Welcome to the general Timeline. Here, all updates and events will be posted. Date, description and source, with a link if possible, must be provided. Timeline sections in any other articles (such as the SN articles) should only refer to this page.

Events and activities are assigned to the days according to local time.

This page should be kept in a manner that it is search-friendly (CTRL+F).

Abbreviations[]

  • B: Super heavy booster number [new designation]
  • BN: Super heavy booster serial number (first stage of the rocket)
  • CH4: (Liquid) methane
  • COPV: Composite overwrapped pressure vessel (black helium tank for tank pressurisation)
  • FST: FutureSpaceTourist
  • GSE: Ground support equipment, including ground tanks
  • HPU: Hydraulic pressure unit (on booster)
  • IT: Integration tower (for catching boosters and stacking starship)
  • LN2: Liquid nitrogen
  • LOX: Liquid oxygen
  • LR: Liebherr crane
  • MSIB: Marine safety information bulletin
  • NET: No earlier than [+date] (but very likely later)
  • NSF: NASASpaceflight
  • OLM: Orbital launch mount
  • OLS: Orbital launch site (the east part of the launch site)
  • PB: Power bay or comms building (at the far east of the OLS)
  • PPS: Propellant production site (prop prod site)
  • QD: Quick disconnect (arm)
  • RB: Raptor boost
  • RC: Road closure (prim and sec - primary and secondary)
  • RC: Raptor Center (same as raptor boost, but with gimballing capability)
  • RSN: Raptor engine serial number
  • RVac: Raptor vacuum engine
  • S: Ship (upper stage) [new designation]
  • SH: Starhopper
  • SF: Static fire
  • SN: Starship serial number (upper stage of the rocket)
  • SoLS: Suborbital launch site
  • SPMT: Self propelled modular transporter
  • TFR: Temporary flight restriction (for flight tests, issued by FAA)
  • TPS: Thermal protection system heat shield tiles (hexagonal black tiles)
  • TVC: Thrust vector control, by engine gimbal; hydraulic or electric

2023[]

December 2023[]

Date Description Source Link
31.12.2023
30.12.2023 S30 moved to Massey's Outpost

LR11000X moved to SoLS Pad B

B10 lifted off OLM

LabPadre
29.12.2023 One of the Mega Bay 2 bridge cranes picked up the 2pt ship lifting jig

B12 moved from Mega Bay 1 to Massey's test site [Massey's outpost according to official sign]

OLIT#3 Tower segment and GSE-tank arrived in south Texas on a barge Chopsticks moved up above the SQD arm

S29 moved out of high bay and into mega bay 2

Elon Musk info: "The super heavy booster can be used more frequently than the ship, as it returns in about ~6 minutes and can theoretically be ready for reflght in an hour. The ship needs to complete at least one orbit, but often several to have the ground track line back up with the launch site, so reuse may only be daily. This means that ship production needs to be roughly an order of magnitude higher than booster production. To achieve Mars colonization in roughly three decades, we need ship production to be 100/year, but ideally rising to 300/year."

S28 static fire (likely single engine)

B10 33 engine long-duration static fire

S29 attached to 2-point ship lifter in mega bay 2

LabPadre
28.12.2023 Sixth new cryogenic storage tank of the OLS tank farm extension was delivered

New intermittent RC for 2 January 2024 (6-9am)

Overpressure notice issued to residents for S28 and B10 static fire of tomorrow

B12 lifted onto thrust simulator that was moved into mega bay 1 earlier today

LabPadre
27.12.2023 B20 transport stand moved at the launch site

B10 transport stand moved at the launch site Booster thrust simulator stand moved from Massey's to build site

LabPadre
26.12.2023 S24.2 is scrapped

Chopsticks lowered to bottom stop at 15:50-16:30

Scaffolding erected up to B10 LOX tank hatch

The Ringwatchers

LabPadre

23.12.2023 B10 transport stand moved back next to LR11000

SpaceX sign delivered to launch site and installed above gate D1 [Rusty Buckets]

LabPadre
22.12.2023 HLS: Recently, the HLS Starship sub-scale mockup elevator has been tested by NASA astronauts Nicole Mann and Doug Wheelock NASA

Detonation suppression system tested at OLM Overpressure notice issued to residents Mary and road was closed for a potentially planed B10 static fire test. No test occurred.

B10 transport stand moved at launch site

LabPadre
21.12.2023 IFT-2 (Starship Flight test 2) post launch conference [see IFT-2], confirmation that SpaceX plans to build a second pad at Starbase

B10 static fire test aborted. Engine purge testing also occurred afterward.

