farm at 3.40 pm

Outline of new high bay visible RGV

Jib pieces for LTM1250 crane delivered

NSF

Mary

LabPadre

RGV

[132]
18.08.2021 RCs for August 19 and 20 canceled

At least two Rvac engines that were installed on SN20/S20 left Boca Chica

Musk: fwd flap design error and changes announced

B4 work in high bay continued

Starship aft section moved (3-ring); will be used for fit test on a stand; moved to PPS

Stand mounting points prepared at PPS

Aft section lifted and placed onto stand at PPS [stand next to the stand with yellow railings]

OLM work continued

SN20/S20 still hooked to LR11000

Work on black catching arm continued

OLS, IT; pipes continued to be installed along the outside of the tower; grey metal extension on segment #1 has been added again

QD arm work continued [the yellow/black arm]

BN3/B3 LOX tank still on pad A

New RCs for August 24–26 (5-11pm)

3.6mm 304L stainless steel delivered

NSF

Mary

LabPadre

[133]
17.08.2021 OLM work continued

LR11000 moved from SoLS pad A to pad B

B3 dismantling work continued

SN20/S20 prepared for move to SoLS pad B for testing (ambient and cryo proof/pressure testings expected); work through access hole

Catching arm for OLS, IT continued

QD arm work continued

GSE2 being worked on

High bay bar work continued

B4 work continued in high bay, external box has been added [?]

B5 aft dome sleeve (3-ring) spotted

New trinagle stand structure continued to be worked on

SN20/S20 moved towards pad B; lifted onto the pad by LR11000 (6:13pm)

Berm extension and berm tunnel spotted; possibly on the south side of OLS tank farm RGV

NSF

Mary

LabPadre

RGV

[134]
16.08.2021 B3 LOX tank attached to LR11000 for further scrapping

Work on triangle-stand continued

Possible inner booster thrust simulator at PPS [the one from Pad B???]; moved towards triangle-stand

PPS: Booster thrust sim [grey circular structure] attachment clamps installed

Unknown structure [black stand with yellow railing] loaded onto SPMT at PPS; moved around

GSE tank dome outside tents

B4 work in high bay continued

SN20/S20 work on raceway (electrical wiring) continued

Work on possible booster catch arm and QD arm continued; insulated plumbing installed at QD arm

Pipe delivered to launch site

Today's RC canceled

Tomorrows RC canceled

OLS, IT: Cryo pipe installation has begun

NSF

Mary

LabPadre

[135]
15.08.2021 BN3/B3 scrapping continued; CH4 tank further cut into parts

SoLS pad B work continued

QD arm work continued

Catch arm (black pipes) continued to be worked on, especially on upwards facing arm

GSE1 and GSE2 still have scaffolding going up to access hole as well as internal ventilation

OLM work continued, now completely painted grey

PPS: Cryo tank shell work continued

B4 work in highbay continued; dents have appeared and disappeared again as the booster expands and contracts (normal)

OLS, IT: Exterior cladding beginning to be added on segments #1 and #2

SN20/S20: TPS tiles work continued; also some work on external wiring

SN20/S20 work continued during the night [vid 16]

OLM and OLIT work continued during the night [vid 16]

Catching arm work continued; mounting points added [vid 16]

NSF

Mary

LabPadre

[136]
14.08.2021 BN3/B3 attached to LR1100 with spreader bar

GSE aft dome spotted (3-ring with dome); GSE8?

B4 work continued in high bay

Stand with triangles work continued at PPS

GSE7 nearing completion in mid bay; more pipes have been attached

Booster thrust simulator: more parts added

QD arm work continued

Lift and catching arm work continued

BN3/B3 began to be scrapped; cut in half; upper segment lowered

OLS tank farm: more pipes attached for horizontal tanks

OLM/table work continued

NSF

Mary

LabPadre

[137]
13.08.2021 PPS: Cryo tank shell #7 work progressed; stacking complete

B4 work in high bay continued

SN20/S20 prepared for roll out

S21 aft dome moved into production tent

QD arm work continued; some propellant seem to have been installed

Tower arm (catch arm) work continued

OLS, IT: New parts lifted; taken down again; new pipes at segment #1 installed; scaffolding continued to be removed

OLM/table work continued

SoLS Pad B thrust ram removed (without being used), moved to build site at 12:47am SN20/S20 a lot of TPS tiles removed from nosecone barrel section

SN20/S20 moved back to launch site; arrived at 11:57am

Boom lifts moved to launch site

GSE6 lifted by LR11000 and placed west to GSE3/Shell#4

Coil of stainless steel delivered

Diverse deliveries to the build site

FCC report for Starlink operation for ground testing on Starship

LR11000 moved towards pad A

OLS, IT: Scaffolding installed for QD arm installation

New RCs: Intermittent RC for Aug 16 (9am-1pm); RC for Aug 18&19 (5-11pm); RC for Aug 20 (6am-12pm)

NSF

Mary

LabPadre

[138]
12.08.2021 SN20/S20 TPS tiles inspection/repair work continued; blue markings "E1", "E2" seen

S21 aft dome spotted

S21 legskirt spotted (2-ring); label still "SN"

OLS; work on QD arm and tower arm continued

Work on potential booster test stand with triangles continued

SN20/S20 TPS tile replacement began

B4 work in high bay

OLM work continued; a work lift has been installed [day unclear]

OLS, IT; scaffolding being removed

B4 Raptor engine removal continued

Grove GMK5275 crane arrived in Boca Chica

Liebherr crane parts arrived [?]

New intermittent RC for August 13 (9.30am-12pm)

NSF

Mary

LabPadre

[139]
11.08.2021 B4 rolled back to build site on two SPMTs; during the transport, the booster was kept pressurized; moved into high bay

GSE6 rolled out to the OLS tank farm; both met near the road block

SN20/S20 moved out of the high bay to prepare it for B4; positioned outside mid bay

Methane transfer tubes (downcomers) delivered to build site

Two Raptor eninges loaded onto Raptor van

Potential booster test stand with triangles work continued; purpose yet unknown; more plates added

Booster thrust ram/simulation (grey circular structure) work continued

Caged ladder moved around

SN20/S20 work on TPS tiles continued (labels)

GSE7 aft dome sleeve (3-ring) spotted

B4 Raptor engines began to be removed

OLS tank farm: Cryo shell #4 lifted with LR11000, placed over GSE3 at 1:50pm (southeastern location)

GSE6 hooked to LR11000

NSF

Mary

LabPadre

[140]
10.08.2021 B4 prepared to be lifted from OLM

B4 removed from OLM at 7:45 am by LR11350; detached from crane/load spreader at 3:06 pm

SN20/S20 more colored labels attached to TPS tiles

PPS: Cryo tank shell #7 stacking continued

B5 comm dome sleeve (4-ring stack) and fwd tank #2 (3-ring stack with lead-ins) spotted

Top platform added to circular structure with triangles

OLS tank farm: work on GSE1 and GSE2 continued

Work on black pipe structure (tower arm) and yellow pipe structure (quick disonnect arm, confirmed) continued

Stainless steel roll delivered

GSE8 fwd dome stack #2 spotted [GSE8 will replace the scrapped GSE4)

New intermittent RC for August 11 (7am-12pm)

GOA's decision deniying the HLS protests by Bluo Origin and Dynetics released; confirming SpaceX's concept of operations, involving 16 total launches each 12 days apart and three different categories of Starship (HLS lander, tanker, undisclosed variant [DELETED])

NSF

Mary

LabPadre

[141]
09.08.2021 SN20/S20 more TPS tiles marked

Cryo tank shell #4 LOX rolled out to launch site; SpaceX label: "Outer Shell#4 LOX"; slated for most southeastern GSE tank [GSE3, see August 6]; load spreader and LR11000 attached to the shell

GSE2 work continued

Weather balloon released near production site

PPS: huge tanks still packed in blue plastic

New intermittent RC for August 10 (7am-12pm); later canceled

BN2.1 placed on a concrete stand at PPS

NSF

Mary

Jack

LabPadre

[142]
08.08.2021 B4 work for preparing to remove it from OLM

B4 attached to LR11350

OLM legs are being painted grey

SN20/S20 colored labels attached to TPS tiles, likely to indicate damage that needs repairs

Deck installed on possible raptor installation platform

PPS: Cryo tank shell stacking continued on shell #7 (likely final shell)

BN2.1 inspection work

Hydraulic rams installed on a new potential raptor thrust sim

GSE7 fwd tank section ready to be stacked on aft section; hooked to crane in mid bay; later both parts were stacked together; now likely full hight

Work on new stand like structure with triangles continued

Work on black/yellow structure continued; now NSF calles is the "quick disconnect arm" which "will load propellant into Starship prior to launch"

OLS tank farm continued to be worked on

NSF

Mary

LabPadre

07.08.2021 GSE7 in mid bay, outside pipes apparently already installed

GSE6 still at production site [!]

Work on a test stand like structure at PPS

New parts delivered to production/build site; some parts from McGregor arrived

Lower bulkhead for Superheavy booster spotted [B5?]

S21 nosecone spotted in tent 3

PPS: Cryo tank shell construction continued: shells #3-6 likely complete; shell #7 likely more than 10 rings tall

SN20/S20 Rvac engines removed and moved around

SN20/S20 Sea level raptor engines removed

B4 reattached to LR11350

Work on black and yellow pipe structures continued

GSE? section (6-rings) attached to crane/load spreader

NSF

Mary

LabPadre

[143]
06.08.2021 SN20/S20 more TPS tiles installed

OLS, IT; OLM; OLS tank farm work continued

SN20/S20 stacked onto B4 by LR11350, fully assembled rocket for the first time ever!!

SN20/S20 removed from B4 by LR11350 after first fit check for final construction, touch-down at 9:45 am

SN20/S20 moved back to build site; into high bay; hooked to bridge crane

Time for today's RC changed to 11.30am-2pm

GSE3[?] lifted over the tank farm and lowered onto OLS tank farm foundation; placed at the most southeastern foundation

GSE3[?] detached from load spreader after being lifted into place by LR11000

Musk: different new information

New intermittent RC for August 9 (7am-12pm)

NSF

Mary

LabPadre

[144]
05.08.2021 SN20/S20 and GSE6 [NSF]/GSE3 [LP] rolled out to OLS [apparently it was GSE3, vid 07]

Black and yellow tubular structures continued to be worked on

GSE5 sleeved with a cryo shell [the one in north-eastern position]

B4 detached from LR11350

SN20/S20 attached to LR11350

New intermittent RC for August 6 (9.30am-12pm)

SN20/S20 lift scrubbed due to high winds

NSF

Mary

Jack

LabPadre

Musk

[145]
04.08.2021 SN20/S20 nosecone lifted into high bay; stacked at 4:11 am

B4 CH4 tank condensation at 3am

B4 attached to LR11350 load spreader

B4: GSE hoses detached ahead of lifting

B4 lifted onto OLM by LR11350 in a very careful manoeuvre

Musk: Mechzilla (OLIT) not yet ready, but for future rockets

SN20/S20 unhooked from bridge crane, now fully assembled!

NSF

Mary

Jack

LabPadre

[146]
03.08.2021 Standard TFR renewed for covering ground testing such as cryogenic and staic fire tests (5000 ft, until August 31)

Work on SoLS pad B continued with some welding

SN20/S20 work continued outside high bay

B4 detached from high bay bridge crane

New intermittent RC for today (9:30am-3pm)

B4 roll out to OLS, near OLM

Musk infos about catch mechanism on OLS IT

FCC/Starlink update [Sheetz]: up to 400 satellites per launch on Starship (vs 60 per Falcon 9)

RV5 and another RVac engine moved towards Starship SN20/S20 likely for a fit check

SN20/S20 moved into high bay ahead of nosecone stacking

OLM work continued

New intermittent RC for August 5 (6:30-9am) canceled

Everyday Astronaut interview with Elon Musk

SN20/S20 nosecone moved and stopped just outside lowbay, more TPS tiles added; later moved to high bay for stacking as well

SN20/S20: all six Raptor engines (3SL, 3Rvac) have been installed [Musk]

NSF

Mary, Jack

LabPadre

E. Musk

[147]
02.08.2021 RC74,64, RCxx, RCxx, RCxx, RC65, RB22 installed on B4

B4 work in high bay continued on mating the two halves

B4 had 29 Raptor engines installed in just one night

SN20/S20 nosecone: TPS tiles installation continued

SN20/S20 rolled out of mid bay, nearly fully covered with TPS tiles on one site (still some needed near the section welds)

SN20/S20 aft flap installed (with TPS tiles)

GSE3, GSE6 work continued

Stainless steel coil delivered

PPS: [not launch site] concrete poured

OLS tank farm: Work on GSE1 and GSE2 continued

LR11000 and LR11350 detached from OLM platform

LR11000 moved back to OLS tank farm

OLM welding work

Yellow pipe structure growed

Blcack pipe structure welding work continued

SN20/S20 second fwd flap installed, second aft flap installed

NSF

Mary

LabPadre

[148]
01.08.2021 B4 more grid fins installed

Fit check of B4 on OLM NET Tuesday [Musk]

Black tubular structure work continued

Yellow pipe/tubular structure work continued

OLM: work on attaching the platform on the legs

GSE2 work continued

BN3/B3 still on pad A, plans unclear

RB engines arrived from (RB17, RB18, RB9, RB21, RB22)

S20/SN20: first forward flap attached to nosecone; smaller sice visible; work on the TPS tiles installation continued

Stainless steel coils delivered

GSE3 and GSE6 work at production site continued

New pipes for black tubular structure arrived

RB

B4 LOX tank moved in high bay and work platform installed ahead of final stacking

B4 CH4 tank lifted by high bay crane and stacked onto LOX section; final stacking; met at 4:37 pm

B4 Raptor engines roll out in this order [where?]: RB7, RB2, RB3, RB15, RBxx, RBxx, RB9, RB21, RB19, RB18, RB4, RB6, RC74, RC79, RC58, RB8, RB11, RB14, RB20

B4 raptors installed late night: RB7, RB2, RB3 pictured; at least 14 Raptors already installed as of 1:20 am of August 2 [?!]

NSF

Mary

LabPadre

[149]

July 2021[]

Date Description Source Link
31.07.2021 SN20/S20 nosecone stacked onto barrel section at wind break; quadratic TPS heat shield tiles spotted near the flap attachment rig; lead-ins removed after the two parts have been welded together

More black tubular structures delivered (see July 20, 24, 27, 29)

Yellow pipe structure work continued, now getting higher; could be a lift sliding up and down the OLS IT

GSE6 work at build site continued

Plating from booster thrust simulator mount at PPS removed

SN20/S20 tank section work in mid bay continued

Rvac engine delivered (after another delivery last night, at least three on site now, fourth wasn't unloaded yet)

OL platform / table lifted by LR11350 and LR11000 onto OLM legs!!, touchdown at 1:46 pm

The OL platform has 20 hold down clamps installed

Several more Raptor engine deliveries

Musk: Possibly steering away from traditional grid fins in the future to something with more drag

Musk: OL platform weighs 370 tons

SN20/S20 first aft flap installed in mid bay

NSF

Mary

LabPadre

[150]
30.07.2021 Yellow pipe structure work continued; getting really huge

Black pipe structure attached to crane

OLM preparation work continued; work at the base of its legs

LR11000 crane moved towards OLS, IT/landing pad after shortly leaving the OLS onto hwy 4

PPS: Cryo tank shell construction continued with shell #6 looking nearly complete (some 2-3 rings short) but still attached to crane; shell #7 stacking began with first section (dome+ring) stacked onto another section

New brick building behind mid bay

B4 thrust section /aft dome section (3-ring with lead-ins) moved into high bay; stacked with LOX section later

SN20/S20 nosecone: TPS tiles being installed; aft flaps moved near tents

B4 stacking continued in high bay, methane tank section looks to be complete (13 rings) and LOX tank as well

Ship aerocover unloaded (SN20?)

New container wall being built at launch site

B4? grid fins spotted

B4 methane tank moved out of high bay; moved back later

B4 grid fins installation on methane tank section began

NASA/GAO: Denies BO and Dynetics protests of HLS contract awarded to SpaceX

New intermittent RC for Monday, August 2 (3-7pm)

WAI/RGV: Work on new pads and concrete foundations at OLS with rebar laid (near landing pad, at OLS tank farm and staging area, terminal for trucks for fuel delivery, around/north of OLM)[151]

LR11350 and LR11000 moved into position for OL platform lift [vid 31]

B4 first grid fin installed on upper methane tank section [vid 31]; apparently they can't fold (confirmed by Elon Musk)

Rvac engine delivered [vid 31]

NSF

Mary

LabPadre

Michael Sheetz

WAI/RGV

[152]
29.07.2021 B4 fwd #4 section ready for stacking (4-ring with lead-ins)

Nosecone with blankets and TPS tiles rolled outside tent (likely for SN20/S20)

GSE5 has been detached from LR11000

OLM readied for installation of OL platform (table) with scaffolding being installed

LR11350 disconnected from IT, stacking of the tower appears to be complete

OLS: concrete work

New Raptor engines arrived at launch site

SN20/S20 aft flap installation rig moved inside mid bay and affixed to the ship for flap installation

Work on GSE3 and GSE6 continued at production site

Concrete forms placed in a circular stand like shape at the build site

Work on grey circular structure continued at PPS

B4 methane tank stacking continued with top 9-ring stack (fwd) stacked onto another section (fwd #4), methane tank section looks completed now

Another black pipe structure delivered to OLS (see July 20, 24, 27)

Grate lifted onto OLS, IT by LR11350

Fwd flap delivered to build site (SN20?)

NSF

Mary

LabPadre

[153]
28.07.2021 OLS, IT: Segment #9 with a winch wheel lifted by the LR11350 crane with an American flag after a huge winch extenseion has been added instead of a fourth column; slowly lowered onto segment #8

GSE5 transported to OLS by two SPMTs

OL platform transported to OLS by two SPMTs after some scaffolding has been added on it

GSE2 detached from LR11000

GSE5 lifted into place at OLS tank farm by LR11000 right to the east of GSE1

Two RBoost and two SL Raptors have been delivered

B4 thurst dome has been flipped

B4 methane tank stacking: 6-ring fwd section attached to high bay crane and stacked to another 3-ring stack (now 9 rings tall)

NSF

Mary

LabPadre

[154]
27.07.2021 B4 methane transfer tube "downcomer" installed early in the morning

OLS, IT: Work on segment #9 continued, with an intermediate floor and black winch wheels being installed (5th pulley has been installed); later LR11350 and load spreader attached to the segment

Gravel delivery to OLS

OLS: work on yellow pipe structure continued

More large black pipes arrived at launch site (see July 24, July 20)

PPS: work on cryo tank shell #6 continued, now likely full height

OL platform work continued, some parts have been painted

Raptor engines delivered to build site (likely those earlier removed from BN3/B3)

GSE3 and GSE6 now again labelled as those being place more north

GSE5 moved

GSE2 work continued

B4 LOX tank section inside high bay ahead of stacking

New intermittent RC for Wednesday, July 28 (9-11am)

BN3/B3: GSE pipes for fuelling disconnected

WAI internal SpaceX info: B4/S20 [SN20] ready on OLM by August 5 as internal goal![155]

NSF

Mary

LabPadre

WAI

[156]
26.07.2021 B4 stacked with fwd 5 section (4-ring), now 20 rings tall (~37m) at 12:50 am

B4/B5? downcomer pipe spotted

OLS, IT: Segment #9 third and fourth pulley installed

SpaceX: 100th build of a Raptor engine complete (RB16)

GSE3? work continued [isn't this GSE5]

Work inside GS*3

Test nosecone used in the cargo bay pathfinder scrapped

Work on a transport stand at PPS

OL platform work continued, more parts delivered

Stainless steel roll delivered

OLM: Scaffolding installation continued

GSE1, GSE2: Installation of stringers for strengthening of the tanks continued; GSE2 still attached to LR11000

Hwy4 repaving work continued, milling machine tearing up the highway

OLS, IT: Segment #9 work continued, new equipment lifted into it

Work on yellow pipe structure (possible fuelling arm) continued

Brick work at high bay base continued

GSEs: GSE3 in front of high bay, GSE5, GSE6 a bit north (according to NSF; not congruent with previous information!)

GSE3 has stringers already installed

Possible B5? thrust dome outside tents

Nosecone barrel section with TPS base layer (for SN20/S20?) lifted into windbreak

Nosecone with TPS base layers being worked on in tent 3

Raptor vacuum mount and thrust puck for starship delivered

Possible GSE tank 4-ring section with lead-ins moved into high bay

NSF

Mary

LabPadre

2E
25.07.2021 Pesticide spray plane flying low over starbase against mosquitos

B4 aft 5 (4-ring with lead-ins) outside high bay

B4? aft dome sleeve outside tent 1 (3-ring); later hooked to crane and flipping jig, flipped

OLS, IT: Segment #9 work continued

GSE6 (13-rings) rolled out of high bay near GSE3, pipes not yet fully installed?

GSE5 work continued

Nosecone barrel section prepared for TPS tiles, with lead ins, possibly for SN20/S20

PPS: Cryo tank shell work continued; Shell #6 (13-rings) lifted and stacked on another 4-ring section; shells #3-5 looking quite finished

OLS tank farm: work on GSE1 and GSE2 reinforcements continued

OLM: Worik platform? installation continued

SoLS, pad B: third thrust ram for RVac installed

SN20/S20 work in mid bay continued with several man lifts up

B4 aft dome/thrust dome placed on sleeving stand

SoLS tank farm venting a lot; WAI suggested possible OLS tank farm GSE tanks test as both are connected

NSF

Mary

Stephen

LabPadre

WAI

[157]
24.07.2021 B4 stacking continued in high bay, now 16-rings tall

OLS, IT: Parts for suspected IT carriage delivered to launch site

2 Raptor engines delivered, RC, RB; three engines (RC62 identified) loaded onto truck

GSE7 aft dome sleeved (3-ring plus dome); GSE7 stack #2 fwd dome sleeve (2-ring) spotted

GSE6? work in high bay continued

PPS: Cryo tank shell construction continued on shells #5 and #6, according to Brendan shell #7 commenced with dome stacked with first ring

Work on circular grey structure continued

OL Platform work continued, pipes have been installed

More large black pipes/tubular components delivered to launch site (looking the same as spotted on July 20)

OLS, IT; Work on base continued, equipment added to segment #1; segment #9 construction continued with a large beam being added

Yellow pipe structure work continued

OLM: work platform installation began

GSE1 and GSE2 reinforcement work continued

Liquid nitrogen delivered to OLS tank farm !!!!

B4? fwd dome placed on sleeving stand

Super heavy booster aft dome work in tent 1 continued

Delivery to SoLS tank farm

GSE3 moved north

Reinforced barrel section flipped ahead of stacking (no dome inside)

B4 fwd sleeve flipped at 3:35 pm

Elon Musk: Bigger highbay to be constructed later

NSF

Mary

LabPadre

[158]
23.07.2021 RC57 moved to launch site

SN20/S20 tank section now fully stacked

RC62 removed from BN3/B3 at 2:22 pm, moved to build site

Special yellow pipe section with pivot points for a possible GSE arm delivered at 2:24 pm; work on structure continued

GSE6? aft dome section (3-ring section with dome and lead-ins) outside high bay, lifted into high bay

Superheavy booster thrust dome in tent 1, another one as well (likely earlier in the production process)

Nosecone moved from scrapyard to rear of production tents; TPS tiles on aerocover

SN20/S20 under construction in mid bay (at least 16 rings tall)

GSE5 pipe work continued

New barrel section prepared for stacking (lead-ins installed)

Welding work on a transport mount

Grey circular structure work continued; potential Super Heavy outer ring thrust ram or a Max Q simulator

PPS: Work on cryo tank shell #6 continued

New barrel section (4-ring) attached to crane and lifted into mid bay, possibly beginning GSE7

Brickwork added to the base of high bay

Stainless steel roll delivered

Pathfinder nosecone with barrel section moved out of windbreak, payload bay has been cut into leeward side, hooked to crane; tip of nosecone cut off, likely going to scrapyard - New payload door design with conventional side doors instead of previously suggested mouth like opening? [WAI][159]

SN20/S20? nosecone with TPS mount points in tent 3

Work on SoLS Pad B continued with new black structures being installed (RVac puck shucking hydraulics)

A lot of black small pipes delivered to launch site

OLS, IT: Segment #9 assembly continue

Liquid nitrogen delivered

GSE2 reinforcement work continued, still attached to LR11000

PA system on top of tank

Concrete work near Starhopper (SH)

B4 aft 4 outside high bay (4-ring with lead ins)

NSF

Mary, Stephen

LabPadre

WAI

[160]
22.07.2021 OLS, IT: Segment #9 or #8b assembly began at the launch site with columns set into place by PBI 12000-1 crane and cross beams added

SN20/S30 thrust section (5-ring section) moved into mid bay, connection point for GSE fuelling arm visible for the first time

Elon Musk: narrower and lighter flaps

OLS, IT: Work on the base continued and roof of winch room; also some work at a column of segment #2

Yellow pipe structure: welding work continued

OLS: Work at new concrete pad continued

OLM: Work continued

GSE2: Scaffolding erected at the base, access hole opened

BN3/B3 top dome venting; work at the engine section; RC59 removed, packed and transported back to the build site

GSE3 moved out of mid bay towards high bay, near GSE5

GSE6 hooked to high bay crane

Grey circular mystery structure work continued

OL platform work continued

Super heavy booster aft dome being worked on in tent

RC57 removed from BN3/B3 at 11:54pm

11:16 pm: first cargo door was cut out and removed from pathfinder nosecone

NSF

Mary, Stephen Marr

LabPadre

[161]
21.07.2021 B4 stacking progressed in high bay, aft tank #2 has been stacked (at least 10 rings tall now)

Hydraulic cylinders delivered and installed on grey circular mystery structure (lifted by Grove ORT 8100 crane), likely all around the structure

Grey circular mystery structure: piping installed

PPS: Rebar laid for a new foundation

GSE5 work outside mid bay continued, more pipes installed

PPS: Work on cryo tank shell #5 and #6 continued

Stainless steel loaded onto truck

Aft dome now sleeved (likeyl made out of scrapped parts)

Booster aft dome without thrust puck near the tents; status unclear

Storm in Boca Chica

OLS tank farm: GSE2 attached to LR11000

Concrete work between the two berms towards OL tank farm

Work on yellow pipe structure (some black pipes visible too) continued

Generators delivered

New sections of the black piping at launch site lifted

BN3/B3 lower LOX tank hatch closed

NSF

Mary, Stephen Marr

LabPadre

[162]
20.07.2021 BN3/B3 wok continued (inspection of raptors and aft section)

Two white/blue cranes drove to the launch site

Genie SX-180 crane (blue) sptted at launch site; yellow grove crane driving around

PBI Manitowoc 12000-1 crawler crane boom has been lowered previously

OLS, IT: Work on winch room continued

Aft dome lifted onto sleeving stand [tag ripped off, someone noted B2.1 on it, BN2.1], sleeved with a super heavy aft ring stack, likeyl to practice dome mating with scrapped parts

RB2 (raptor boost 2, named "R2B2") arrived

OL platform work continued, possible hold down clamps installed [?]

OLS, IT: Load spreader detached from segment #8, LR11350 moved back, load spreader lowered

OLS: New concrete rebar between the two berms towards OLS tank farm

Black steel structure delivered to launch site

Huge black pipe structure delivered and lowered into place at launch site [possibly something to do with the yellow pipe structure?)

OLS, IT: Three single-hight columns for segment #9 delivered to launch site by SPMT (possibly to be lifted individually), fourth column, smaller than the other three, delivered later at 1:42 pm

Ship [S20?] aft flaps spotted on a stand, with TPS covering; likely some 30% smaller than previous

Grey circular mystery structure work continued at PPS

The black stand with yellow railing still standing around

B4? aft dome (3-ring stack or sleeve) spotted

B4 aft 4 (4-ring with lead-ins), B4 aft 5 (4-ring with lead-ins), B4 fwd 4 (4-ring with lead-ins) ready

GSE tank ring stack (4-ring with lead-ins) spotted

GSE5 work continued, more pipes attached

GSE3 work continued in mid bay

B5 "aft dome" sleeve (unfinished) spodded

OLS: staging area foundations for starship and superheavy progressed

NSF

Mary

LabPadre

RGV

WAI/RGV

[163]
19.07.2021 OLS, IT: LR11350 still attached to segment #8

OLM work continued (or inspection)

OLS: concrete work at landing pad

Unknown piping delivered to launch site and attached to crane

Work on yellow pipe structure continued

Liquid Methane delivered

PPS: Cryo tank shell construction continued with stacking of GSE shell #6 (dome with top ring stacked onto a new segment)

Transformer delivered

GSE5 work continued outside of mid bay with more pipes being installed

GSE3 and S20 still in mid bay; work on S20 continued

Grey circular structure at PPS: welding work, some brown metal/steel parts have been added recently

Black stand-like structure with yellow railing lying around

OL platform work continued

Booster aft dome sleeve (3-ring section) spotted [B4?]

GSE fwd dome sleeved (with 2-ring stack) [GSE4/GSE6?]

BN3/B3 static fire

NSF

Mary

LabPadre

[164]
18.07.2021 OLS, IT: Segment #8 detached from and reattached to laodspreader at least 3 times in order to balance the load for liftting (due to one column being taller); crane turned to move the segment closer to tower ahead of stacking; then lifted by LR11350 and stacked to tower; extension platform looking towards OLM

Alert notice for July 19 for Static Fire attempt on BN3/B3 issued (12-10pm)

NSF

Mary

LabPadre

[165]
17.07.2021 Work on Starship thrust ram installed on SoLS Pad B

OLS tank farm work continued, pipes moved

OLS, IT: Two parts of electrical conduit lifted inside tower by LR11350; segment #8 work continued

Rebar laid for new concrete pad between landing pad and blast berm

Potential B4? aft section (3-ring) hooked to flip rig and flipped; no dome installed yet inside!!

Raptor engine delivered

New equipment delivered to build site "HYM-211, TLH_Axial 11"

Work on a GSE tank inside mid bay (not GSE6? or GSE4?), GSE3 fully stacked inside mid bay [?]

Grey circular mystery structure work continued with a parts lifted into it

Black stand like structure work continued

Hydraulic rams loaded onto Flatbed truck

GSE5 moved out of high bay, now waitng outside

Work on a nosecone barrel section with lead-ins outside tent 3 and low bay

Ship aft dome laying around near PPS

PPS: Cryo tank shell #5 nearly fully stacked now (the 6th of eight 12-m tanks)

GSE tank aft section (3-ring with dome) moved [GSE4/GSE6?]; label, likely outdated, mentioning B4: "BN4 aft dome stiffed panel"

OLS, IT: Roof installation on winch room continued

OLS, IT: Segment #8 attached to LR11350

Pieces possibly for catching and lifting system delivered to build site

NSF

Mary

LabPadre

[166]
16.07.202 B4 work in high bay continued

Nosecone moved to scrapyard (previously in front tent 3)

PPS: Grey circular mystery structure work continued; black stand like structure work continued

OLS tank farm progressed with new GSE installed; control panels spotted; white tanks (possibly for compressed helium/nitrogen) moved around

SN20/S20? aft flap with TPS tiles spotted; the first time with curved tiles like this [!]

OLS, IT: Roofing installed on tower winch room [east and south side base extension]

OLS, IT: Segment #8 prepared for stacking

Yellow pipe work continued

Liquid nitrogen delivered to SoLS tank farm

Pipe parts delivered "Not Cryo cleaned", "Not clean for LOX", "Do not use"

OL Platform work continued

PPS: Second flare stack installed, possibly just temporary solution

B4 aft 4 and B4 aft 5 (both 4-ring stacks with lead-ins) spotted

NSF

Mary

LabPadre

15.07.2021 B4 aft 3 section (4-ring stack with lead-ins) in front high bay

B4 common dome section stacked in high bay [likely with aft #2?]

BN2.1 hooked to crane

PPS: unknown, tall black structure spotted

PPS: Grey circular mystery structure looking nearly complete

PPS: Cryo tank shell #4/5???? construction work continued, 5-ring section lowereed into scaffolding (official name: "Cryo Shell: 01445452-505 Shell#5, Cryo Shell#4; Item:01445452-535 - TRANSITION QUAD STACK; WO:1687287)[pic: second-lowest 5-ring stack) and the other section (13 rings and dome) stacked onto it

PPS: truss sections delivered

PPS: Flare stack in action; first ignition at 2 am

White pipes delivered

OLS, IT: Part lowered by LR11350; stairs lifted out; segment #8 moved; work on east side base extension continued

OLS tank farm: work at horizontal tanks continued

OLS: Yellow pipe work continued

BN3/B3 work continued

RC for today canceled

New RCs for July 19–21 (12-10pm)

NSF

Mary

LabPadre

[167]
14.07.2021 Aft flap delivered [SN20?]

Many deliveries to build site

RB11 (Raptor boost) spotted

SN20/S20 nosecone spotted: new forward flap mounting jig design; lots of TPS pin attachments; four port RCS thruster (vs 3 on previous SNs); superman logo near top of flap mounting jig

Overpressure notice to Mary for today (12-10pm); but testing RC later canceled

SN20/S20 work in mid bay continued

GSE3? waiting in mid bay

OLS, IT: Segment #8 roll out after work on the sideward extension had progressed

PBI Manitowoc 12000-1 crawler crane moved to the launch site

PPS: Cryo tank shell work continued

Unknown black stand-like structure attached to crane

Work on grey circular mystery structure at PPS continued (likely part of the launch mount)

GSE1 welding work

Pad B thrust ram installed for future cryo tests with Starship

Yellow pipe mystery structure continued to grow

Cryo shell load spreader removed from LR11000 and placed on SPMT, returned to build site

B4 fwd 2 section (3-ring stack with lead-ins) spotted

Astronomical/tracking telescope dome spotted

FAA: "The FAA warned SpaceX that, due to the agency's ongoing environmental review, the massive Starship launch tower is yet unapproved and could need to be taken down.

"The company is building the tower at its own risk," an FAA spokesperson told CNBC."; "The FAA's warning to SpaceX traces back to this letter in May, but the company has continued forward with work in the past few weeks"

Overpressure notice issued for July 15

NSF

Mary

LabPadre

Michael Sheetz [168]

[169]
13.07.2021 Second raptor delivered to launch site (BN3/B3) at 2:28 am

Both additional raptors installed until 5:57 am; confirmed to be RC57, RC59, RC62

Lightning appears to have striked SN16

LR11350 lowered for some work and risen again later

OLS concrete work

OLS, IT: East side base extension roof beams added

OL platform work continued with parts lowered into it [hold down clamp?] and a part lifted out

SN20/S20 leg skirt with lead-ins (fewer than with old sections)(2-ring stack) moved; covered TPS tiles attachment pins; lifted onto a mount

SN20/S20 thrust section outside tent 1 (3-ring stack, with access hole)

SN20/S20 thrust section stacked onto leg skirt

GSE tank under construction in high bay [!] at least 5 rings, with dome [GSE5?]

Cryo tank shell #2 lifted by LR11000 onto an empty tank farm stand (most south-western)

RC for today canceled

Intermittent RC for tomorrow added (2-4pm)

NSF

Mary

LabPadre

[170]
12.07.2021 Second BN3/B3 raptor, identified as RC59, lifted on 12:10 am local; but moved back to build site later

Cryo tank shell #2 moved to launch site [the other is a water tank]

Some road work on pad A ramp

Ring section likely for TPS tiles testing spotted [NSF: possibly for SN20/S20]

Several deliveries to build site

Booster section attached to flipping jig inside high bay [B4?]; later flipped [vid 13] [why booster; could it be SN20?]