Nasaspaceflight

LabPadre

20.12.2023 B10 transport stand moved away from OLP

Overpressure notice issued to residents for today's test of S28 Mary Back of BQD hood reattached

Booster engine installation stand moved back to build site

S28 performs a static fire of all 6 engines; payload bay door also tested later on.

B10 igniter test at 16:12:46

Overpressure notice issued to residents for B10 test tomorrow Mary

OLM work platform lowered in the morning, moved away from launch site in the evening

Scaffolding removed from OLM

Nasaspaceflight

Labpadre

19.12.2023 Ship QD arm retracted early morning

B10 was lifted and has been secured onto the OLM becoming the fourth booster to take this position; fireX testing conducted. BQD attached to B10

Brendan Lewis Discord
18.12.2023 B10 moved to the launch siteB10 pressure hoses reattached Starship Gazer

B13 F2:3 staged in front of Mega Bay 1

"A barge carrying a Starship launch pad tower segment and methane tanks is departing the turn basin dock at the Kennedy Space Center." Spaceflight Now

Back of BQD hood moved to OLM area Nosecone welding turntable spotted in the starfactory expansion, the first known construction hardware to be installed LabPadre

Labpadre

The Ringwatchers

17.12.2023 Main ring of the third and final new-style booster work stand for mega bay arrived at the ring yard from Sanchez
16.12.2023 B13 M:20 stacked onto AX:4 making it the A:24 [LOX tank stacked onto thrust section]

Both SPMTs from S28 transport left the launch site as well as the transport stand

Top ring of the new ship engine installation stand spotted inside mega bay 2

S28 spin prime test

15.12.2023 LR11000X detached from S28

OLIT#3 segment 7 moved to Kennedy Space Center turning basin from Robert's Road facility

S28 aft and forward flaps underwent several actuation tests after having been opened around 9:20

B13 AX:4 (thrust section) moved into the Mega Bay for stacking.

Starlink gateway dishes lifted onto the new concrete building at Sanchez site

LR11000X moved away from Pad B and later to OLS tank farm near gate D2

The Ringwatchers

Labpadre

Nasaspaceflight

14.12.2023 Christmas lights added to OLIT stairs and SQD arm

S28 rolled out in a festive manner and was lifted onto Pad B by LR11000X

S29 and S30 are shuffled around in the high bay, with S29 moving to the tiling station and S30 rolling back and placed in the back of the high bay

S24.2 lifted out of the Structural Testing Cage at Massey's

13.12.2023 Pipe prefabrication building in Boca Chica village demolished just 4 months after construction Cosmical Chief

Transport closure for S28 added (12:30am–3:00am on 14 Dec)

SoLS Pad A demolished

SPMTs moved into high bay for S30 movement

S30 moved out of the high bay to make way for S28 roll out

SPMTs decorated with lights and a Christmas tree moved to highbay for S28 roll out

12.12.2023 LR11000X detached from SQD after it was lifted off the OLIT

LR11000X rolled away from OLIT back to SoLS Pad B

New intermittent RC for 12 December (3pm-7pm)

SoLS Pad A being demolished with beams and columns being cut and removed

"Orbital Pad clear" siren and PA message

First column of next section of Starfactory expansion raised

Kathy Lueders update in Brownsville:

  • SpaceX is in the process of submitting flight approvals and amendments for flights #3 and #4
  • They will continue to monitor sound levels especially during low cloud cover and higher winds
  • Both Starship and Booster RUD likely due to AFTS and they are working on the mishap investigation to conclude why
  • Hoping to start catching boosters sometime in 2024
  • Confirmed plans of second tower at Starbase and moving engine testing to Massey
  • Planning for multiple flights in 2024
  • Says they are aiming for 1Q 2024 for IFT-3, says unlikely to achieve December despite Elon aspirationsB13 LOX tank lifted off turntable in mega bay 1
11.12.2023 B12 moved from front left corner to the new stand in the back left corner of mega bay (previous position of B10)

B7.1 test tank is scrapped at Massey's site

S26 disconnected from load spreader and moved back into previous position at rocket garden

10.12.2023 SQD attached to LR11000X and cut free and detached, not yet lifted off the OLIT LabPadre
9.12.2023 A recent flyover confirms that SN15's aft section is now completely scrapped.