PPS: OLS, IT: Work on segment #8 progressed, special extension added

BN3 work continued

BN3/B3 Cryo proof test

LR11350 6m crane section (old) transported away

GSE5 midsection #2 (4-ring with lead-ins) moved outside high bay [vid 13]

Second Raptor delivered to BN3/B3 at 11:36 pm

NSF

Mary

LabPadre

[171]
11.07.2021 Second raptor engine for BN3/B3delivered to launch site at 12:52 pm, unknown RSN

Installation of first engine on BN3 continued (RC57) [Raptor Center]

A downcomer (LOX or CH4) has been moved into mid bay on July 5 at 10:42pm

LR11350 extension work continued with parts added to jig; jig now reattached to boom

LR11350 lifted

PPS: Cryo tank shell #5 stacking continued with top 6-ring section stacked onto another 5-ring section; shell #4 seems still 1-2 rings short

GSE5 fwd dome section outside [inside?] mid bay, at least 6 rings tall now

OLS tank farm work continued

OLM beam welding work continued

SoLS tank farm filled

PPS: OLS, IT: Assembly of segment #8 continued

Black steel boom [?] delivered to launch site

Nosecone in front of tent 3 [the one spotted earlier] hooked to crane and stacked on barrel section; "both sections have tape markings indicating payload door tests" [the_denks]; NSF: "Nosecone 18 going onto SN17's barrel section" [vid 12]

4-ring barrel section in front of high bay; another one in tent [vid 12]

NSF

Mary

LabPadre

[172]
10.07.2021 New Superheavy [B4?] thrust puck (for nine engines) delivered

PPS: OLS, IT: First column of segment #9 delivered, along with an even smaller column

BN3/B3 work continued

PPS: Cryo tank shells #4 and #5 work continued

PPS: OLS, IT: Segment #8 work continued

OL Platform work continued

GSE5 fwd dome spotted (sleeved?)

RB6 engine moved inside tent

Hwy4 work continued

LR11350 extension work continued with a white segment inserted into boom (above power boom section)

Next large cylinder (wrapped up in blue) delivered to PPS

OLS tank farm: more plumbing added

Unknown parts delivered to buil site

RC57 delivered to launch site at 6:55pm; installation on BN3/B3 began on 10:13pm

NSF

Mary

LabPadre

[173]
09.07.2021 PPS: Cryo tank shell #5 hooked to crane

PPS: Piping lifted into place

GSE3 moved outside of mid bay; moved in again, moved out again

GSE4 fwd dome outside tent 1 for scrapping [!] [it has been already stacked, but now cut off]

Steel parts delivered to production site

New black stand-like structure at PPS

PPS: parts lfted into grey circular mystery structure; circle now complete

OL Platform work continued

LR11350 extension work continued

bN3/B3 work continued with several man lifts up and work through access holes

OLS tank farm: more pipes installed and moved around near horizontal grey tanks

Two huge cylinders delivered to build site

Cryogenic vaporizor (heat exchanger for regazifying liquified gases stored as liquid under cryogenic temperatures) delivered to launch site

Work on booster transport stand (welding)

RC for today canceled

New RCs for Tuesday-Thursday (12pm-10pm)

Tweet by Elon Musk showing 9 raptor engines [RSN27 and RC59 identifiable, at least one RB]

NSF

Mary

LabPadre

[174]
08.07.2021 RB5 delivered (Raptor Boost Serial Nr 5)

RC for July 8 changed to 6pm-12am

BN3/B3 venting early in the morning [thrusters or pressure?]

BN3/B3 work continued with several man lifts up ahead of testing

BN3/B3 ambient pressure test

Thrust ram lifted into suborbital Pad B [not yesterday?]

PPS: Cryo tank shell construction work continued (shell #4 and shell #5 with new dome)

OLS Tank farm: more pipes have been installed, scaffolding tent removed

Liquid nitrogen delivered

OLS, IT: work at the base continued (east side base extension, more beams added)

OLM work continued

PPS: Natural gas generators delivered and installed

LR11350 extension work continued

Two nosecones outside tent 3, one with TPS tiles at flap attachment point

Land cleared next to production side (east)

NSF

Mary

LabPadre

[175]
07.07.2021 PPS: OLS IT: Segment #8 fourth column lifted at 9:26 am; cross beams added to fourth column; the column has an extension for ninth segment [?]

BN3/B3 work continued through the night

PPS: Cryo tank shell #4 work continued with stacking on next ring section; some first rings for shell #5 appear to be ready

GSE3 (fully stacked) and SN20 (two sections) now in mid bay

Tent 3: new ring section in production (with vertical strengthenings)

Between high bay and tents: Three 4-rings stacks with lead-ins ready for stacking

PPS: Grey circular mystery structure: New parts have been delivered; work continued

OLM work continued (5 man-lifts working simultaneously)

Work on yellow pipe structure continued [for OLS, IT?]

LR11350 boom disconneced and moved away by SPMT ahead of extension

Puck shucker lowered into Test Stand/Pad B at 5:48 pm

NSF

Mary

LabPadre

[176]
06.07.2021 PPS: OLS IT: Segment #8 fourth column arrived

LR11350 parts for extension arrived (boom parts and winch)

Single ring section stacked onto 2-ring section in front of tents [SN20/S21 aft section used on June 30??]

OL Platform work continued

BN3/B3 work preparation work continued

OLS, IT: More beams added to east side base extension [white winch likely installed now, see vid July 16]

LR11000 at OLS tank farm; moved new grey tank

Excavator picked up SN11 debris and placed it into scrap bin at launch site

PPS: More ducting installed

OLM work continued at cross beams

High bay top work continued; beam lifted and put into place

New RC [BN3/B3] for Thursday, July 8 (12-8pm); Friday, July 9 (6am-8pm); Monday, July 12 (12-8pm)

Puck shucker moved down hwy4 towards launch site at 11:02 pm

NSF

Mary

LabPadre

[177]
05.07.2021 Loadspreader and LR11000 detached from BN3/ B3 at 8:42 am

Inspection robot in tent checked a new ring section (3-ring with lead-ins)

BN3/B3 test preparations work continued with lots of wires and some piping installed; ventilation hoses run into booster

Small berm north of landing pad looking finished

OLM work continued

OLS, IT: More equipment installed on east side base extension

Work on orange pipes continued

Two SPMTs moved under GSE3 tank ahead of potential move; later moved towards entrance/mid bay[?]

OL Platform work continued

LR11000 moved towards OLS tank farm

PPS work continued with ductings lifted into place

High bay roof top work continued, only a few glass panels still missing

Gray circular mystery structure work continued

B4 aft tank #2 4-ring section with lead-ins moved between tents towards high bay area [still labeled BN4][vid 06]

A downcomer (LOX or CH4) has been moved into mid bay on July 5 at 10:42pm [LabPadre, Redstone, July 11]

NSF

Mary

LabPadre

[178]
04.07.2021 PPS: Cryo tank shell #4 work progressed; work on cryo tank shell #5 (of 7) began [?]

LR11350 extension work began

OLM: welding at the cross beams

Booster fwd dome [B4?], Starship aft skirt, S21 aft dome in front of tents

Work on a booster? barrel section (3-ring) inside tent 1

Welding work on booster transport stand

OL Platform work continued

Nosecone barrel section and nosecone still ready for stacking in front tent 3

Earth work east of mid bay area

B3 work continued

SN20 mid LOX section with tiles spotted on July 2 during lift into mid bay [Maria Pointer]

NSF

Mary

LabPadre

Maria Pointer

[179]
03.07.2021 4-ring barrel section with lead-ins inside high bay, likely with dome in it

SN20 common dome (3-ring stack) with lead-ins and TPS-tile cover spotted (passive pressure relief valve on it); hooked to crane and lifted into mid bay for stacking it onto Mid-LOX section (header tank visible)

3 Raptor engines delivered: RB3, RB4 ("RBoost - Engines without gimbal, with higher thrust and lower throttling ability" [incorrect according to Musk]), sign: "Hello my name is boost"; RC79 (Former RSN79 - RC for Raptor Center)

SN21/S21 thrust dome upgraded

B4 common dome on sleeving stand, sleeved with 4-ring stack ("CMN Dome Stiffend[?] Barrel")

Long tube moved to BN3/B3 at launch site (possibly a part of its raceway)

BN3/B3 work continued, still attached to LR11000

OLS, IT: More beams installed for east side base extension, first equipment installed [winch room in video July 16]

OLS tank farm work continued

PPS: Cryo tank shell #4 work continued

NSF

Mary

LabPadre

Oskar Wróbel

[180]
02.07.2021 OLS, IT: LR11350 disconnected from tower

LR11350 lowered for third extension RCs for July 6 and 7 cancelled

BN3/B3 secured on Pad A, still attached to LR11000; work at the base/stand; later, man lifts went up, work on booster through access holes

OLS tank farm only progressing slowly at the moment

B4 "comm dome" section (4-ring stack with some small holes in it) spotted

B4? fwd dome section and S21? aft section near each other after stacking test

GSE fwd dome on sleeving stand and sleeved later

GSE4 fwd dome section scrapped: fwd dome and a single ring has been cut off; remaining 4-ring section attached to crane and moved to scrap yard

PPS: Cryo tank shell #4 construction continued with welding

Booster transport stand at build site

High bay roof work continued

At least three nosecones under construction in tent 3

PPS: Work on unknown structure (tall, grey, circular) has progressed; some parts still missing

Work near base of SN15; pressurization rig for starship shown

OL platform work continued

NSF

Mary

LabPadre

[181]
01.07.2021 OLS, IT: Segment #7 lifted and stacked

BN3/B3 roll out (36-rings tall, engines won't be covered as with Starship, lowest ring is the aft dome; hot gas thrusters haven't been uninstalled, pipes sticking out of lower section side and huge COPV on other side); huge manlift went up to attach the load spreader of LR11000 to the booster; detached form transport stand, lifted onto Pad A by LR11000 [no engine section???]

New RCs for July 6 and 7 (7am-5pm) [likely for BN3/B3 testing]

NSF

Mary

LabPadre

[182]

June 2021[]

Date Description Source Link
30.06.2021 Potential starship aft section (2-ring stack) spotted

Potential B4 fwd dome sleeve (3-ring stack with fin attachment structures and thruster holes) spotted, moved outside tent

Deliveries to production site

PPS: Cryo tank shell #4 construction work continued

Three Raptor engines delivered! (RC57 identified)

Stage separation mechanism tested [?] between booster and starship sections: Starship aft section mated with booster fwd section by crane

Nosecone and nose cone barrel section with lead-ins outside tent 3

OLS tank farm work continued, man lifts up and ground piping installed

Berm work continued as well as hwy4 work

OLM work continued, all beams have been attached

OLS, IT: work continued; stairs installed to segment #7, moved towards crane, attached to LR11350

OLS, IT: More beams installed for west side base extension installed

LR11000 began moving towards Pad A, possibly for BN3/B3 lifting

PPS: OLS IT: Segment #8 fourth collumn missing

BN3/B3 work continued, later unhooked from bridge crane

GSE5 mid #2 section (4-ring stack with lead-ins) outside tents

Concrete poured in the base of OLS IT

NSF

Mary

LabPadre

[183]
29.06.2021 Super heavy booster transport stand staged next to high bay; later moved into high bay

BN3/B3 lifted onto transport stand; the section is 23 rings tall (engine section, LOX tank, common dome); some sort of fins have been installed on the engine section; lead ins on the common dome section, prepared for stacking

BN3/B3 fwd tank (CH4, 13? rings tall) stacked onto lower booster section; now at full height!

SN15 lift up, some work

GSE tank construction in mid bay

PPS: New grey sections being assembled, forming a circle; pars wore delivered on June 22

PPS: Ground work near propellant production plant

GSE5 tank midsection 1 (4-ring section with lead-ins) in mid bay

New mount sections delivered

OL platform construction work continued

New sign at stargate building

OLS tank farm contstruction work continued

PPS: Cryo tank shell work continued; shell #4 being painted

NSF

Mary

LabPadre

[184]
28.06.2021 PPS: Cryo tank shell work continued on shell #4 with stacking the 5-ring to stack onto another section and on shell #3 with welding (now apparently full height)

New barrel section with lead-ins spotted in a tent

IT: Segment #7 roll out to OLS; there appeared to be a slight problem as they needed to stop for a short time, they adjusted the weight distribution/horizontal alignment

OLM work continued, fifth beam added

Pad A modification work continued with support beams added to the super heavy adapter

New berm being constructed from Starhopper entrance gate eastwards (north of landing pad, indicating that SpaceX plans to use the landing pad in the future)

OLS, IT: LR11350 detached; elevator section for segment #5 lifted into place

OLS, IT: More beams installed for west side base extension installed

New RC (with beach) for July 1 (7am-3pm)

FCC: "SpaceX has filed for Starlink terminals to be flown on [orbital] Starship and Superheavy. FCC filing is for August 1st - October 1st." For SpaceX, this is a "logical extension" of the existing authorization to use Starlink on suborbital flights for demonstration

NSF

Tyler Gray

LabPadre

[185]
27.06.2021 BN3/B3 fwd tank section moved in highbay; work on booster continued

Celebration/party at Boca Chica with fireworks, party at high bay top

OLS, IT: Sixth tower segment stacked by LR11350 (lifted, crane moved forwards, lowered; guiding weights used); Fifth and sixth segment have no lift installed yet; segment #7 nearly ready for roll out

Pad A work continued

PPS: Cryo tank shell #3 work continued, fully stacked; work on shell #4 had commenced [date unclear]

Sleeved aft dome and new fwd dome sleeve outside the tents

OL platform work continued

S21 aft dome with vacuum raptor engine mounts spotted

First vacuum raptor engine delivered to Boca Chica build site

NSF

Tyler Gray

LabPadre

[186]
26.06.2021 Sections of new transport stand delivered

BN3/B3 work on fwd tank section work; the fwd dome spotted earlier this week has been stacked onto other fwd tank section (4-ring); another stack waiting outside

BN3/B3 fwd ring section spotted (4-ring stack)

BN2.1 and stand now near SN15 and 16

GSE tank fwd dome in tent

Pad A: Super Heavy test stand adapter mounted to Pad A, previously used as lower part of BN2.1's stand; according to Elon Musk it is planned to use B3 for testing on Pad and make a new booster for flight

Hwy4 roadwork continued; foundations laid for new berm from starhopper entrance eastwards

OLM: 4 of 6 curved cross sections now added

Staging areas for SH booster and Starship spotted next to the integration tower (one 6-column foundation, one 12-column foundations; both with quadratic pad with rebar) [RGV]

NSF

Tyler Gray

LabPadre

RGV

[187]
25.06.2021 BN2.1 and its test stand moved from launch site to build site (near SN15 and SN16)

Work on Pad A, preparation for Super Heavy testing

OLS, IT: segment #6 attached to LR11350

OLS, IT: first beam for west side base extension installed

PPS: Cryp tank shell #3 work continued

PPS: OLS IT: Work platforms added to segment #7

OLM: Second, third and fourth beam added between pillars (of total 5)

Work on a ring stack with lead ins

Round metal? parts delivered

New S21[?] thrust/aft dome sleeved (3-ring stack)

BN3/B3 fwd tank 2 section spotted

New intermittent RC for June 28 (11:30am-1pm)

NSF

Tyler Gray

LabPadre

[188]
24.06.2021 PPS: Cryo tank shell #3 work continued, shell #2 ready for roll out waiting at the gate

PPS: OLS IT: Scaffolding added to segment #7

BN3/B3 moved to the left in high bay; CH4 section work began with fwd dome connected to high bay bridge crane

GSE tank fwd dome on sleeving stand, another near tents

SN20/S20 aft dome in tent

BN2.1 lifting jig attached, removed from part of its test stand

LR11350 detached from tower, preparation work for connecting it to segment #6

OLM first cross beam added

Today's RC cancelled

OLS, IT: Segment #6 attached to LR11350

New intermittent RC for June 25 (10am-12pm)

NSF

Tyler Gray

LabPadre

[189]
23.06.2021 PPS: Cryo tank shell #3 work continued

PPS: OLS IT: Segment #7 looking finished

SN16: work around it, especially at the top

GSE3 tank work continued

BN3/B3 moved slightly in high bay [New naming scheme, B and S insead of BN and SN]

OL platform work continued

LR11350 still attached to tower

New intermittent RC for June 24 (3-5pm)

NSF

Tyler Gray

LabPadre

[190]
22.06.2021 BN3? fwd dome on sleeving stand

BN3? fwd dome sleeve moved and sleeved onto the fwd dome on the stand and moved into tent 1; new hot gas thrusters have been added at the top of the sleeve (for Reaction Control System RCS thrusters; "It is beleived these will burn methane and liquid oxygen")

Large hardware delivered to the PPS

PPS: Cryo tank shell #2 ready for roll out

OL platform work continued

Work at the top of the high bay continued

PPS: OLS IT: Segment #8 third column added

Starlink ground stations (white domes) delivered, three moved to the tracking station

Work on a ring section in tent 3

NSF

Brady Kenniston

LabPadre

[191]
21.06.2021 PPS: OLS IT: Parts and columns for segment #8 (smaller) arrived, first two columns lifted; work on segment #7 continued

PPS: Cryo tank shell #2 moved between 2.10 pm and 2.20 pm GSE fwd dome section has counterweight attached

LR1600/2 disassembly continued, parts loaded onto truck

Launch site: dirt/gravel work

Hwy4 work continued

Curved stainless steel sheets delivered

Mobile office section delivered to launch site [or left?], looking blast-hardened

OLS tank farm: work continued at GSE tank foundations with attachment pins being added

OLM work continued

NSF

Brady Kenniston

LabPadre

[192]
20.06.2021 Inspection robot working on a ring stack inside tent 1

GSE tank fwd section was rolled into tent 1

Ring section outside tents received top stabilisation ring

Work on transport stand

NOV ADS-30Q hoist (removed from Phobos) now installed on the IT base

LR11350 reattached to OLS IT

LR1600/2 parts at OLS

OLS: work on yellow pipes continued

Fwd dome caps spotted outside tents

NSF

Brady Kenniston

LabPadre

[193]
19.06.2021 LR11350 detached form OLS, IT; loadspreader detached

New Superheavy (BN3?) fwd dome sleeve spotted; first sleeve was likely a pathfinder

BN3? fwd dome sleeve mounted in the flip rig (which one?); later detached without flipping it

BN3 attached to bridge crane

Welding robot in tent 1

PPS: Cryo tank shell #3 stacking continued

LR1600/2 "Bluto/Tankzilla" now disassembled RIP

Hwy4 work north of launch site continued

OLS, IT: NOV ADS-30Q Drawworks hoisting system delivered, rated for a hook load of 1245 tons with 16 lines

GSE tank fwd dome spotted [?]

OLS, PB: a lot of equipment in the bunker installed

LR11350 lifted ADS-30Q onto the launch tower (on a steal construction at the base, south side)

PPS: Cryo tank shell #3 stacking continued [vid20]

GSE tank fwd dome spotted [vid20]

SN20 aft section in tent 1 [vid20]

Raptor engine partial combustion chamber and nozzle spotted outsides [vid20]

NSF

Brady Kenniston

LabPadre

[194]
18.06.2021 OLS, IT: Segment #6 rolled out to launch site

OLS, IT: Segment #5 still attached to LR11350

Rebar and shipping container delivered to launch site

Hwy4 work near OLS

OLS: New GSE pipes with orange part spotted

LR1600/2 "Tankzilla/Bluto" disassembly continued

PPS: Cryo tank shell stacking continued

Curved steel sections delivered, potentially for a new stand

WAI/RGV:

  • GSE Bunker: Compressed nitrogen tanks added
  • CH4 recondenser added between the two white vertical tanks
  • New foundation south of blast berm
  • New road/expansion of OLS extending southeast
  • Work around pad A: (water?) pipes; possibly for BN static fire
  • PPS: New building between LOX plant and airstream trailer park
  • SN15 kept under pressure, possible not simply a display stand
  • Gwynne Shotwell speach: Countdown/Timer released (likely time since first engine shipped for orbital flight)
  • OL platform: more hold down clamps installed
NSF

Brady Kenniston

LabPadre

WAI/RGV

[195]
17.06.2021 PPS: Segment #7 more cross beams added; segment #8 nearly soon ready for roll out, work plattforms added

PPS: Cryo tank shell work continued; shell #2 looks finished, work on shell #3 (5-ring) continued with stacking onto another section

Raptor van arrived, but no Raptors on board; one crata delivered, another returned to McGregor

OL platform work continued

High bay: more glass pannels installed

PPS: LOX distiller painted white

BN2.1 cryo proof test

Launch tower stands moved back to build site

Work on 3-ring barrel section outside the tents

New intermittent RC for June 18 (9-10:30am)

OEAAA information (June 14): LR11000 "to support SpaceX orbital launch site construction and launch operations [...] most frequently be at height of 350ft."; 18 month permit until 12/29/2022

NSF

Brady Kenniston

LabPadre

[196]
16.06.2021 PPS: OLS IT: Segment #7 cross beams added, segment #6 nearly complete

PPS: Cryo tank shell stacking continued

OLS, IT: Segment #5 stacked onto tower by LR11350 crane (attached to crane, lifted, moved forward, lowered)

SN16 removed from high bay, turned down Remedios Avenue, to display stand at PPS, near SN15; 1935 TPS tiles spotted

White GSE delivered

BN3 fwd dome sleeve unhooked and moved into tent 1

SN20 aft dome moved around

LR1600/2 "Bluto/Tankzilla" boom removed, possibly being disasssembled

NSF

Jack Beyer

LabPadre

[197]
15.06.2021 BN3 "booster 2" LOX section (20 rings) relocated, then stacked onto aft/engine section

PPS: OLS IT: Segment #7 all four columns lifted; work on segment #6 continued

BN? fwd dome sleeve hooked to crane (unknown 3-ring stack from yesterday)

BN3? fwd dome with attachment pins waiting to be sleeved

OL platform work continued

OLM work continued

OLS, IT: segment #5 prepared for lift and elevator installation

OLS: yellow GSE pipes mated; work at tank farm coontinued; concrete work outside OLS on hwy 4

LR11350 moved around, lifted the next temporary elevator section into OLS, IT

NSF

Jack Beyer

LabPadre

Elon Musk

[198]
14.06.2021 Unknown 3-ring stack with multiple holes and side attachments spotted, later removed from flipping rig and moved; potentially for booster (BN3?)

Starship SN21 or above thrust puck spotted

PPS: Cryo tank shell construction continued, work on shell #3 began with new dome stacked onto ring section

Test nosecon: tip removed

Semicricular steel parts delivered

Launch tower transport jig moved back to build site (by SPMTs)

Work on possible super heavy stand/mount continued

Hwy 4 road work continued

OLS, IT: LR11350 crane detached form tower

SpaceX recently purchased Massey's Gun Shop and Range on the way to Boca Chica; some sources have indicated "That this location will be the 'Raptor Facility' and possible uses may include repair, rebuild and testing of rocket engines."

RCs for June 15 and 16 canceled

NSF

Jack Beyer

LabPadre

Matt

[199]
13.06.2021 Lift up at SN15

PPS: Cryo tank shell construction and painting work continued

Test nosecone moved to scrapyard

OLS, IT: Load spreader attached to LR11350, tower segment #4 attached to crane, section partially unbolted from transport rig, safety meeting, segment lifted slightly, completely unbolted from transport rig, lifted a bit, rotated, let down a bit; LR11350 moved backwards, segment lifted, crane moved forwards, segment lowered into place at 6pm local

NSF

Jack Beyer

[200]
12.06.2021 LR11350 boom lifted and lowered again; work continued on crane

Cryo tank shell moved to LR11000, attached to crane and lifted; positioned west of GSE2

OLS work continued; nitrogen vaporizer moved to tank farm; earth work contineud

Road work on Hwy 4; currently only one way, traffic lights installed

Launch tower column delivered

PPS: Work on cryo tank shells continued; stacking continued on third tank (cryo #2, prev #3; possibly now 17+4 rings tall), welding

RSN72 "Philosoraptor", RSN74 "Plaid Mode" delivered; RSN56/59 plus one onknown RSN loaded onto truck

BN2.1: welders worked on the top of the test tank

NSF

Jack Beyer

LabPadre

[201]
11.06.2021 Water tank lifted at 9am, lowered at OLS tank farm, just behind GSE2; detached from LR11000

OLS IT segment #5 moved to launch site, arrived at 11:47am

SN20 thrust/aft dome sleeved (with 3-ring stack)

New nosecone barrel section spotted in tent

Parts delivered to OLS

NSF

Jack Beyer

LabPadre

[202]
10.06.2021 LR11350 lifted, work on jib, lowered again later [vid11]

Nosecone barrel section and nosecone still waiting for stacking; Nosecone: Section Serial 502B, For Nose Serial NC1B, WO# 1554305, Start date 1/20/21

OLM: work at the leg/extension joint

BN2.1 inspected

GSE pipe moved at launch site

High bay bar work continued

OLS work continued

GSE5 aft dome section (3-ring and dome) outside tent

Nitrogen vaporizer delivered; nitrogen tanks moved to launch site

GSE? fwd section moved

New RCs June 15–17 (12-8pm)

NSF

Jack Beyer

LabPadre

[203]
09.06.2021 OLS IT: Segment #4 rolled out

Water tank [prev. referred to as cryo tank shell #2] for OLS tank farm rolled out [first double roll out]

Concrete work at PPS

Load spreader attached to LR11000, water tank attached to it later

OLS: earth work

PPS: Cryo tank shell #3 stacking progressed

PPS: OLS IT: More cross beams added to segment #6

New intermittent RC for June 11 (10.30-11.30am)

NSF

Jack Beyer

LabPadre

[204]
08.06.2021 Intermittent RC for today cancelled; testing closure extended to 10pm

PPS: tank #2 moved, work continued; Cryo #3 (now cryo #2) work continued

Cryo #2 now confirmed as water tank, thus not as a cryo tank shell

PPS: OLS IT: Work on segment #6 continued and fourth column added, cross beams added; segment #4 ready for roll out, moved closer to hwy 4

New dome on sleeving stand

Ring segment (3-ring) with hole spotted in tent

Temporary elevator parts delivered

OLS: work around PB continued; work on and around horizontal GSEs continued

OLM: work at the welds between leg and extension

BN2.1 Cryo proof test

Huge pipes and other equipment delivered

Container and wind radar moved by SPMT

New intermittent RC for June 9 (8.30-10.30am); RC for June 09 (12-8pm) cancelled

NSF

Mary

LabPadre

[205]
07.06.2021 PPS: OLS IT: Work on three segments continued; scaffolding on segment #4 nearly complete; more columns delivered; segment #6 third column added; launch tower braces delivered

PPS: Work on second cryo tank shell (weld) continued; work on third cts continued

Stainless steel rolls delivered

High bay: top glass work continued

OL platform work continued

OLS work continued; pipes fitted and removed at east horizontal GSE tanks

LR11350 extension now attached, work continued

Intermittent RC for today cancelled as well

New intermittent RC for June 8 (9.30-11.30am)

McGregor: At least 3 engine tests of different length

NSF

Mary

LabPadre

Reagan

[206]
06.06.2021 BN3/booster 2 methane downcomer delivered, lifted into high bay

PPS: OLS IT: Segment #6 work coninued, second column lifted

PPS: Work on second tank continued, third cryo tank construction began

LR11350 extension work continued

Pipes delivered to OLS

OLS work around horizontal GSEs continued

RC for Monday afternoon cancelled

"Mini Bakery" delivered ("The Bakery = heat shield manifacturing facility in Cape Canaveral, Florida)

NSF

Mary

LabPadre

[207]
05.06.2021 PPS: Cryo tank shell #2 now some 22 rings tall; welding work

PPS: OLS IT: scaffolding installation at segment #4; work on segment #5; first column of segment #6 lifted

Crane claw attachment delivered

LR11350 extension work continued; new 2-armed jib installed

OLS, IT: Staircases removed as elevator now is operational

OLS: work around horizontal GSEs continued

BN2.1 preparation work continued

OLM: Fifth and sixth (final) extensions added to legs

OLS, PB: ground equipment delivered

Berry crane Grove GMK6350L at PPS

SN20 "aft" dome spotted

NSF

Mary

LabPadre

[208]
04.06.2021 BN3 stacked onto another 4-ring section (now 20 rings tall) [Booster section#5?]

OLM: Fourth leg went up for third time at 7:46am

BN2.1 work near Pad B, pressure and thrust tests expected soon

[SN20?] nosecone and barrel section still outside tent three

PPS: OLS IT: work ont segments #4 and #5 continued

PPS: Work on cryo tank shells continued

High bay work continued

OL platform work continued

Work on a new stand commenced; with black side extensions [!, some suggest for launch platform]

LR11000 moved to pad north of OLS tank farm; possibly awaiting new GSE/shells to arrive

OLS: insulated pipes installed around western horizontal GSE tanks; earth work continued

LR11350 extension work continued: boom tip removed, new jib prepared

BN3 "fwd 3" section (3-ring stack) spotted near tent 3

SN14 practice dome weld area cut out

New intermittent RC for Monday, June 7 (10:30-11:30); possible segment #4 roll out

McGregor: 15sec static fire of the new vertical raptor test stand for first time (5.30pm)

NSF

Mary

LabPadre

Reagan

[209]
03.06.2021 SN7.2 moved to an unknown location (12:52am)

OLM: Fourth extension lifted at 9:54 am; later removed; up again, removed again

BN2.1 (test tank on test stand) moved to the launch site

New RCs Mon-Wed June7–9 (12-8pm), possibly for testing BN2.1

GSE6 Mid #1 stack spotted

SN14 sleeved dome, reused to test Raptor vacuum mounts and Boster outer engine mounts; now SCRAP

PPS: Second cryo tank shell stacked onto next ring section

PPS: OLS IT: Work on section #4 continued; cross beams added to segment #5

BN3 Booster Section #5, 4-ring section with lead-ins prepared for stacking

SN17 engine section at scrap yard (near SN5)

SN7.2 at scrap yard (near SN5)

OLS, IT: Work continued (elevator); segment transport mounts moved back

Unknown roll delivered

Crane Berry, gmk6350L moved

OLS: pipe work; dirt work

LR11350 extension work began

GSE7 "fwd dome" (not stack #2) barrel section spotted, 2-ring stack

Robots in tent 3

NSF

Mary

LabPadre

Starship Gazer

Austin Barnard

[210]
02.06.2021 New intermittent RC for June3 (2-4pm)

PPS: Piping added to second cryo tank shell

PPS: OLS IT: segments #4 and #5 work continued; third and fourth columns lifted

PPS: Cement work

OLS, IT: Work continued, elevator installation continued

OLS, PB: Work continued

OLS: Horizontal GSE tanks (east) received some pipes ["Subcoolers, chill LOX and CH4 to near their freezing point to maximize efficiency", NSF]; wor at and around the tank farm bases continued; Dirt work near exesting berm

SoLS: "Seems to be a staging area for OLS components and equipment" [NSF]

Header tank assembly jig spotted on a truck

SN11 remains left Boca Chica

NSF

Mary

LabPadre

[211]
01.06.2021 OLS: Four horizontal GSE tanks placed onto stands east of tank farm (2 more empty foundations) [likely on May 31?]

Unknown GSE parts delivered (big steel pipes/tanks), Five blue/white Diesel generators from Leroy Somer delivered

Crane inspection

OLS: Rebar placed north of tank farm for pad extension (west of new pad) and later concrete poured; the two horizontal GSEs (for subcooling propellant) west of tank farms received some piping on top

PPS: OLS IT: Work on segment #4 continued; later segment #5 first column lifted at 5:15pm, second column lifted at 6:03pm

PPS: Work on second cryo tank shell continued, stacked onto another ring section; welding of some ring section; the second tank has another dome than the others - possibly for water storage [?]

OL platform work continued, some welding; 8 hold down or support clamps/arms now installed [RGV]

LR11350 crane detached from OLS IT; crane lowered later for boom extension

OLM: third cap/extension installed

NSF

Mary

LabPadre

RGV

[212]

May 2021[]

Date Description Source Link
31.05.2021 Memorial Day - mot much work

Downcomer pipe section delivered

BN2.1 test tanks lifted onto new test stand for thrust test (Modified nosecone stand)

OLM: second leg cap/extension added

SN15 has been bolted onto a display stand

NSF

Mary

LabPadre

RGV

[213]
30.05.2021 The SH thrust puck is for the 9 center, gimbeling Raptor engines

PPS: some minor work on shells and IT segment continued; SN15 still on stand

3 Raptor engines spotted in a van, likely the SN15 engines for sending them back to McGregor

Two launch tower stands still on launch pad

OLS IT: LR11350 still attached to segment

OLM some inspection at the top of a leg, later first launch mount leg cap installed on it

OL platform work continued

BN2.1 left mid bay, moved next to tent 3, near thrust shucking stand

Deimos under construction for launch next year

Orbital duration static fire of a Raptor engine at McGregor for first time!

NSF

Mary

LabPadre

Elon Musk

Teslarati

[214]
29.05.2021 GSE7 stack #2 fwd dome spotted

Super heavy thrust puck delivered [BN3?], confirming a total number of 29 engines (adding a center engine), which was confirmed by Musk [later to be risen to 32]

BN2.1 puck shucking stand hydraulic rams installed

PPS: second cryo shell stack continued

New ring sections spotted at the production site

Some sort of lift moved into tent

Starship fwd dome (stacked and flipped) hooked to crane [SN20??]

IT segment still remained attached to LR11350

OLS: concrete poured north of tank farm (rebar laid on May 27–28)

SN11 wreckage cleanup, some still lying around

Two large horizontal GSE tanks moved east of tank farm

High bay work continued

Air force budget for a research project "Rocket Cargo" involving Starship released

Raptor production at 48h/engine

NSF

Mary

LabPadre

Elon Musk

[215]
28.05.2021 SN17 destacking: mid LOX and cmn dome section cut in two

PPS: cryo tank shell moved to launch site

OLS, IT: segment #3 attached to LR11350, stacked onto segment #2 ("Klein Tool")

LR11350 parts unloaded (arrived yesterday)

Large grey tank delivered to the launch site, as well as more crane parts (ropes)

OLS: work north of tank farm continued

Rolling 5000 ft TFR added (June 1 - July 31)

NSF

Mary

LabPadre

[216]
27.05.2021 OLS IT: Ladders installed to third segment, moved to launch site; elevator installed on stacked sections (McDonough elevator)

PPS: OLS IT: work on fourth segment continued, some parts at the top removed [?]

BN3: stacked to 16 rings, with common dome on top

New nosecone still outside tent 3, near barrel section with heat sheet tiles and lead ins [SN20?]

Starship 3-ring common dome full with TPS mounting pins [SN20?]

PPS: Cryo tank shell work continued, crane disconnected from second stack; full stack moved a bit

Robotic welder moved

OL platform work continued

Prefabricated buildings delivered

OLS: rebar laid north of tank farm for new pad and earth work continued (lower level than farm, same as street); concrete work

Robotic dog walked around

LR11350 parts delivered for boom extension

New RC intermittent for May 28 (10am-12pm)

NSF

Mary

LabPadre

RGV

[217]
26.05.2021 LR11350 moved/turned

OLS work continued, insulated piping delivered

RC extended to 5pm

SN15 put on transport stand, moved up Hwy 4, turned into Remedios Avenue, parked near nosecone test rig at PPS

New intermittent RC for May 27 (2.30-5pm)

PPS: OLS IT: Segment #3 prepared for roll out as work platforms being attached

Pipes delivered to production site

PPS: Cryo tank shell #2 stacked onto another ring section

OL platform: hold down clapms spotted, firs one installed on the inside

Test tank spotted in Mid bay [BN2.1]

Modified test stand to work as new puck shucker for SH test tank BN2.1 as hydraulic cylinders are visible inside the structure [the_denks]

BN3 stacking continued [?]