Two SPMTs with counterweights moved into high bay

RGV aerial photography

The Ringwatchers

LabPadre

8.12.2023 New info from Air Force regarding the Rocket Cargo Contract: "Next year, the Air Force also plans to have a cargo bay mockup — basically the upper half of a Starship — it can use to refine the techniques for rapidly loading and unloading 20-foot containers from a rocket. That mockup is now in the final stages of construction by the engineering firm SES in Alliance, Ohio." Spanjers

Tanks moved towards Massey's test site

Chopstickes rose Today's closure revoked

New intermittent RC for December 10 (12pm to 2am)

LabPadre
7.12.2023 SpaceX IFT-2 (Second flight test) recap video released, confirmed S28 and B10 (Starship 20/28) for IFT-3

S26 moved closer to the engine installation stand, attached to LR1750

LabPadre
6.12.2023 S27 AX:4 is scrapped, dome remnants still visible on 8 Dec

B10 moved to the rocket garden

The Ringwatchers

Labpadre

5.12.2023 New booster transport stand moved into mega bay 1

Ship lifting squid delivered to launch site

SQD arm retracted at 10:00

B10 conducts grid fin testing and is later lifted off the engine installateion stand onto a new-style transport stand

B10 is moved out of the mega bay towards the rocket garden

Chopsticks raised to the top of the tower and then descended back to the stop; SQD arm swung back in

4.12.2023 B10 HS:1 (hot staging ring) lifted onto booster and installed in the Megabay

S33 ML:4 moved to the scrapyard

IFT-3 update: "At the Natl Acad cmte meeting, NASA's Lakiesha Hawkins shows a slide that says SpaceX will do a propellant transfer demo on their next Starship test." Marcia Smith

'Gateway to Mars' sign lit up for the first time

B10 hooked up to both bridge cranes in MB1; new-style transport stand moved out of rocket garden towards mega bay

2.12.2023 "Gateway to Mars" sign lit up slightly

Wall along OLS tank farm starting from gate D2 has started being dismantled

LabPadre
1.12.2023 Back of Booster QD hood removed at OLM LabPadre

November 2023[]

Date Description Source Link
30.11.2023 NASA Artemis program: HLS challenges gao.gov lead to potential delays with a crewed landing on the moon unlikely to happen in 2025. One reason is the delay of OFT-1 by 7 months to April 2023

"Gateway to Mars" sign completed

LabPadre
29.11.2023 LR11000 went back up after being laid down for launch of IFT-2

First of the two booster stabilization pins atop OLM reinstalled

4th and 5th Horizontal storage tanks delivered to the launch site and installed

The Ringwatchers

LabPadre

Nsf Live

28.11.2023 First horizontal storage tank installed on the first set of new tank pedestals

S33 AX:4 moved to the scrapyard, questioning the existence of this Ship

New sign delivered to launch site and being installed on the black wall outside the SoLS tank farm ["Gateway to Mars"]

3rd and 2nd new Horizontal storage tanks delivered to the launch site

27.11.2023 Both CO2 tanks installed on B11

S24.2's bottom ring weld on the "windward" side buckles during an apparent structural test New 'Gateway to Mars' sign letters spotted

New Horizontal storage tank delivered to the launch site [First of 5]

OLM work platform moved over to the vicinity of the OLM and was raised

24.11.2023 Elon Musk hinted to a Version 2 Starship:

-"Four more Starships, the last of V1" X

-"Version 2 of the ship holds more propellant, reduces dry mass and improves reliability" X

NC36 is scrapped [Believed for S33?]

B11 CO2 purge tanks added

23.11.2023 S28 rolled to the highbay; S30 also returns to the highbay - all 4 ships now in high bay
22.11.2023 SpaceX released tracking camera footage of the booster MECO, where 30 of 33 engines shut down in preparation for hot-staging

S28 scaffolding removed after supporting work inside its tank ever since the ship was put on the engine installation stand at Sanchez site

Booster transport stand returned to sanchez site after being staged outside Mega Bay 1

S30 moved out of high bay weighed down in front of high bay

S28 detached from lifting squid

S28 reconnected to lifting squid and lifted off the engine installation stand

21.11.2023 Booster Raptor installation work platform returned to the launch site at 2:14am

One of the large black rings being constructed in Sanchez moved to the build site, possibly new version of the booster transport stand

Elon Musk Update on Raptor engine production and next generation engines: "Could make them faster, but engine production is not the limiting factor. I’m very excited about the next-gen Raptor engine that is robust enough not to require a heat shield. Will also have more thrust, higher Isp and many other improvements." X

20.11.2023 B11 lifted off thrust simulator stand (from Massey's stand) onto engine installation stand inside Mega bay 1

OLM work platform returned to launch site at 5:37 am

SpaceX has begun posting signs indicating that the rocket garden portion of Remedios avenue is private property which would lead to restricted access JoeTegmeyer