Phobos dismanteling work continued

NSF

Mary

LabPadre

RGV

Nomadd

Shane Overvold

[218]
25.05.2021 New intermittent RC for May 26 (2-4pm)

SN15 attached to LR11000

OLS: concrete pouring at access to OLS tankfarm as well as south of it, work on tank farm continued (GSE tanks and foundations)

BN3 (some 12 rings high) moved in high bay, new stack moved into it and attached to bridge crane, stacking continued; LOX tank now at the bottom according to Elon Musk (unlike BN1)

LR11350 (Kong/Frankencrane) detached from IT, load spreader removed

PPS: OLS IT: work on segments continued

PPS: Second cryo tank shell work continue, as well as piping on first tank

BN3 aft tank #5 section (4-ring, with lead-ins) spotted

Crane moved to launch site

High bay work continued, more glass pannels installed

Nosecone test stand modifications continued

OLM work continued

OLS, PB: containers lifted on roof of PB

NSF

Mary

LabPadre

RGV

[219]
24.05.2021 9m transport stand moved to launch site together with counterweights, possibly for transporting SN15 back

OLS, IT: segment #2 attached to LR11350 load spreader, detached from stand and lifted. Crane moved forwards, segment lowered and stacked onto existing structure

OL platform work continued

PPS: Cryo tank shell work continued, second shell growing

Nosecone test stand modified

SN20 common dome with CH4 header tank still outside tents

LR11000 rolled toward Pad B, SN15

NSF

Mary

LabPadre

[220]
23.05.2021 BN3 section lifted in high bay, stacked onto new section

PPS: Cryo tank shell work continued

OLS, IT: Segment #2 prepared for stacking, assisted by LR11350; work on segment #1 [built] continued; stacking loadspreader attached to LR11350; work lift lifted into the base

GSE parts [see May 20, possibly for prop subcooling, vaporization or recondensing] moved, stacked on the new concrete foundations ("pedestals") west of OLS tank farm

OLS: more pipe channels put into place west of OLS tank farm

OLS: valves and piping arrived; steel structures lifted into place at tank farm

New Starship [5-?] ring section with a lot of TPS tiles in a new arrangement and lead-ins moved out of mid bay [SN20?]

SN15 flaps tested (4:53pm–5:15pm)

SN20 aft dome near high bay

BN3 fwd tank #4 booster section spotted

Robot arm worked on nosecone in tent 3

SN17 section now cut out

NSF

Mary

LabPadre

Starship Gazer

[221]
22.05.2021 SN21 common dome [not yet stacked] now for GSE5 (fwd dome)

GSE5 fwd 2-ring stack spotted

GSE5 fwd dome "Stack #2" lifted onto sleeving stand, sleeved later

New section in tent 1

OLS, IT: work continued, work platforms added to the top of the first segment

SN7.2 probably going to scrapyard

PPS: OLS IT: Work on segment continued

PPS: cryo tank shell work continued, again attached to crane, stacked onto new ring section, looking like a rather difficult task

Nosecone test stand modified

OL platform: work on the inner structures continued

Work on a heavy duty transport stand

OLS: concrete plates added east of tank farm; concrete plates removed west of tank farm

SN15 work continued

Some damage to one of the satellites

NSF

Mary

LabPadre

[222]
21.05.2021 IT section #2 started to move to launch site (landing pad) at 8:15 am, ladders installed on the inside of the section

LR11350 raised, apparently in a small configuration that will need to be extended for stacking upper segments

SN20 common dome spotted (3-ring), covered in TPS tile attachment pegs, with lead ins, CH4 header visible

SN21 common dome spotted [Starship Gazer

GSE aft section (3-ring) with reinforcement and lead ins next to SN20 cmn dome [GSE5?]

SN17 section outside mid/high bay, some tiles cut out [mid lox&cmn dome stack]

More 4-ring stacks with lead-ins spotted

SN15: RSN54 removed, as well as a second raptor engine and third engine later, brought back to build site

BN3? fwd dome spotted

OLS, IT: Preparation work for stacking

Tent 3: two nosecones inside it, one nosecone outside it

According to Marcus House: BN3 stack in high bay is common dome on fwd LOX section (total of 8 rings). GSE4 in mid bay has been stacked this week onto its aft section, now complete.

Marcus House: Combinations SN20-BN3, SN21-BN4, SN22-BN5, SN23-BN6, then major upgrades for SN24-BN7

NSF

Mary

LabPadre

Starship Gazer

Marcus House

[223]
20.05.2021 PPS: OLS IT: Scaffolding erected on top of a segment, possibly for some stacking at the site [?]

PPS: cryo tank shell work continued, segments lifted and stacked

SN15 inspection/work

OLS building east of tank farm concrete poured

SN11 wreckage still not fully cleaned up

GSE equipment (4 greay tanks with 4+ inlets) delivered to launch site

OLS, IT: work continued

High bay glass work continued

Test nosecone rig disassembly continued

PPS: pipes and tanks delivered

New nosecone rolled out (without flaps), barrel section with work platform near it

Intermittent RC May 21 (09:30-12:00)

NSF

Mary

LabPadre

[224]
19.05.2021 HLS bill modification: selection decisions or awards that were announced prior to the date of enactment shall not be recscinded, terminated or modified

Thundersotrm in the area, some damage at the production site; crews left site

BN3? CH4 assembly spotted, 28 pipes for all 28 enginges "Super Heavy Propellant Manifold", feeding methane to engines from downcomer

Nosecones in tent 3 [SN17?, SN20?]

Tent 1: Robot working on new ring stack

LR11000 fully assembled

LR11350 "Frankencrane/Kong" nearly complete, hookblock attached

PPS: OLS IT: Assembly work continued

PPS: Cryo tank shell work continued

High bay: more glass panels installed for bar

BN3 in high bay [consensus]

OL platform work continued

OLS work continued, new concrete bars east of farm, earth work north of farm, building work west of farm continued

OLM legs now full of concrete, curing done [RGV]

NSF

Mary

LabPadre

RGV

[225]
18.05.2021 LR11000 "King" assembly continued, raised

LR11350 crane assembly continued

GSE4 aft parts lifted into mid bay [where the rest of GSE

Test dome put on sleeving stand, Rvac engine mount visible

PPS: Cryo tank shell construction work continued; dome lowered onto a new ring section

PPS: OLS IT: work continued

OLS tank farm work continued, as well as earth work around (N, E, W) it; SW foundation

Mysterious new parts delivered to build site

Scrap 2-ring barrel section hooked onto crane for sleeving, sleeved with test dome

Earth work near launch site entrance, north of landing pad

NSF

Mary

LabPadre

[226]
17.05.2021 PPS: OLS IT: Level four fourth column lifted at 9:17am, work on other segments continued

PPS: Lift moved into the shell stacking area

OLS work continued, earth work between berm and OLS tank farm, as well as between it and PB

LR11000 assembly continued by the help of Tankzilla/Bluto, counterweights and boom parts delivered

SN20 fwd dome outside tents (not stacked yet)

Three ring section outside tents

OLS, IT: Work continued

OLM work continued, welding of rod caps with mount legs

OLS tank farm: NW foundation concrete plates removed

Test dome spotted outside tents

STARBASE sign and coloured lights [vid May18]

NSF

Mary

LabPadre

[227]
16.05.2021 LR11000 (max 1000tons, 220m) assmebly began/continued; Bluto/Tankzilla assisting hereby; more parts delivered (trucks waiting in lane at entrance of launch site)

LR11350 "Frankencrane/Kong" assembly continued; power boom part nearly finished

OLS work between tank farm and PB continued

PPS: OLS IT: Work on fourth level continued

PPS Cryo tank shell assembly work continued

PPS wiring at the outside of container wall, conduit laid near STARBASE sign

New nosecones in tent 3 [?]

SN15 being inspected thorugh access hatch; starling dish inspected

Cidco Road: (New) piece of equipment now erected, as high as the remaining section of Mk2; some suggest it to be an ISRU Methalox part for fuel Starships

SN20 MID-LOX and Leg skirt spotted (again)

BN3 fwd tank #3 spotted

NSF

Mary

LabPadre

John Winkopp

Starship Gazer

[228]
15.05.2021 OLS work continued, new building foundations between tank farm and berm

Crane mats placed north of tank farm

BN2/BN3 section in high bay rotated

Test nosecone disassembly continued

PPS; OLS IT: third column added on fourth level

PPS: work on cryo tank shell continued

STARBASE sign installed at PPS container wall, letters ignited in the evening

Marcus House: Tank farm speculation: 1 nitrogene tank, 3 oxygene tanks, 3 methane tanks (2 rings shorter, higher concrete foundation), 1 water tank; capability for 2 full stack launches

NSF

Mary

LabPadre

[229]
14.05.2021 RC for today cancelled

SN15 lifted onto Pad B; 8:58am; flaps closed at 09:02am

FAA: "SpaceX mus meet all licensing requirements before Starship/Super Heavy can launch"[230]

PPS: OLS IT: Level/Segment 4 work began with first column being lifted, more columns delivered

Red crane parts delivered to launch site

Work on SoLS Pad A as well as Pad B

LR11350 crane assembly continued

OLS IT: work continued

OLS tank farm work continued

OLS: concrete plates for new building? between tank farm and berm

PPS: cryo tank shell assembly work continued

Test nosecone scrapping continued

OL platform work continued

SN15 lifted from SPMT by Tankzilla/Bluto; SPMT moved away, flaps retracted, lifted onto pad B; SPMT left launch site

Nosecone test rig moved behind PPS [vid 15]

"Bob" Test nosecone dismantling continued [vid 15]

SN15 unhooked from Bluto/Tankzilla on pad B (previously on pad A) [vid15]

New crane LR11000 parts delivered to launch site [vid15]

Bluto/Tankzilla moved [vid15]

Super heavy booster section moved into high bay for stacking, BN2 or BN3 [vid15]

NSF

Mary

LabPadre

Chris B

[231]
13.05.2021 PPS: OLS IT; Parts delivered, work on the sections continued

PPS: cryo tank shell scaffolding

OLS tank farm work continued, concrete poured at NW foundation

Box culvert parts moved for underground pipes

LR11350 ("Kong/Frankencrane") assembly continued

OL platform work continued; coverings inserted on the outside

High bay: window installation continued

Work on an incomplete dome section

FCC: orbital test flight information, NET June 20

SpaceX

NASA: awarded SpaceX a $50 mio contract for "on-orbit large scale cryogenic propellant management and transfer demonstration" [=refuelling], to be completed by gthe end of 2022

"Bob", test nosecone scrapping began; top section removed

OLM construction work late night [video next day]

Nosecone test rig disassembly continued [video next day]

Bob: Cut in half [video next day]

SN17 MID-LOX tank section next to tent 1 [video next day]

NSF

Mary

LabPadre

Michael Baylor

[232]
12.05.2021 Test nosecone rig: Cage lifted by bridge crane, nosecone rolled out, cage lowered again

RC for May 14, (10am-12pm, intermittent)

PPS: Cryo tank shell work continued

SN15 waiting to lifted onto Pad B

SN15 work on the base, around the skirt area

OLS tank farm work continued

LR11350 assembly work continued, more parts delivered

PPS: OLS IT level 2 work continued; lift caps installed on a segment

Delivery of steel [IT?] parts to build site

Elevator delivery to build sited

PPS: new yellow crane delivered [see video yesterday as well]

NSF

Mary

LabPadre

[233]
11.05.2021 Loadspreader attached to Bluto/Tankzilla

SN15 moved to SoLS pad B, attached to Bluto/Tankzilla

LR11350 crane assembly continued, becoming very colourful, more parts delivered

OLS, IT: work continued

Steel parts delivered to launch site

SN11 cleanup continued

Nosecone test rig moved back to build site, into high bay, bridge crane removed cap, closeup shows clear dents

OLS tank farm, concrete plates added to wester GSE foundation as well as south Easter (high) foundation

OLS, PB: work on ground equipment around the building

PPS: cryo tank shell stacked onto next part

NSF

Mary

LabPadre

[234]
10.05.2021 SN17? and another nosecone in tent 3, flap mounting hardware visible

GSE4 aft dome flipped

GSE4 stacking in mid bay [fwd dome section onto other section?]

Test nosecone flap pieces now at build site

PPS: Cryo tank shell work continued, welds checked and analysed

PPS: OLS IT work continued

OLS tank farm work continued

OLS, IT: work continued

LR11350 "Kong" assembly continued

GSE2: special object hanging down from aft dome

SoLS Pad B work

Manitowoc 12000-1 crane moved to OLS tank farm area

Liebherr LTR1220 moved down the road to launch site, soft closure between 8:50-9:15 am

White poles ? delivered to build site

Test nosecone rig loaded onto SPMTs [video May 11]

Tankzilla/Bluto moved to SoLS pad B [video May 11]

LR11350 crane parts delivered, assembly continud [video May 11]

RC for May 11 (12-2pm, intermittent)

NSF

Mary

LabPadre

[235]
09.05.2021 OLS, PB: Much GSE equipment around it

OLS tank farm: concrete plates removed, two high foundations appear to be ready soon.

SPMT loaded with counter weights

Nosecone test rig work continued

High wind warning through loud speakers

SN16 work continued; work platform being removed

Big white tank delivered to PPS; now there are three white tanks

PPS: work on cryo tank shell and IT continued

High bay: first glas panel for roof bar installed

OL platform work continued

NSF

Mary

LabPadre

[236]
08.05.2021 SN16 moved to the side of high bay, possibly to make place for booster assembly

SN17 section (7 rings tall, with lead ins, upper part with many TPS tiles, some damaged), one stack called Mid-LOX, moved out of mid bay [Mid LOX and common dome, possibly indicating a hold

PPS: OLS It: Work on both level continued

PPS: Work on cryo tank shell assembly continued

OLS tank farm work continued

OLS, IT: work at the top

OLS: Work between PB and tank farm, earth piles visible

SpaceX crane GMK7550 moved at launch site (to OLS tank farm)

Work on nosecone test rig

Tent 3: Work seems pretty finished

Electrical transformers delivered to launch site

Phobos, Deimos: SpaceX request to use Starlink terminals on board the platforms

Phobos: Remaining towers, some of the room-structures and other objects removed [Shane Overvold, Levy]

NSF

Mary

LabPadre

[237]
07.05.2021 SN15 saving continued: legs appeared to be crampled, at least one TPS tile missing, some have been damaged during flight

OLS tank farm work continued with concrete pouring and other

SN16 detached from crane and work platform removed, second aft flap added

PPS: OLS IT: work on both level continued, level 3 received fourth pillar

PPS: work on cryo tank shells continued; big stack lowered into scaffolding

3-ring dome sleeve spotted

OL platform work continued

SN17 nosecone barrel section with lead ins and work platform

LR11350 moved to OLS (IT)

SN20 mid LOX section (4-ring stack) spotted

SN15 moved to center of landing pad

OLS, IT: work on top of level 1

SN15 landing legs removed, some of them looking burnt a bit

BN3? common dome flipped (3-ring and dome)

Test nosecone rig: both flap simulators removed

NSF

Mary

Jack Beyer

LabPadre

[238]
06.05.2021 SN15 saving continued; lift went up 06:06-07:02, working on right fwd flap and later put on mega SPMT; aft flaps extended

PPS: OLS IT work continued on both levels

PPS: cryo tank shell work continued; 5 ring stack stacked onto high (8-ring?) stack

GSE3 work on plumbing continued

Delivery of unknown white carriage like structures to build site

OL platform work continued

BN3 fwd tank #2 section (4-ring) spotted

SN6 remains moved to scrap yard

SN16 work continued; received one aft flap

Tankzilla/Bluto moved to region of pad A

RC from yesterday extended to 12pm

RC (intermittant) for May 7 (10–12)

NSF

Mary

Jack Beyer

LabPadre

[239]
05.05.2021 SN15 successful flight and landing

GSE3 work continued

BN3 aft dome still attached to flipping jig

SN16 remained attached to bridge crane, work platform still there

OLS tank farm: work on tank foundations continued

PPS: cryo tank shell work continued; the tank in the scaffolding lifted; three more domes ready

PPS: OLS IT: level two assembly continued (top beams added); level three third column added

NSF

Mary

LabPadre

others

[240]
04.05.2021 SN15 flap testing at 6:22 am, as well as later in the morning; FTS armed

SN15 scrubbed flight attempt

SN15 pressure vents (double depress)

OLS, PB: work continued

OLS, tank farm: progress on foundations; third foundation now ready [?]

Landing pad: more water deluge system sprinklers installed [date unclear]

BN3 aft dome flipped and placed on a cart

GSE4 fwd dome section attached to crane

SN16 still attached to crane

GSE3 pipe work continued

New 4-ring stack with lead ins spotted outside tents

PPS: OLS IT: level two more cross beams added; level three: two columns raised and cross beams added

PPS: Cryo tank shell now painted white

OL platform work continued

NSF

Mary

LabPadre

[241]
03.05.2021 BN3 aft dome section attached to flipping rig

SN16 still attached to crane; crews entered through access hatch

PPS: Cryo tank shell dome sections stacked onto another section (now probably 8 rings tall)

PPS: OLS, IT level two: more cross beams added; fourth column raised

New thrust puck delivered

Painted chair arrived at boca chica village

Deliveries of steel parts to build and launch sites

OL platform work contineud

OLS: work between PB, tank farm and hwy 4 continued ("Raptors Loose")

OLS tank farm: concrete plates with weird shape for north eastern foundation

SN15 preparation work continued

PPS: cryo tank shell dome painted

RCs for May 4–5 (12-8pm) added

NOTMAR added for May 4–6

TFR unl added for May 6

SN15 ambient pressure test

Alert notice issued for May 4

NSF

Mary

LabPadre

[242]
02.05.2021 Nosecone "Bob" in test rig has been undergoing stress tests as buckling of panels visible

SN15 ambient pressure test

PPS: OLS IT level 2: cross sections and third column added (at 10:25am)

PPS: More solar panels added

SN17 nosecone barrel section in front of tent 3; attached to crane

SN16 still attached to crane

Single ring sent to scrap yard

High bay work continued

Tent 3 work continued; apparently getting a second east gate

OLS: work between PB, tank farm and hwy 4 continued ("Raptors Loose")

OLS: tank farm work continued (foundations)

OLM: caps (the ones with rods) being welded to the legs

SN15 work on aft section

Alert notice issued for May 3

TFR unl added for May 5

TFR for May 3 removed

NSF

Mary

LabPadre

[243]
01.05.2021 TFRs for Monday and Tuesday added

TFR for Sunday removed

OLM: Leg grinded

GSE3 soon ready for roll out; work through access hatch

NSF

Mary

LabPadre

[244]

[245]

April 2021[]

Date Description Source Link
30.04.2021 SN15 scrubbed flight attempt

Evac notice for 10am, depending on weather

SN16 nosecone moved to high bay, attached to bridge crane; stacked onto tank section

GSE3 (fully stacked) still attached to crane, more pipes added

SN17 nosecone barrell section full with heat shield tiles in front of tent 3; work platform erected, attached to crane

Single ring "Super stringer stack" spotted

OLS, PB: entrance gate added

OLS work continued (e.g. at tank farm)

PPS: Assembly of second OLS IT level (construction at PPS, then the whole level will be transported to the OLS and put onto the current columns)

PPS: Cryo tank shalls construction work continued

OLS: the two tanks now painted white

Berm work continued

OL platform work continued

Video shows collection of earth movers

Raptor RSN? "insert meme here" delivered

Alert notice for Saturday issued, but no RCs

New TFR for Sunday (two identical TFRs); one TFR for Sunday removed

TFR for Saturday removed

NSF

Mary

LabPadre

[246]
29.04.2021 SN17 nosecone work in tent 3

OLM: more caps delivered

New 3mm stainless steel single ring spotted

GSE3 aft dome section work

GSE3 hooked to crane, stacked on aft dome later

SN5 and SN6 at scrap yard

Raptor van with crates

OL platform work continued [again]

Vacuum raptor engine (RVac) mounts spotted

PPS: 12m dome with single ring lifted

Downcomers delivered

OLS, PB: surrounding work continued

Berm work continued

OLS, IT: ready for next level

SN15 work under skirt

LR1300 moved, and left launch site together with Tankzilla/Bluto

SN11 debris cleanup continued

SN15 FCC approved starlink antenna from April 28 to June 28

Landing pad repair work finished

FAA authorized the next THREE Starship launches

Alert notice issued for tomorrow

TFRs from Fri-Sun

OLM all center supports cut off

SN16 moved from mid bay to high bay (19:27-19:48)

SN15 FTS installed at 22:26-00:44

NSF

Mary

LabPadre

Tank Watchers

Christian Davenport

[247]
28.04.2021 SN16 nosecone removed from crane; a stack covered with TPS tiles near it

GSE [GSE4 fwd?] dome on sleeving stand, sleeved with 3-ring stack

RSN59 [?] delivered "The Mighty DOGE"

RSN55 loaded onto raptor van, probably left

3/4-ring stack moved into mid bay

OLS work continued

OLS, IT: four columns connected

The two blue (military grey) tanks to be painted white

OLM: support structure beginning to be removed

Berm work continued

SN15 broken TPS tiles removed

Landing pad repair work

OL platform work continued

SN15 flaps unchained and unfolded

RC for April 28–30 (12-8pm/8am-5pm)

NOTMAR for April 29 and 30

SN17 common dome (3-ring stack full with TPS tiles) moved into mid bay; stacked on its LOX tank section (4-ring stack)

TFR for 29 April removed

Road closed at 16:35, pad clear at 18:32, Nosecone test; road opened at 19:48

NSF

Mary

LabPadre

[248]
27.04.2021 SN15 Static Fire #2

SN20 aft dome being constructed

SN16 Nosecone work continued, still attached to crane

Stainless steel rolls delivered

OL table work continued

COPVs delivered on Raptor van

PPS 12m "cryo tank shells, top dome" work continued, "cryo shells may potentially be used to insulate cryogenic storage tanks"

PPS: parts of OLS IT

OLS, IT: work continued

Work between PB and tank farm continued

OLS, PB: concrete poured on the ground

OLM work continued

SN15 some TPS tiles damaged during static fire #1

OLM cap [?] see April 22, delivered to launch site

Blast berm work continued

Red crane loaded on SPMT at launch site

TFR for April 28 removed

TFR for April 29 added

NSF

Mary

LabPadre

[249]
26.04.2021 SN15 Static Fire #1

Fwd dome sleeved on a 4-ring stack [?]

GSE 2-ring and 3-ring stack from yesterday

GSE3 aft dome section, ready for stacking

SN16 nosecone stacked on its barrel section

OLS berm work continued; more earth work on the east side of it

OLS, IT: cross beams added between columns, both vertically and horizontally; more columns delivered

OLS, PB: work continued; red roll-lift near it

OLS tank farm: concrete form being added to fifth foundation; earth work between it and PB

OLM work continued

Tankzilla/Blute loaded on SPMT

PPS: Huge 12m diameter domes; work continued; supposedly for putting over GSE tanks for insulation?

Phobos: derrick tower removed, much of the helipad and accommodation block as well [Gavin Cornewll]

RC 26–28 April (12-8pm)

Blue Origini protest about NASA HLS selection

Alert notice for April 27

NSF

Mary

LabPadre

Gavin Cornwll

[250]
25.04.2021 TFR unl added for April 28

OLS, IT: Fourth column lifted again, cranes moved; work for 143 meter tower continued

BN1 final section hooked to crane for scrapping

GSE3 work on pipes continued

OLS, PB: concrete forms removed

OLS Tank farm: Work on the two next concrete foundations continued, seem to be taller thant the two for GSE1 and GSE2

Nosecone test rig at SoLP: work continued

SN15 work on aft section (under skirt)

Bluto/Tankzilla moved towards gate

BN3 aft section removed form sleeving stand

Tent 3 expansion work continued (east and west walls)

Huge white tanks at the PPS; more solar panels added to the PPS fence

OL platform work continued

New [Sn16?] nosecone washed in front of low bay; Other nosecone [Sn17?] in tent 3

Fwd dome moved to and lifted on sleeving stand; three ring stack beside it

New two ring stack spotted

Alert notice issued for April 26

RC for April 26 (12-8pm)

TFR for April 27 removed

NSF

Mary

LabPadre

[251]
24.04.2021 SN16 nosecone RCS testing

GSE3 more pipes added

BN3 aft sleeve (3-ring) near the BN3 aft dome (on sleeving stand), later sleeved ["aft dome booster WO# 1626306)

Mounting hardware for RVac engines delivered (Vacuum raptor engines)

4-ring section moved into tent

SpaceX cat seen

Stainless steel roll delivered

OL platform work continued

Work on tent 3 west wall

OLS, PB: concrete forms removed

OLS, IT: work continued connecting the three columns; fourth column delivered, installed and later taken down again

PPS: one tank attached to crane, rebar for a ring foundation

Rapotor vacuum mount on a test dome (former SN14 thrust dome)

TFR for Monday removed

NSF

Mary

LabPadre

[252]
23.04.2015 SN15 cryo/ambient test with tank farm activity and venting (skirt, methane, LOX, front tri vent?)

GSE4? aft dome flipped

SN16 nosecone with flaps installed in tent 3, moved next to wind break, near a 4-ring stack with work platform

BN thrust dome, possibly for BN3 spotted

GSE3 prepared to be stacked onto aft section

OLS, IT: column delivered at 10:45am

OLM last caps with rods lowered

Blast berm work continued

SN17? ring section spotted with a lot of TPS heat shield tiles attached

2-ring stack scrapped

SN16 tank section fully stacked in mid bay

OLS, IT: Third column attached by Bigge crane

OLS, PB: concrete poured

TFR for Monday (unl.)

RC cancelled; new one for April 26 (12-8om)

NSF

Mary

LabPadre

[253]
22.04.2021 OLM leg cap delivered (some sort of gray pipe)

GSE3 attached on crane, stacked onto mid LOX section (now 10 rings tall), they haven't been very cautious with it

GSE4 section (3-ring stack with dome) moved [aft?]

Test nosecone moved to launch/test site, between SoLP A and B

OLS, PB: work continued

GSE tank farm: more foundation work, concrete poured into third foundation

OLS, IT: Work continued, connecting beams placed between the two poles

OLM more caps, with rods lowered into legs

GSE2 moved into final position

Zeus and Apollo spotted walking around

SN15 big TPS panel completed at 2 am

Berm reinforcement continued

2 Nosecones [SN16, SN17?] inside tent 3

Aft fin delivered to build site, accompanied by a toy dump truck

TFR for Friday cancelled

Elon Musk, X-Prize: Lunar Starship will deliver up to 200 tons of payload to moon

Overpressure notice for April 23

Road closed, venting

NSF

Mary

LabPadre

[254]
21.04.2021 TFR unl. for April 24

RC updated to 5-7pm

RC updated to 12-2pm and 5-7pm, then to 10:30am–12:30pm and 5-7pm, 5-7pm cancelled later

"The FAA has not signed off on the SpaceX Starship SN15 flight yet, but I'm told they are close, working through documentation for some of the new components."[255]

LR11350 moved to build site (crane yard)

Second column for IT delivered to the OLS, lifted at around 4:38pm

OLM legs received caps with steel rods hanging from them

RCs for April 22: 7-9:)0 [sic!]a.m. and 5:30-6:30pm

RC for April 23: 7am-12pm (beach and road)

BN2 aft section flipped

GSE3 more pipes attached

GSE3 mid LOX (mid #2) tank (4-ring stack) spotted and moved

Test nosecone rig assembly work continued

Round stand parts delivered

OL platform work continued

OLS tank farm: work on fourth jig started with concrete plates

OLS, IT: parts lowered into base

Blast berm work continued

SN16 tank section now fully stacked in mid bay

Overpressure notice for April 21

RC added for April 22 (7-9am, 5:30-6:30pm) and 23 (7am-12pm)

NSF

Mary

LabPadre

Christian Davenport

[256]
20.04.2021 SN16 aft section (5-ring stack) moved into mid bay, other sections stacked onto it

B2.1 dome spotted inside tent 1

New 3-ring stack spotted

Test nosecone rig assembly continued

OLS, IT: first steel column added at a corner, (9:22am lifted, 11:09am released from crane)

OLM preparation work continued

Bluto/Tankzila still attached to GSE2

OLS, PB: Work continued

PPS: fourth ring added to the [tank]

High bay roof work continued

3-ring stack moved out of tent 1

New [?] nosecone inside tent 3 [possibly SN17]

Overpressure notice for tomorrow, April 21 (12-8pm)

TFR unl for April 23

NSF

Mary

LabPadre

[257]
19.04.2021 SN15: RSN54 installed at around 5:53am local

New RC for today from 12pm to 1:30pm

OLS, IT: steel parts delivered

GSE3 aft dome sleeved, not yet flipped

OLS, PB: cement/concrete poured into wall forms

Blast berm work continued, rebar added on top [?]

GSE2 moved out of mid bay, put on transporter, moved to OLS tank farm

Tankzilla/Bluto placed GSE2 on concrete jig adjacent to GSE1

(2:34 left build site, 3:57 entered launch site)

Test nosecone rig work continued, more pieces added

3-ring stack at PPS removed from crane

OLS, Bunker; work, scaffolding on south side

LR11350 nearly fully assembled (small configuration), work on its support boom

Yellow crane near IT

BN2 aft dome section (not flipped yet)

OL platform wedling

GSE3 aft dome craner removed

TFRs removed

RC for tomorrow cancelled

NSF

Mary

LabPadre

[258]
18.04.2021 FAA: SN15 launch authorization pending

Lowest part of a nosecone spotted [?]

SN11 debris field still not fully cleared

OLS: pipes coming out of the ground at the far NE corner

OLS tank farm: concrete plates added to third base

SN15 more tiles added

New concrete fields in the village area

TFR unl for Wednesday, April 21 (7am-8pm)

Overpressure notice for SF tomorrow (third raptor still missing)

RC for Monday cancelled

SN15 third raptor delivered: RSN54 again

NSF

Mary

LabPadre

Chris B

Austin Barnard

[259]
17.04.2021 Remaining raptor has left the launch site at 3:15 am

OL platform: welding work

Airgas truck at the launch site

SN11 debris still lying around SoLS, later compacted into dumpster

SN15 work under skirt (Raptor installation)

Earth wall / berm work continued

OLS, IT: has two huge entrances facing west and south

LR11350 parts arrived, some yellow some red [?]

OLS, PB: work continued

Tankzilla/Bluto still at OLS tank farm

Pipes deliverd to build site, unloaded

Tent 3 front wall not yet completed

TFR unl. for Tuesday, 20 April (7am-8pm)

NSF

Mary

LabPadre

[260]
16.04.2021 SN15: RSN61 moved under skirt early morning, lifted at dinner time

Second rapter lifted at 11:00 pm, lift came down at 12:06am next day

GSE3 fwd dome section stacked onto MID #1 section

2-ring stack moved to scrap yard

Propellant production site (PPS): parts delivered

Test nosecone rig: work continued

Fwd dome barrel section spotted (2-ring)

LR11350 assembly continued

OLS, IT: work continued

Dirt berm between OL tankfarm and landing pad growed, compacted with steamroller; excavtor compessed the west facing slope

OLS, PB: concrete forms removed

GSE3 aft dome barrel section moved into tent 3

NASA, Artemis: SpaceX's Starship selected exclusively for the development of HLS (Human landing system)

SN15 more TPS tiles added

NSF

Mary

LabPadre

[261]
15.04.2021 Deliveries at building site, steel hexagon delivery

Foklift stuck in gravel

OLS cranes moved, Bluto/Tz still near OL tank farm

BN2 fwd aft dome section moved (3-ring stack)

SN20 comn dome barrel? section spotted (3-ring)

SN20 fwd dome spotted

SN16 4-ring section lifted into mid bay for stacking

Raptor van picked up RSN56

GSE3 fwd dome section (2-ring and dome): pipes attached

Test nosecone rig: rods attached

2-ring section moved to scrap yard

OLS, PB: concrete poured

OL tank farm: work on third stand

Launch site: new signs ("Raptors loose")

LR11350 assmebly continued

Work on earth wall between OL tank farm and landing pad continued

High bay work continued, sections moved up

RC for Friday, April 16 cancelled

Progress on Phobos [Shane Overvold]

New RCs: prim Monday, April 19 (12-8pm); sec Tues-Wed, April 20–21 (12-8pm)

SN15 three Raptors delivered to launch site: RSN54, RSN61, RSN66

NSF

Mary

LabPadre

[262]
14.04.2021 SN15 pad A puck shucker (thrust simulation ram) removed

RCs cancelled

BN1 scrapping in high bay continued (e.g. BN1 Booster Qund3 section, started 5 January 21, completed 12 Jan 21)

Test nosecone rig work continued

SN16 mid-lox section stacking in mid bay

GSE2 pipes added in mid bay

GSE3 MID #1, 4-ring section with lead-ins spotted [weld control shown]

Odd column structure delivered to launch site

OLS, IT: concrete forms removed

Roll-Lift 12000-1 crane near OLS tank farm (behind Bluto)

Tent 3 expanison work continued

Domes at prop prod site stacked on rings [diameter?]

Chick-fil-A delivery

SN15 work continued

NSF

Mary

LabPadre

[263]
13.04.2021 BN1 cut in half in the middle, bridge crane used (first time?)

BN1 scrapping continued throughout the day, stackes moved to scrapyard

Test nosecone work continued, hexagon added at the top

BN2? aft dome sleeved

OLS, PB: concrete forms added

GSE1 work continued

Blute/Tankzilla near OLS tank farm

SN15 more TPS heat shield tiles added

Stainless steel single ring moved inside prop prod site

GSE2 work in mid bay continued

Deliveries at building site (I beams)

LR11350: more parts arrived

New RC: prim 15 April ( 12-8pm), sec 16–17 April (12-8pm/7am-12pm)

RC today extended to 10pm

SN15 cryo test #2

NSF

Mary

LabPadre

[264]
12.04.2021 SN15 cryo test #1

SN16 section spotted with approx 960 heat shield tiles, biggest part covered yet

Test nosecone: work on rig continued

Tent 3: heat shield tiles attached to a nosecone barrel section

Tent 3 there are three 4-ring nc barrel sections in the tent

OLS work continued; piling east of OLM

OLS, PB: work continued

Work on wall between OLS and landing pad continued

OLS, tank farm: work at the base of GSE1

Tankzilla/Bluto moved around launch site

SN11 debris still being cleand up

New 3-ring dome sleeve spotted in front tent 1 and moved towards tent 3

LR1300 SX at the prop prod site

BN grid fins loaded onto a trailer

FCC application for 20 km flight, refreshing permit for 11 April to 11 October 2021

NSF

Mary

LabPadre

[265]
11.04.2021 GSE2 final stack

OLS, IT: concrete forms removed

SN15 starlink antenna visible at the left side at the top of the tank section part

SN15 aft flaps opened

Tent 3: assembly of a new nosecone began

COPV delivery

OL Platform work continued

OLS, PB: rebar tied, first concrete forms removed

Work on wall between OLS farm and landing pad continued

SN11 debris still all over the place

Nosecone test rig: new poles added (delivered yesterday, see video), flap structure attached to pole

Cranes moved around at prop prod site (now two yellow and two red crawler cranes there)

SN20 leg skirt spotted

BN[2?] aft dome (with many holes) placed on sleeving stand

LabPadre

NSF

Mary

[266]
10.04.2021 SN22 aft skirt spotted [Carter Goode]

BN2 [?] fwd dome sleeved

GSE2 tank moved into mid bay at 10:30

SN15 single user terminal request: SpaceX installed a Starlink antenna (dish) on SN15 and wants to use it on a flight NET April 20 for a flight test no higher than 12.5 km.

New info: recovery vessels

Dome pedestal delivered

Large ring section moved at the prop prod site

Work on GSE at prop prod site

Pieces for new LR1300 SX crane arrive [crane to build the big crane? - no, seems to be placed at prop site [267]

Large propellant storage tanks now at prop prod site [see April 7]

Test nosecone work continued; lines attached to the black cap

OLS, PB: work continued (rebar), new structures between PB and tank farm

OLS, tank farm: preparation of second concrete stand for GSE2 tank (west of first stand)

OLS, IT: work continued on the tower foundation

SN15 work on aft section; hydraulic ram to be used for simulating Raptor engine thrust during a proof test

White beams delivered (522 and 523)

Tent 3 wall work continued

LabPadre

NSF

Mary

Carter Goode

[268]
09.04.2021 SN15 ambient pressure test

GSE2 tank attached to crane New SN and BN forward domes spotted [?], BN [2?] fwd dome on sleeving stand

Unknown GSE on SPMT

Prop prod plant progressed, two red l cranes and one yellow crane in the area (Liebherr)

Test nosecone work continued

SN15 no raptors installed, detached from crane, most heat tiles installed up to now

OLS, PB: building work progressed

OLS: cranes moved

Launch site: fencing delivered

Launch site: rebar placed for a new earth wall between landing pad and OLS [?] [old wall has been upgraded]

Downcomer pipes loaded on truck

OL platform work continued

SN15 launch not yet approved by FAA [C. Davenport]

Hexagram spotted next to stress test nosecone

LabPadre

NSF

Mary

RGV

[269]
08.04.2021 SN15 rolled out to suborbital pad A

GSE2 tank onto another 4-ring section (now 12 rings)

GSE1 unhooked from crane

Blunt nosecone hydraulic ram lowered into it and it received a black tip (hat): stress test structure

OLS, IT: FAA info

OLS work continued

OLS, tank farm: smaller tank painted

LabPadre

NSF

Mary

[270]
07.04.2021 SN20 fwd dome spotted

A dome leeved with 2-ring stack [see 6 April]

BN thrust dome spotted with 40 holes on the outside (for 20 engines) and holes for 8 enginesin the middle, possibly for BN2/3

SN (higher) thrust dome with many holes (from earlier testing) but fewer pipes spotted, with access ports for vacuum Raptor engines [271]§

OL platform work continued

OLS, power bay [PB]: work continued (rebar and concrete plates), red crane at this building

OLS, IT: concrete plates installed; yellow crane near it [LR1300]

OLS: more drilling near blast berm, rebar moved

GSE1 still attached to crane

LOX distiller work continued

White horizontal propellant tank delivered

New nosecone spotted behind tent 3

RC: prim April 8 (11–1.30)

LabPadre

NSF

Mary

RGV

WAI

[272]
06.04.2021 GSE1 lifted by Bluto/Tankzilla and placed on concrete stand

SN15 work

I-Beams delivered

Tent 3 work on outer wall continued

Dome inside tent 1, methane header tank outside tent 1 [?]