SQD arm rotated back into extended position at 18:42 for first time after launch Chopsticks closed and returned to normal resting location at 20:29 S30 rolled out of the highbay into the ringyard

S31 rolled out of the highbay to Sanchez (rocket garden)

S29 rolled back to the high bay

19.11.2023 Workers went into OLIT to inspect the chopsticks, SQD arm and actuator

Scaffolding went up around OLM New intermittent RC for today 8pm-11pm

Elon Musk update on IFT-3 and IFT-4: "Starship Flight 3 hardware should be ready to fly in 3 to 4 weeks. There are three ships in final production in the high bay (as can be seen from the highway)."

B11 returned to mega bay 1 from Massey's Outpost

18.11.2023 B9 launches S25 into space. Following an apparently perfect launch, 33-engine burn, and hot staging separation, at around 90 km altitude over the Gulf of Mexico, Booster 9, with the hot stage ring still attached, is terminated during the boostback burn after apparent engine trouble. Meanwhile, Ship 25 becomes the first Starship to reach space, nearly completing its 6-engine burn before apparent engine trouble and flight termination at an altitude of 148 km and a speed of over 24000 km/h. Labpadre

Nsf Live

The Ringwatchers

17.11.2023 Vented interstage reinstalled on B9

Hot staging ring transport stand and load spreader moved back to ring yard

New TFR added for 20 November 2023 Space TFRs

S25 stacked back onto B9

Steel for OLIT#3 continued to be delivered at Starbase RGV

Announcement from Hawkins: "SpaceX will use both Starbase and LC39A launch pads for Artemis III HLS. In the "high teens" of number of launches needed to aggregate fuel. Lander is about half way thru that sequence. Must do all in quick succession due to boil off issues."

LR11000X crane moved to SoLS and was lowered ahead of launch

SQD plate attached to S25 at 10:31

S25 transport stand moved back to build site

Announcement: Rocket garden no longer available for public access, all of Remedios Avenue now private. Maria Pointer has confirmed that SpaceX was granted this by Cameron County recently. Austin deSisto, and here

The Ringwatchers

Nsf Live

LabPadre

16.11.2023 LR11000X moved to OLS

S25 destacked off of B9 following a grid fin actuation failure; Hotstage ring also destacked afterwards - launch of IFT-2 postponed to 18 November

S32 AX:4 moved into the highbay; S32 N:16 stacked on AX:4 completing the stacking for S32 after 36 days from start to completion

Two grid fin actuators replaced between 19:15 and 20:15

OLIT#3: second and third column pieces for new launch tower at Starbase arrived Starship Gazer

Maria Pointer: Boca Chica village to be evacuated on 10pm on Friday night

Third grid fin actuator removed and replaced, then grid fins on B9 were tested (23:56)

B9 interstage clamps tested

Labpadre

Nsf Live

The Ringwatchers

15.11.2023 SQD scaffolding removed

Hotstaging ring reinstalled on B9

First OLIT#3 hardware delivered to Starbase Cosmical Chief

LR11000X lowered ahead of IFT-2

Temporary pressure plate removed from S25

FAA: Launch license for IFT-2 granted after the FWS finished its Written Re-Evaluation finding no singnificant impact on the environment; Main points:

  • The deluge tanks have a capacity of 358,000 gallons
  • Launches are expected to use only 132,000 gallons maximum, so it is possible the system could be used twice.
  • Static Fires will use approximately 72,000 gallons.
  • SpaceX will be able to use the deluge up to 30 times a year under this WR.
  • The nitrogen purge to activate the deluge operates at 3000 psi.
  • A launch is expected to ablate up to 190 pounds of steel from the plate.
  • 92% of the deluge water is expected to be vaporized.
  • SpaceX is expected to add up to 30,000 gallons of additional retention pond storage.
  • Retention pond water can be reused if it passes environmental testing, otherwise the pond water must be shipped out for waste.
  • The WR finds no significant environmental impacts are expected to wildlife or vegetation at this time and no mitigations are required by SpaceX at this time.
  • As always the FWS can come back and request a new WR and changes if impacts beyond expectations are found.

S25 stacked onto B9 for 7th time

Nsf Live
14.11.2023 NC36/S33 NC moved to Sanchez

S25 new heat shield tiles added where they recently fell of during stacking

TFT for November 17 for IFT-2

Christian Davenport: "Also just heard that a license is indeed imminent and that a Starship launch attempt could happen this week."