OL platform work continued

"Bigge" crane and tread parts delivered [LR11350?]

New GSE tank is called GSE2 [?]

Concrete foundation built at the restaurant (near intersection)

OLS: work continued

SN11 wreckage cleanup continued, suborbital pads seem cleared

New 2-ring stack spoted

New permits provided info about other sites

New RCs for SN15 roll out: Prim April 9 (7–12), sec April 12/13 (12-8pm)

OLS, IT: LR11350 assembly commenced

LabPadre

NSF

Mary

[273]
05.04.2021 Bluto/Tankzilla moved to launch site

SN15 not rolled out as originally planned [?]

SN15 work platform removed

SN16 nosecone barrel section "Nose Quad" with work platform spotted

Large domes at prop prod site outfited with pipes

OL platform work continued

SN11 still a lot of debris lying around

GSE1 tank rolled out of mid bay, moved to new OL tank farm

RVAC 2 on horizontal test stand at McGregor

OLS, IT: concrete poured

LabPadre

NSF

Mary

[274]
04.04.2021 Tent 3 extension: new wall construction

SN16 [?] nosecone spotted in tent 3 SN15 still attached to crane, detached late in the evening

OLS tank farm: third concrete stand to be prepared

Thrust simulation ram installed on pad A, likely for testing SN15's new thrust puck design before raptor installing

SN15 slated to roll out on April 5

OLM last pillar trimmed

LabPadre

NSF

Mary

Anthony

[275]
03.04.2021 Tent 3 old wall removed

Work on new nosecone inside tent 3 continued

New GSE dome flipped (3-ring)

SN15 welding continued, work near aft flaps, aft flaps moved

BN3 aft tank #5 ring section (4-ring, with lead ins) spotted

New GSE tank: pipes attached (3 external pipes)

OLS, power bay building work continued

OLS, IT: work continued

OLM 5 out of 6 poles trimmed

New crane erected

Thrust simulation ram work conitued

High bay top: work continued

OL platform work continued

SN11 wreckage cleanup continued

RC for April 5, 7am to 12pm, Hwy 4 traffic, near Boca Chica Beach, may be intermittently delayed.

Thrust simulation ram moved to the launch site

LabPadre

NSF

Mary

[276]
02.04.2021 OLM: legs trimmed for OL platform

SN15 nosecone sections moved into high bay, while employees still worked on welding platform

SN15 aft flaps folded prior to stacking

SN15 nosecone work platform removed

SN15 nosecone sections stacked on tank sections (using external crane)

OLS, IT: new concrete plates placed

New GSE tank section stacked [see April 1]

New GSE fwd dome section (3-ring) moved [the one spotted on March 31?]

BN3 aft dome (3-ring) barrel section spotted

New stand moved by SPMT

Blunt nosecone, work continued on the top

New small dome structures delivered

Work on thrust simulator ram continued

14.3t counterweight delivered

RC due to bad weather (unrelated to SpaceX)

LabPadre

NSF

Mary

[277]
01.04.2021 OLS east building: confirmed to be Power Bay/Comms Building

Installing of the new cranes at launch site: yellow crane LR1300 rising, arriving parts of LR11350

RC for Friday cancelled

GSE 4-ring fwd dome section moved and later stacked onto another 4-ring section

Blunt nosecone has very special structures attached at the flap location

New aft flaps delivered

OL platform work continued

Parts for new crawler crane delivered

SN15 nosecone welding and work continued

SN15 work platform installed on top of tank section

Tankzilla/Bluto prepared for moving

New nosecone out of tent [?]

LabPadre

NSF

Mary

RGV

[278]

March 2021[]

Date Description Source Link
31.03.2021 BN3 common dome spotted

SN11 wreckage inspected and clean up; raptors landed near SH, legs spotted damaging the roof of an ATV

SN15 nosecone has been stacked on its barrel section

SN15 tank section moved out of mid bay

SN15 aft flaps installed

SN15 moved into high bay, many heat shield tiles installed

Road work between fence and hwy4 at prod site, new sun panels

New cranes delivered to launch site (yellow LR1300 max 300t, red LRT1220)

OLS, IT: concrete pouring

Blunt nosecone in structure received flap root addons [?]

New fwd dome spotted in tent, possibly for GSE

Road: opened at 5pm, but only for beach access until further notice

LabPadre

NSF

Mary

SPadre

RGV

[279]
30.03.2021 SN11 flight and RUDWork on new nosecone in tent 3

OL Platform work continued

Tent 3 expansion: only front wall missing

RC: extended to March 31, 5pm

LabPadre

NSF

Mary

SpaceX

[280]
29.03.2021 SN11 scrubbed flight attempt

Blunt nosecone lifted into mystery structure

RC: primary March 30 (7am-3pm), Secondary April 2 (7am-12pm)

28.03.2021 TFR unl added for March 31

GSE1 moved into mid bay

SN15 nosecone prepared for stacking on barrel section

Blunt nosecone near mystery structure

BN3 fwd dome barrel section spotted

BN1 work in high bay continued, work plattform still up

Tent 3 expansion work continued

Small bridge crane in front tent 2 still worked on

OLS: east building work continued (rebar and concrete plates), earth work between landing pad and new tank farm

OLS, IT: work continued

Work on 4-ring barrel section with lead-ins

New TFR unl for Friday March 31

RC for March 29, 12-5pm, NOTMAR added until Thursday

Robotic arms delivered to the tent 3

LabPadre

NSF

[281]
27.03.2021 New GSE equipment spotted near huge domes

Crane detached from GSE 1 tank

Tent 3 extension work continued, now as long as other tents

New spot welder delivered

BN2 [?] aft dome with 8 raptor ports spotted in tent

OLS, Integration Tower: Concrete forms placed for the wall, rebar work continued

OLS, east building: Work continued with rebar and concrete forms

4-ring barrel section moved into tent

High bay work continued

Thrust ram work

Work on a fwd dome in front of tent 2

Gantry crane in front of tent 2

BN2 fwd dome moved

New TFR unl for Monday, March 29 and Tuesday March 30

LabPadre

NSF

Mary

[282]
26.03.2021 SN11 single enginge static fire

SN11 scrubbed flight attempt

GSE1 tank has been stacked onto GSE1 aft dome; still attached to crane

Blute/Tankzilla into old configuration

Scrap GSE dome section spotted

OL Platform work continued

SPMTs (blue) stacked with counterweights and connected, possibly for BN1 transport; other configuration than for SN transport

SpaceX, Musk: Monday next SN11 flight attempt

LabPadre

NSF

Mary

[283]
25.03.2021 SN11: RSN46 delivered and installed

SPMT moved Newly sleeved GSE dome moved

New nosecone in front of tent 3 now two flaps installed, assumed now for SN15, barrel section right aside

GSE1 aft dome flipped and moved, ring added like on SN7.2 [!?]

2 ring sectiono with fwd dome spotted [?]

Tent 3 expansion continued

Bridge crane installed

OLS work continued, vehicle integration tower beginning to grow with rebar being placed

Delivery of black structures

New forward dome with two rings stacked on another two ring stack that was seen yesterday right aside

GSE 1 tank attached to crane

Work on SN11 near access hatch

New TFR for Sunday (unl.)

Long term TFR shifted from 7200 ft to 5000 ft

RC for March 26 from 7am to 7.30pm, sf and flight indicated

Mary received alert notice

LabPadre

Mary

NSF

[284]
24.03.2021 SN11: Raptor removed and moved to the build site at 5am for repairs

Tent 3 expansion continued Work on new nosecone outside tent 3 continued, second flap installed

Work on new nosecone inside tent 3 continued

GSE 1 fuel aft dome spotted in front of SN16 aft section (including leg skirt)

SN16 aft section moved into tent 1

Bridge crane installing continued

OL platform work continued

GSE tank dome on sleeving stand and sleeved later

Pipe stands delivered

High bay and bridge crane work continued

Concrete work on driveway entrance at the launch site

OLS new building work continued

OLS tower construction started

New TFR for Saturday

LabPadre

Mary

NSF

[285]
23.03.2021 New TFR for Fr 26 March

New noseone with one flap moved out of tent 3

BN1 disconnected from crane, moved inside the high bay, possibly to make place for bridge crane installing

Delivery of white structures

Tent expansion continued

OL platform work continued

SN11 pressure test, vents

OLS: building in the east continued

Section of bridge crane lifted and lowered again, installing continued

New platform delivered

New nosecone attached to crane, second flap not yet installed

NOTMAR for March 24–26

RC for tomorrow cancelled

Now there are 6 of the huge domes

New foundations at the gas well site

OLS: integration tower stated to go up

RC for Thursday removed, TFR for Wednesday and Thursday removed

LabPadre

Mary

NSF

RGV

[286]
22.03.2021 SN11 Static fire #2, some TPS tiles damaged

SN11 FTS installed, work in skirt area

GSE 1 LOX/fuel work continued, piping installed

"Mystery" structure: work continued

Delivery of green hardware

4 Flap aerocovers (where the flaps are attached) delivered

Tent 3 expansion progressed

OLS: work continued, especially in the very east

SoLS: More concrete work near ramp and landing pad

New nosecone barrel section in front of tent 3: work plattform added

TFR added for Thu 25 (unl.)

RC and TFR for 23.03. cancelled, Thursday rc changed from possible to scheduled

RC added for 23.03. from 12pm to 1pm

LabPadre

Mary

NSF

[287]

[288]

21.03.2021 TFR added for Wednesday 24 (unl.)

Blunt nosecone stacked on additional 4-ring section, now 8 rings (first time procedure!!!)

Progress on OLT (OL tower): fundament seems ready, berm around landing pad moved?

Mary received alert notice

BN1 still attached to crane

SN11 RCS thrusters tested, excess pressure vented

OLS: work continued (rebar...), piling machine now west of new tank farm

SoLS: ramp looking finished

Tent 3 expansion progressed

Pad prepared for concrete (no rebar yet) at the northeastern end of the construction site

LabPadre

Mary

NSF

SpaceX Updates, Spaceport3D

[289]
20.03.2021 Smoke at production site, fire?

SN11 flaps/fins tested

Nosecone in tent 3 has both fins installed

GSE 1 LOX/fuel tank work continued

OL platform work continued

Tent 3 expansion work continued

OLS: new building started to grow in far east corner

New "mystery" structure: work coninued

GSE 2 tank midsection (MID #2) spotted (4-ring stack)

Blunt nosecone attached to crane

TFR for Tuesday 23 (unl)

NASA astronauts visited SN11

LabPadre

NSF

Mary

[290]
19.03.2021 GSE 1 LOX/fuel tank moved out of midbay and stacked (8 rings + dome onto 4 ring stack)

New "mystery" structure: cross bars installed between white poles

Flap installed on nosecone in tent

Work on tent 3 expansion continued

Nosecone barrel section in front of tent 3 has heat tiles installed

Sn2 on concrete stand: water tower?

BN1 work continued

New rc: Mon&Wed primary 7–15; Tues&Thurs secondary 7–15

LabPadre

NSF

Mary

Jack Beyer

[291]
18.03.2021 Tankzilla/Bluto upright

BN1: LOX tank stacked on CH4 tank (full height now visible), LOX tank previously was cut off from its bottom ring, thus BN1 now one ring short [?]

Nosecone barrel section with platform and lead-ins in front tent 3, nosecone moved into tent 3

New 4-ring barrel section with lead-ins on stand in front of mid bay

OLS: formwork removed from second concrete stand, piling continued, SoLP ramp work continued

Domes moved, 3-ring stack moved into tent 1

More beams attached to white poles structure

TFR added for Sunday

FAA on environmental review: "A total of 231 comments were received," with concerns including impacts on protected species, closure of public areas, & more

TFRs later removed

LabPadre

NSF

Mary

Michael Sheetz

[292]

[293]

17.03.2021 Unknown parts delivered

White poles connected on the top

Repair work on Hwy 4

OLS: work on the far east area taking up with rebar preparation, as well as piling; formwork removed from first concrete stand

Concrete work at SoLP ramp

Stainless steel rolls delivered

Tankzilla/Bluto extension installation finished

High bay work continued

Bridge [overhead] crane (not gantry crane) arrived for high bay, capacity 180 tons, unloaded

Prod prod site work continued, scaffolding around some side tanks

Oil cooled transformer delivered

TFR added for Saturday

LabPadre

NSF

Mary

[294]
16.03.2021 SN18 aft skirt and engine section now mated (5-ring stack)

Tent 3 expansion continued, insulation installed

White poles (6) attached to the new stand structure, unclear what this is for

BN1 work platform and lead-ins attached for stacking LOX tank on CH4 section

High bay work continued

Robotic welder working inside tent

OLS work continued, piling machine now east of the new tank farm, earth work in the south of the landing pad, work on SoLP ramp continued

Tankzilla/Bluto extension installed, crane mats moved

FAA license modification: now requiring a safety inspector to be present for launches

TFR added for Friday

Phobos: removing the tower and large section of the accommodations started

LabPadre

NSF

Mary

Michael Baylor

BigBoatDriver

[295]
15.03.2021 SN11 static fire attempt, assumed abort

Bluto/Tankzilla moved from pad to high bay, probably for BN1 stacking, laid down; extension for the crane moved

SN11 FAA approved SN11 flight

TFR added for Wednesday 17th and Thursday 18th

Closure extended to 3pm, but not used

Mary received alert notice for tomorrow SF testing

OLS tank farm: concrete poured in circular forms

Huge pipes and rings with holes delivered to production site

H-Beams welded to the OL platform

SN7.2 moved back to production site, status unclear

Work between road and fence at production site continued

Argon delivered (for welding)

Beams liftet on top of the high bay

LabPadre

NSF

Mary

Christian Davenport

[296]
14.03.2021 SN11 venting at 03:47:30 am

New piling spotted, 2 rows of totally 9 piles, south of landing pad

Work on ramp to pad A continued

SN7.2 work continued

Work on prop prod site continue

BN1 work platform installed for stacking LOX sections on CH4 sections

[SN15] nosecone has flap actuators, but no flaps yet

Aft dome spotted, unclear if new or old practice dome; appeares to have raptor vacuum engine mounts

Work on OLM table continued

Mary received alert notice for tomorrow SF testing

GSE tank section moved into mid bay

LabPadre

RGV

NSF

Mary

Jack Beyer

[297]
13.03.2021 New rc for Mon 15 March 6–12, unlim. TFR for Tues 16, TFR for Mon cancelled

SN11 work on aft section and other parts, access hatches opened

Work on starhopper camera equipment

OLS work continued

Panels: GN2 recharge (gaseous nitrogen), probably stored at 200 bar; GCH4 recharge (gaseous methane), probably stored at 400 bar

X ray inspection of new tank farm plumbing at OLS stand

BN1 work continued

Aft skirt section in tent 1, unknown SN, with many TPS tiles

Forward dome cap delivered

LabPadre

NSF

Mary

Jack Beyer

[298]
12.03.2021 SN11 scrubbed static fire attempt

Mary received overpressure notice, 7–12

BN1: methane tank sections (lower part) including common dome section stacked on engine section

Bluto moved away from SN11

Tent 3 expansion began

New three ring stack spotted in tent

GSE 1 LOX forward dome spotted (dome and 4 ring stack)

Crane mats moved to high bay

Condenser like equipment delivered

Work on prop prod site continued

GSE tank (dome+3 ring stack) flipped

Tankzilla/Bluto put on SPMTs

Loud venting warning:

SN11 vents from LOX and CH4 tanks

LabPadre

NSF

Mary

[299]
11.03.2021 SN11 cryo proof test

Mary received an overpressure notice, but seemed wrong

Work on huge domes continued

BN1 Booster double section moved into high bay, stacking imminent

New stand under construction

Bulkhead moved to scrap yard

Launch table work continued

New nosecone spotted in tent 3

New barrel section outside tent 2

OLS: much work, also in the very eastern part, two stands nearly ready for concrete

SN10 cleanup continued

Concrete work near suborbital pad A

New white propellant tanks at gas well

SN16 4 ring section now spotted in mid bay

LabPadre

NSF

Mary

RGV

[300]
10.03.2021 SN11 testing: aborted

SN11 work at the base

Baker industries delivery

OLS: Two vertical ropellant storage tanks erected at the launch site, right west of the bunker (white tank and black tank)

OLS: Control panels installed on roof of bunker (400 bar storage, GCH4 Recharge)

Concrete work near landing pad continued

Firework: SpaceX festive activities at build site

LabPadre

NSF

Mary

[301]
09.03.2021 SN11 Ambient temp pressure testing

SN11 now mounted on pad B, crane disconnected at 11:54 am

Work on top of the high bay coninued, rail sections installe

Thrust rams installed, probably for testing BN1

Raptor SN59 delivered

OLS work continued

Huge black ground piles placed [near launch mount, where piling work has been going on for some weeks]??