Sanchez site: Air separation unit column started to being dismantled

New cryo tank delivered to Massey's test site RGV

The Ringwatchers

LabPadre

13.11.2023 Several updates for imminent launch of Starship 9/25 on IFT-2 Elon Musk, RC, FAA ATCSCC, MSIB] LabPadre
11.11.2023 S25 stand returned to OLM area

LR11000X crane raised back up

Ship 25 destacked from Booster 9; Hotstaging ring removed from B9 following destack

Nsf Live

The Ringwatchers.

10.11.2023 NOTAM for US side of Gulf of Mexico posted for IFT-2

Hot staging ring for B9 returned to launch site at 19:16

SpaceX: "Starship preparing to launch as early as November 17, pending final regulatory approval"

SpaceX
09.11.2023 It appears that the FTS explosive charges installation on B9 ans S25 have concluded as the boxes were sealed [Starship 9/25]

DearMoon update: After the results of IFT-2, a new timeline will be created: "We were planning for our lunar orbital mission "dearMoon" to take place in 2023, but seems like it will take a little longer. We’re not sure when the flight will be, but we will give you all an update once we know more." Yusaku Maezawa

NOTMARS for Hawaii for IFT-2

LR11000X lowered

FCC on IFT-3: Most recent FCC filling shows that SpaceX intends to launch IFT-3 into a 235km apogee, and perform a powered landing of the Ship in the Indian Ocean, as opposed to the Pacific Ocean during IFT-1 and 2: "The Starship-Super Heavy test flight will originate from Starbase, TX. The booster stage will separate and will then perform a partial return and land in the Gulf of Mexico. The orbital Starship spacecraft will continue on its path to an altitude of approximately 235 km before performing a powered, targeted landing in the Indian Ocean."

Raptor installation platform moved from launch site to Sanchez site

FTS covers on B9 closed again

LabPadre
08.11.2023 Stand that used to hold the B9 hot staging ring moved back from launch site to ring yard

NOTMARS added for 13–18 November for IFT-2 (Gulf of Mexico and Hawaii)

Safety net below OLM work platform lowered

WB-57 plane for NASA flew back to Texas after a week in California ahead of the potential launch

Sanchez site: Grove GMK7550 "Grover" attached to air separation unit column ahead of removal

Chopsticks attached to S25 for potential lift

NOTMAR for November 15 posted for IFT-2

OLM work platform lowered onto transport stand and moved from launch site to Sanchez site

LabPadre
7.11.2023 Chopsticks lifted to S25

Choopsticks lowered, crews continued to work on S25

LabPadre
6.11.2023 Top section of structural test frame installed over S24.2 ahead of stress testing it at Massey's test site

3 new road closures posted for November 13–15, all from 12AM to 2PM CST 'Note that these are labeled as non-flight closures, however so were the closures for IFT-1 when first published and the times are the same.'; also NOTAM for Mexican airspace issued for November 13–18 (7:00am–9:39am)

Brendan Lewis' Discord server

LabPadre

3.11.2023 S32 N:12 stacked on ML:4 creating N:16. [S32 stacked onto mid-LOX section inside high bay, now 6 sections tall]

SpaceX announced that the second flight of Starship is set to fly in mid November, pending regulatory approval. SpaceX also posted on their website an updated timeline for IFT-2. Marcia Smith, SpaceX

The Ringwatchers
2.11.2023 FWS teams arrived at Starbase again for an inspection on site of the deluge discharge zone and nearby wetlands

S24.3 installed in the structural test frame at Massey's test site

S32 ML:4 moved into high bay for stacking.

S25 de-stacked from B9, presumably for FTS installation

Nsf Live

The Ringwatchers

1.11.2023 S25 re-stacked on B9 for unknown reasons Nsf Live

October 2023[]

Date Description Source Link
31.10.2023 FAA review completed, Awaiting FWS review.
30.10.2023 Pamela Melroy visitied SpaceX Raptor production and was briefed on HLS program [including picture of Rvac engines]
28.10.2023 New booster engine installation stand moved into Megabay 1

Vented interstage reinstalled on B9

Nsf Live
27.10.2023 Vented interstage removed from B9 again

S26 returned to rocket garden, and was placed in between B4 and S29

HLS news from Spaceflightnow:

  • SpaceX will be conducting a HLS docking test sometime this week aimed to simulate both docking with Orion and Gateway.
  • Watson-Morgan (lead program manager of HLS) stated that she and her team are eager to see around 15 to 17 flights of Starship en route to the crewed Artemis III crewed landing mission.
  • Watson also mentions Starship propellent transfer in orbit in 2024. Notably calling for more assets from SpaceX which have yet to debut (Supposedly alluding to the other unfinished launch platforms and commodities)
  • "That’s where we’re going to get to see multiple launches from multiple pads go into orbit and transfer some amount of fuel between the two. And that will be a really key indicator as to their readiness level".
  • SpaceX are working on smaller thruster systems for HLS.
The Ringwatchers

Labpadre

Nsf Live

26.10.2023 Ship 25 destacked ahead of FTS installation

FWS update on Written Re-eveluation:

  • On Oct. 19, the U.S. Fish and Wildlife Service reinitiated Endangered Species Act consultation with the FAA. We have up to 135 days to issue an amended biological opinion but do not expect to take the full amount of time.
  • Under Section 7 of the Endangered Species Act, reinitiation of formal consultation is required when a project and its impacts change significantly, the amount of take issued previously is exceeded, we ahve new information on listed species not previously considered, or a new species is listed.
  • For SpaceX reinitiation with FAA we are considering the operation of a deluge system at the launch pad.

S26 lifted off Pad B

Nsf Live

Labpadre

25.10.2023 FWS teams arrived at launch site around deluge discharge area and nearby wetlands for inspections

S27 aft section removed from structural testing jail at Massey's

Placeholder NOTMAR issued for a potential launch going into effect on November 6 and onwards NAVCEN

LabPadre
24.10.2023 WDR of Ship 25 and Booster 9 (with FireX) and deluge test post WDR

S32 N:8 stacked on CX:4 creating N:12 [stacked on common dome in high bay, now 4 of 6 sections tall]

The Ringwatchers

Nasaspaceflight

22.10.2023 S21/S22/HLS nosecone moved to the rocket garden

Full stack partial cryo test + Water deluge test.

Nasaspaceflight
21.10.2023 S25 transport stand moved from OLS to SoLS pad A

S32 CX:4 moved into the High Bay for stacking

S26 attached to LR11000X and a ship transport stand on two SPMTs with counterweights has been moved to Pad B

Mega bay 2 reached its maximum height and the topping tree was lifted

The Ringwatchers

LabPadre

20.10.2023 S25 stacked onto B9 (4th stacking of Starship 9/25)

New testing RC for 22 October (8am-8pm)

S26 performs its first static fire with 1 engine

S26 igniter tests at 19:24 and 19:40

SpaceX: "Starship team preparing for additional preflight tests in advance of a full launch rehearsal while continuing to work with the FAA on the Flight 2 license"

Nasaspaceflight

LabPadre

19.10.2023 New edome test tank (TT14) completed a cryo test at Massey's

S22/HLS nosecone aerocovers removed

FSW and SpaceX officials were on site for inspection and cleanup aaround wetland flats LabPadre

NSF live

LabPadre

18.10.2023 Hot staging test article moved from Massey's back to build site

S32 N:5 stacked on FX:3 creating N:8 (3 of 6 sections tall)

IFT-2 launch license: In a statement on Tuesday, a FWS spokesperson said their agency received a final biological assessment from the FAA Oct. 5 and FWS has up to 30 days to review it. This came after the FAA sent FWS a letter in August, which requested "reinitiation of Endangered Species Act consultation." Following the 30-day review of the final biological assessment from the FAA, the FWS has "135 days to issue an amended biological opinion." Spaceflight Now; also NOTMARs for launch NET 1 November posted for the Gulf of Mexico

B11 undergoes cryo test

S26 pre burner test

The Ringwatchers

Nasaspaceflight

LabPadre

17.10.2023 HS FX:3 and HSR:1 moved back to the build site

IFT-2 launch license: "As the consultation with FAA and US Fish and Wildlife over the Starship mishap will likely push into November, further delaying a second launch attempt, SpaceX is calling on Congress to push FAA to issue launch licenses faster" Washington Post, Christian Davenport

S25 lifted off B9 (3rd destacking of Starship 9/25)

The Ringwatchers
16.10.2023 S32 FX:3 moved into the highbay for stacking

S25 lifted onto B9 (3rd full stack of Starship 9/25)

Spacex on IFT-2: Starship fully stacked while team prepares for a launch rehearsal. We continue to work with the FAA on a launch license

The Ringwatchers
15.10.2023 Hot stage ring reinstalled on B9 at 19:41 LabPadre
14.10.2023 Third girder installed in mega bay 2 LabPadre
13.10.2023 B11 underwent cryo testing at Massey's