Tankzilla lowered

Flap delivered [in video of 10 March]

LabPadre

NSF

Mary

[302]
08.03.2021 SN11 roll out to pad B

New road closures: Primary March 9 (12-8pm), Primary&Secondary March 10–12 (12-8pm/7am-12pm)

Concrete at landing pad??

SN10 wreckage almost cleared

OLS: Piling work near the OLM, possibly for tower?

LabPadre

NSF

Mary

2KA
07.03.2021 BN1 section "Booster double" (Aft dome sections+ 2 ring stack) moved onto new heavy stand

SN20 Leg skirt spotted

SN11 and BN1 changed places in high bay

New dome still on sleeving stand

SN18 Leg skirt spotted

SN10 wreckage cleanup continued

OLS-Pad A, rebar for a pad at the far east side prepared

OLS work continued, earth wall (blast berm) extended between landing pad and new tank farm

LabPadre

NSF

Mary

[303]
06.03.2021 New dome now sleeved

New section to be lifted into mid bay

OLS work (tank farm) continued

SN10 wreckage scrapped

Bluto/Tankzilla moved next to pad B

Raptor SN58 delivered, message "Much Land Where Box"

Earth work between road and fence at build site

GSE-1 fule fwd dome moved out of tent

New heavy stand moved by SPMT towards high/mid bay

Job posting for Superheavy catch arm development

New site development plans

NSF

Mary

LabPadre

[304]
05.03.2021 SN15 tank section now stacked on the skirt

Another huge dome spotted

Phobos renovation has started with deconstruction of the tower

Parts for new Puck Shucker arrived

[SN15?] nosecone moved, possibly not anymore slated for SN15

GSE-1 forward dome placed on a cart and moved into tent 1

New 2-ring sections moved

GSE-2 LOX aft dome moved from sleeving stand

Delivery of long white piles[?]

Raptor engine 5? delivered

SN11 prepared for rollout

New dome [fwd?] placed on stand

[SN17/18] Scrap aft skirt with leg deployed

SPMT rolled to build site

LabPadre

NSF

Mary

RGV

[305]
04.03.2021 Crane weights moved to pad

Access stairs moved to pad B, sign for SN11 roll out soon

Bluto/Tankzilla moved to launch pad (9:24 am, arrived at noon), SPMTs later returned

Closure cancelled for Friday 5 March, then back on, later moved to Monday, March 8, 9:00 am to 11:30 am

[SN15?] nosecone work continued

SN10 wreckage inspected, cleanup began

SN10 leg pulled from the dunes

SN7.2 work continued, new layer of welding put on the bottom ring

GSE-2 LOX aft dome ready for sleeving, sleeved later on

Work on OLM table continued

LabPadre

NSF

Mary

[306]
03.03.2021 SN10 flight, landing, RUD

Closure extended until March 4 at 8:59 am

SN15 aft skirt moved into mid bay

New nosecone at the other side of the tent (SN15?)

LabPadre

NSF

Mary

Others

[307]

Many other videos

02.03.2021 Mars landing sites downselected to 3-4 locations with 3 backup locations

Mary asked to evacuate for tomorrow flight attempt

Road closures set up for Wednesday, 2 backup closures

New starship renders for dearmoon mission released

Concrete work between road and container wall at the suborbital launch site

OLS work continued: rebar laid north of new tank pad

Crane weights moved to launch site by SPMTs, transferred to onto a trailer

Idea of city of Starbase rose by Elon Musk

LabPadre

NSF

Mary

[308]

[309]

01.03.2021 TFRs now for Wednesday-Friday

SpaceX received a contract for thermal protection system manufacturing

Tomorrows closure cancelled

Red SPMT headed for SN5

Delivery at production site

SN5 scrapping continued, remains moved to scrapyard

Assembly of OLM table continued, welding the parts together

New stand being built

Highway 4 roadwork in front of tent

New nosecone section stacking started [not yet with new parts]

Highbay elevator now operational

SN10 RCS Test at 02:31 am

LabPadre

NSF

Mary

2XqfPfs

February 2021[]

When it is written about the OLS tank farm, some suggested that it also could be a starship stacking site. Diameter of foundations would match and plans released earlier would also indicated so. Furthermore, pipes go round this structure.[1] However, local workers confirmed a tank farm, matching newer plans by SpaceX.[2]

Date Description Source Link
28.02.2021 Concrete next to nose cone assembly tent removed, perhaps for tent extension

Mary been noticed to evacuate tomorrow for possible SN10 launch attempt

NOTMAR published for 1–5 March

Later, SN10 flight delayed to NET Wednesday, March 3 (perhaps due to weather)

SN10 FTS installed

Raptor SN47 delivered, message "Wen Hop? Much Wow."

OLS work continued with both eastward and westward extension (in reference to circular structures north to the bunker); rebars being tied

New flap delivered

Unknown dome moved

BN1 stacking continued

SN15 nosecone stacking continued, still attached to crane

Piling continued in the south of the launch site, near OLM

SN10 methane vent

New ring section spotted in the tent

Roadclosure for tomorrow cancelled

RGV

Jack Beyer

NSF

Mary

[310]
27.02.2021 Pavement expansion at the high bay

OLS work continued, tank farm taking shape

SpaceX logo painted on landing pad; hopefully not to be destroyed soon...

Work on BN1 in high bay

SN10 upper flap testing

NSF

Mary

LabPadre

[311]
26.02.2021 New unlimited TFRs for Monday-Wednesday March 1–3

Raptor "Under Doge" delivered

Pipes delivered

OL Table work continued

GSE 1 forward dome sleeved [for OLS tank farm?]

Raptor SN56 left the build site

Possible aerocovers delivered

[SN17?] thrust section moved

OLS work continued

30% completion of south port connector road

LabPadre

NSF

[312]
25.02.2021 SN10 static fire #2

TFR for today removed, one added for Sunday

SN15 nosecone being stacked, nose section still without its head

OLS work continued

New barrel section moved

Additional ring pieces for supposed launch table moved

New? thrust puck spotted

Alert notice given to Mary for Feb 26, but road closure cancelled

LabPadre

NSF

Mary

[313]
24.02.2021 SN10: One Raptor removed and a new raptor

SN51 installed

New elements added to orbital launch table

Dome work continued at old gas well, solar panels being installed nearby

New forward dome sleeved, unknown SN

Forward flap delivered

OLS work continued, concrete foundation to be extended eastwards

SN18 forward dome barrel section moved around

Concrete poured near production site

Zeus, SpaceX robotic dog by Boston Dynamics, walking around

Closure of today cancelled

Alert notice given to Mary for Feb 25

3 engine tests at McGregor within 45 minutes

NSF

Mary

LabPadre

[314]
23.02.2021 SN10 static fire #1

New unlimited TFRs for Thur-Sat Feb 25–27

New road closures for Friday, Moday and Tuesday

Elevator being added to high bay

SN5 dismantling continued

Raptor engine SN52 delivered

Raptor engine SN43 sent back

BN1 4-ring section "Booster #2" ready in front of high bay

SN17 thrust dome sleeved

New forward dome placed on stand

LabPadre

NSF

[315]
22.02.2021 SN10 scrubbed static fire attempt

SN10 got approved for flight by FAA (launch license modification granted)

OLS: more concrete poured

SN12 common dome scrapped

SN17 thrust/common? dome ready for sleeving

SN5 dismantling continued

New TFRs for Tuesday-Thursday, different TFR shape

Closure for Thursday added

At least 3 engine tests at McGregor on low throttle

Alert notice given to Mary for Feb 23

NSF

Mary

LabPadre

[316]
21.02.2021 SN15 nosecone barrel section attached on crane

Concrete poured on landing pad

Domes built at the prop production site, bigger diameter than usual, usage unclear

OLS: rebar work

SN10 aft fins inspected and tested

New thrust puck spotted

MK2 stand coming down

Alert notice given to Mary for Feb 22

NSF

Mary

[317]
20.02.2021 SN15 nosecone has fin jigs attached, top cone part removed

OLS: concrete being poured at an outer wall and more dirt wirk

SN10 work on engine section and near the hatch

High bay stairs continued to be removed

Thermal protection tiles being installed on the whole barrel section of a future prototype

Concrete work at the production site

NSF [318]
19.02.2021 SN18 potential forward dome on stand ready for sleeving

OLS work continued

SN10 venting

Several parts in storage: common, forward and aft domes and methane header tanks

SN19 methane header tank spotted (now 3 mht ready)

BN1 section rolled out for stacking, scaffolding erected, moved into high bay

BN1 pipe dome (common dome) ready for stacking

Aft dome moved onto sleeving stand

Work on high bay with crane, security stair deconstruction

SN9 final parts removed

New closures for Mo-Wed Feb 22–24

FAA closed the investigation of SN9 mishap

NSF

LabPadre

Jackie Wattles

[319]
18.02.2021 OLS work continued despite bad weather conditions

SN10 static fire not before Monday 22

High bay crane horizontal again

NSF [320]
17.02.2021 SN15 nosecone section attached to crane, moved out of tent and later detached

SN10 static fire delayed, probably due to bad weather, aft flaps moved

SN9 wreckage cleanup

OLS work continued

Sections spotted: SN18 Nosecone barrel section, SN17 aft dome

New OLM structure supposed to be a Superheavy launch table (Support structure baseplate, NASA term, WAI)

New unlimited TFRs for Feb 19–21, but later removed

NSF

LabPadre

[321]
16.02.2021 SN11 second aft fin installed

OLS work continued, dirt work, rebar work continued in circular shape for new tank farm

Black steel section spotted at the build site, unclear application

Work on prop plant continued

New crane waiting for work on high bay

Stands being moved around

Alert notice given to Mary for 17.02.

NSF

Mary

[322]
15.02.2021 Cold weather in Texas, SN10 currently in a hold

Aft fin delivered, probably for SN15

SN11 second aft fin awaiting to be installed

More parts delivered for possible OLM structure

NSF [323]
14.02.2021 Work on OLS continued (new tank farm and GSE bunker)

SN7.2 still on stand with scaffolding

SN9 cleanup continued

New crane assembled at build side near high bay

Grid fins delivered, possibly for Superheavy

Raptor SN27 returned (previously used for SN5 hop)

NSF [324]
13.02.2021 Propellant prdouction site progress

Work on OLS and suborbital landing pad continued

NSF

LabPadre

[325]
12.02.2021 Closure cancelled early in the night - no SN10 static fire attempted

OLS: Circular concrete foundations started, probably for new fuel farm

OLS: Piling work southwest to the OLM, perhaps for stacking tower?

SN14 aft dome used as pathfinder

Parts supposedly attributed to the OLM moved

Flap related parts delivered

Repair on landing pad continued

LabPadre

NSF

[326]
11.02.2021 SN9 cleanup continued

Work on OLS

Work on widening the suborbital launch pad; new layer of concrete will be put ontop of it

SN11 has received one aft flap, removed from crane and then rotated

SN16 aft skirt and thrust section mated

Concrete work at the construction site near fence

Huge steel componoents deliverd, some suggested being for the OLM

Elon Musk interview

Closure cancelled: SN10 stood down from static fire attempt, new alert notice for 12.02. given to Mary

Interview with Elon Musk on the Joe Rogan Experience

NSF

LabPadre

Mary

Joe Rogan Exper.

[327]
10.02.2021 All unlimited TFRs cancelled

SN10 flaps folded

Repair work began at the landing pad after SN9 RUD

SN16 aft dome ahas been flipped and moved

SN16 leg skirt spotted

New nosecone barrel section ready for stacking [SN15?]

Simple roof installed at the OLS bunker

Closure for 11.02. extended, alert notice given to Mary

FAA

Mary

LabPadre

NSF

[328]
9.02.2021 OLS: Concrete work between the shelter and the road

OLS: Steel added to the bunker/shelter to protect Ground supply equipment

BN1 aft dome sleeved

SN7.2 still being worked on

SN9 wreckage not yet removed

Build up of container wall at the test site continued

Work progress on the propellant production plant

Wednesday closure cancelled

NSF

CC

[329]
8.02.2021 TFRs added for Wednesday, 10 February (up to 7200 ft) and Thursday 11 to Saturday 13 Feb (unlimited); deleted; Thursday TFR reinstalled

TFR (standing) moved up to 7200 ft (until March 31)

SN10 Cryo proof test

SN11 crane still attached

BN1 aft dome sections ready for sleeving

FAA

NSF

[330]
7.02.2021 SN11 nosecone section moved to highbay and stacked later

SN17 forward dome sleeved

SN10 flap movement, FTS installed and removed again (fit check)

New pipes at the OLS

Delivery at the construction site

New rings in tent

BN1 practice thrust dome moved around

BN1 aft dome lifted on sleeving stand

LabPadre

NSF

[331]
6.02.2021 Third Raptor (SN39, removed from SN8) installed on SN10

More ground equipment for the OLS shelters deliverd (piping)

SN9 wreckage cleanup continued

SN7.2 inspection

Work on Starhopper systems

FTR added for Monday, 8 February up to 7200 ft

LabPadre

NSF

[332]
5.02.2021 SN11 rolled out of Mid Bay at 10:46; arrived at 11:20; big area covered with heat shield tiles, no aft fins yet

Second? Raptor (SN50) delivered for SN10 at 08:21, later installed

Road Closures for 8.2. and 10.-12.2. announced

Work at the OLS continued after a break due to SN9 launch

BN1 aft dome sleeve spotted (aft dome spotted on January 25)

Ground equipment delivered for OLS shelters (pipes)

Scaffolding around SN7.2 and inspection

New nosecone spotted with fin mounting jig installed (top missing)

LabPadre

Mary

NSF

[333]
4.02.2021 SN7.2 Second preassure test: SN7.2

SN5 top section removed

SN11 both nosecone sections welded together (fins already attached)

BN2 forward dome spotted

SN18 forward dome spotted

LabPadre

Mary

NSF

[334]
3.02.2021 New thrust dome sleeved

SN16 leg skirt moved

SN5 dismantling begins

Metal ring flipped

SN11 nosecone welding continued

SN5 mass simulator removed

SN5 battery pack removed

SN9 wreckage inspected and cleanup began

New forward dome on sleeving stand (probably SN 17)

NSF [335]
2.02.2021 SN9 launch

SN15 top dome section stacked in Mid Bay

SN16? thrust dome sleeved

LabPadre wiki

other

[336]
1.02.2021 SN16 Nosecone Barrel Section spotted

New Nosecone Section spotted

New Crane positioned near OLS

Concrete work on OLS

BN1 Common Dome flipped

Raptor delivered for SN10

NSF [337]

January 2021[]

Date Description Source Link
07.01.2021

[457 - 18.04.]

NSF 2020 recap (video here)

SN15 common dome section with a row of TPS tiles on each ring attached to crane; moved for further stacking in mid bay

RSN45 delivered to production site

OLS work continued: earth work between bunker and hwy 4 for future pad [add: OLS tank farm]

SoLS Pad A: concrete being removed

Helium truck trailer at launch site [NSF: SpaceX uses helium to pressurize the tanks, but works towards autogenous pressurisation]

SN6 dismantling continued, it won't be the HLS mockup; likely the space will be needed for something else; rings cut off and removed

Mk1 disassembly continued, upper part attached to crane and moved away

Stainless steel delivered

Driveway work behind mid bay (towards hwy four) continued in order to enlarge the entrance to the production site

Sleeved dome section removed from sleeving stand (4-ring)

SN9 work continued after yesterday's static fire (thought to be off-nominal)

Propellant deliveries to tank farm

Work on a ring "Top porrel, Booster Dev, Do not scrap, Bevel Bottom"

NSF

Mary

[338]
06.01.2021 SN6 mass simluator removed, SN6 speculated to be used as future HLS prototype

Nosecone in tent 3 lost its tip [SN11 nosecone?]

OLS earth work continued, as well as concrete being poured; work on ground piping on the east end; pad being prepared between bunker and hwy 4

SN9 launch NET 8 January, preparation work continued

SN15 common dome spotted (3-ring with lead-ins) and worked on external pipes/walves

SN10: Crane detached from SN10 nosecone

Mk1 scrpping continued

New thrust dome (same as yesterday) seen

SN9 static fire (Video here); rather short static fire of about 1.5 secs, followed by double depress vents and nosceone vent, condensation on CH4 tank slowly disappearing; final depressurisation vents;

NSF

Mary

[339]
05.01.2021 Red/orange parts delivered to launch site

OLS earth work continued; ground piping work at the east end of tank farm

TFRs scheduled for SN9 launch

SN9 work continued on several areas

Sleeved starship fwd dome (1-ring) shown

New starship thrust section spotted [unknown SN]

Fwd dome has been sleeved with a f

SN11 nosecone moved back into tent 3

4-ring barrel section moved out of tent 3

Tapered section ready to be stacked

Barrel sections spotted: SN15 nose cone barrel, SN16 mid-LOX, SN17 fwd dome barrel (all 4-rings ?)

SN8 remains being broken up and removed

SN10 speculated to roll out as early as next week

Mk1 attached to crane and cut in half, upper part removed

NSF

Mary

[340]
04.01.2021 No video
03.01.2021 SN8 nosecone: fwd fin attached to crane and removed by crew; transported away

Landing pad: Rebar work on cut out section

Thrust dome section sleeved (3-ring), next to a 2-ring thrust dome section [SN12/SN13??]

Nosecone spotted in tent

SN10 nosecone welding work continued in high bay

OLP work continued

SN9 work continued on Pad B, four man lifts work at engine section

NSF

Mary

[341]
02.01.2021 Emmert international heavy transporter moved away

SN10 worked on in high bay; crane attached to nosecone, nosecone lifted and stacked onto tank section later

OLS work continued: around OLM

Shipping containers moved near OLP by crane

LN2 delivery to tank farm

SN9 worked on, LOX access hatch open

NSF

Mary

[342]
01.01.2021 Launch site work continued; SN8 nosecone wreckage lying around

OLS work continued, especially on ground and eargh work; excavators working near the landing pad

Pad B / SN9: work on engine section

Mobile office building moved on an SPMT, later offloaded near the tank farm, adjacent to the container building row

Equipment moved by SPMT at launch site

SN10 tank section in high bay, awaiting stacking of nosecone

SN11 tank section fully stackied in mid bay

NSF

Mary

[343]

2020[]

December 2020[]

Date Description Source Link
30.12.202 Flaps delivered to producition site [SN10?] [vid 01 Jan 22]