OLM work platform lowered otno its stand at 00:15

S28 still on engine install stand detached from LR1750

S29 moved back to Sanchez site

S29 lifted off the thrust simulator stand onto a transport stand by LR1750 and moved to the rocket garden

Mega bay 2: bridge crane girder lifted and installed

Chopsticks re-attached to S25, then lowered again

New MSIB for October 17

Three new road closures scheduled from Monday- Thursday all from 8am to 8pm CST

S30 has its second flap installed

Mega bay 2: bridge crane completed with trolley hoisted into place

The Ringwatchers

Labpadre

12.10.2023 B11 moved to Massey's. Was outfitted with CO2 tank mounts and the 18 fire suppression vents during its stay in Mega Bay 1

Ship 26 has been disconnected from the LR11000X crane at Suborbital Pad B

The Ringwatchers

Labpadre

11.10.2023 S32's NC35 moved into the High Bay to start stacking of the ship; S32 PL:5 moved into the High bay for stacking; S32's NC35 stacked atop PL:5 creating N:5

B11 lifted onto puck shucking stand which was moved into mega bay 1 earlier, ahead of roll out

S26 attached to LR11000X at 23:39

The Ringwatchers

LabPadre

10.10.2023 New intermittent RC for October 11 and 12 (12am-3am)

Aft flap installed on S30

The Ringwatchers

LabPadre

09.10.2023 Interstage removed from B9 again [hot staging ring]

S32's NC35 moved into the Ring Yard from Tent 3

NC37 is scrapped

S30 rolled out of high bay, was reoriented and moved back into high bay for flaps and tiles installation

S26 Cryo Proof Test

The Ringwatchers/

Labpadre

08.10.2023 -
07.10.2023 -
06.10.2023 -
05.10.2023 SQD detached from S25 at 7:30 arm swung away from fullstack

S25 lifted off B9 at 8:57 set onto transport stand at around 10am; Starship 9/25 destacked

S26 detached from LR11000X at 11:28

SpaceX announced that Elon Musk provides an update on the development of Starship at the International Astronautical Congress in Baku Twitter, Youtube

LabPadre
04.10.2023 Two mega bay 2 bridge crane trolleys delivered

S29 cryo proof test at Massey's test site; both tanks frosting at 17:32

B13 downcomer lifted into mega bay

NC37 moved to the scrapyard

B13 has its downcomer installed

The Ringwatchers

LabPadre

03.10.2023 S31 N:16 stacked atop AX:4 creating A:20, completing the construction of Ship 31 in 33 days

S25 flap tests while stacked on B9

The Ringwatchers

LabPadre

02.10.2023 S31 AX:4 is lifted into the highbay.

S31 downcomer installed, thrust section moved into high bay for stacking at midnight.

The Ringwatchers

LabPadre

01.10.2023 -

September 2023[]

Date Description Source Link
30.09.2023 Booster puck shucker has been moved from Massey's to Sanchez Site

SpaceX: "Starship stacked at Starbase ahead of flight, team continues to work with the FAA on a launch license"

Elon Musk: "Starship is ready for flight 2!"

LabPadre
29.09.2023 S24.2 transported to Masseys

The first CO2 tank has been moved into the megabay for installation on B10; lifted ~ 20 minutes later

The Ringwatchers
28.09.2023 B13 M:16 stacked with A5:4 creating M:20 (20/24 rings stacked)

B13 (former) AX:4 is scrapped.

The Ringwatchers
27.09.2023 S27 AX:4 relocated to Massey's, arrived at around 01:50 [part of the second tileless ship that was previously cut in half]

B13* (apparently former) AX:4 moved to the Scrapyard

S27 AX:4 [aft section] moved into the nosecone cage for structural testing

B13 A5:4 moved into the Mega Bay for stacking

S25 once again lifted onto B9+HS:1; followed by a full speed retraction test of the ship QD

S29 cryo proof test; both tanks partially filled at Massey's test site at 18:15, detanking at 19:50

S26 transport stand left launch site, headed to remedios avenue

Intermittent road closure scheduled for Friday 29 September (12am-3am)

The Ringwatchers
26.09.2023 B9 HS:1 [hot staging ring] was lifted back onto B9

S26 attached to LR11000X again

S29 cryo proof test

The Ringwatchers

LabPadre

25.09.2023 S31 N:12 stacked on ML:4 creating N:16

FCC license granted for Starship launches from 27 Jan 2024 - 27 July 2024, this is an extension to an already active license FCC

The Ringwatchers

LabPadre

24.09.2023 -
23.09.2023 -
22.09.2023 Ship 29 transported to Masseys whilst sitting on the Ship puck shucker

B10 engine section purge tank spotted before installation Randolph Visuals

Massey's tank farm was active for possible S29 test, but no visible test took place

S31 ML:4 [mid lox section] moves into the high bay

EDOME test tank 2 (=TT14) moved from ring yard to Massey's test site, where it arrived around 22:22

The Ringwatchers
21.09.2023 Booster puck sucking stand moved to Massey's Outpost, Ship puck shucking stand was returned to production site

B9 HS:1 is removed from B9; work on fwd dome section started

S29 lifted off its standonto the ship puck shucker

S26.1 conducts a burst test. Failure seems to be around the aft end.

Vented Interstage lifted off Booster 9

The Ringwatchers

LabPadre

20.09.2023 B10 rolls back from Massey's to Megabay 1 on the booster puck shucker

B13 aft tank #5 quad staged outside Megabay 1

New 2-point ship lifting jig moved to ring yard after a test yesterday, possibly for S29 lift

S26 detached from LR11000X

B10 is lifted onto the engine install stand inside Megabay 1

Booster thrust simulation stand (puck shucker) moved out of mega bay 1 after B10 was lifted off it

Deluge T Vent pipes returned to launch site

The Ringwatchers

LabPadre

18.09.2023 FAA [on IFT-2 launch license] submitted a draft update of the Biological Assessment to FWS:
  • The FWS is considering the operation of a water deluge system in Starbase and its environmental effects.
  • The FWS has up to 135 days to submit the final biological opinion to the FAA (Started in August).

B13 A4:4 moves into the Mega Bay for stacking

B13: M:12 is stacked onto A4:4 creating M:16 (16/24 rings tall)

S29 TPS tiles placed over the lifting points on the nosecone Chris Bergin

New intermittent RC for 20 September (10pm-1am)

The Ringwatchers

LabPadre

17.09.2023 B10 cryo proof test (full LOX load, minor CH4 load) LabPadre
16.09.2023 Chopsticks raised to ship (S25) load points between 00:50 and 1:00 LabPadre
15.09.2023 SpaceX: pictures of fully stacked Starship 9/25

New intermittent RC for 19 and 20 September, 10p-1a

FAA on IFT-2 license: In a newsletter, the FAA announced that they are conducting a Written Reevaluation to the PEA due to changes of the launch infrastructure as part of the license application determination process

B10 cryo proof test (partial LOX load)

Chopsticks lowered from S25 at 17:50

Booster transport stand moved from former tracking station to Sanchez site

14.09.2023 B13 next section of LOX tank staged outside mega bay 1 at around 04:25

S31 stacked on its common dome section inside high bay, now 4/6 sections tall

McGregor: Raptor vacuum engine was tested in chilled conditions to mimic conditions after a long coast period in space (according to SpaceX)

McGregor: SpaceX recently conducted a cold start demo of a Raptor Vacuum engine for the NASAArtemis Starship HLS. This test fired pre-chilled engine hardware simulating in-space thermal conditions for landing on the Moon (according to NASA Marshall)

Starship 9/25: S25 destacked from B9 for final preps and FTS work

LabPadre
13.09.2023 B13 LOX tank stacked onto next 4-ring barrel section between 11:00-11:30 after it was moved into mega bay 1; 12/24 rings tall

NASA: The environmental assessment draft for the Roberts Road and Saturn Road expansions has been released and there will be a public comment period from Sept 14 - Oct 16. Draft: https://netspublic.grc.nasa.gov/main/RR%20North%20Expansion_Draft%20SEA.pdf FAA: The FAA told Reuters that the Starship launch license amendment might be granted as early as next month. Next launch out of Boca Chica will also need to be approved by the Fish & Wildlife Service, which has not provided any dates OLM work platform returned to launch site after repairs or modifications at Sanchez site, moved under OLM OLM work platform raised under B9 at 22:00-22:10

S25 transport stand moved to the OLIT

B10 cryo proof test, full CH4 tank load

LabPadre
12.09.2023 B11 moved from rocket garden via Hwy 4 into Mega Bay from 3:20-5:35

SpaceX crews took photos at launch site

B11 lifted off its transport stand onto B10's old transprot stand in the back right of mega bay 1. B11's transport stand then was moved to the Sanchez site

LabPadre
11.09.2023 B10 arrived at Massey's early morning

Jeff Foust: SpaceX senior vice president of commercial business Tom Ochinero says that the company is "real close" to next launch and that they are 2working closely with the regulators" at this point S31 cmn dome section moved into high bay at 15:56

LabPadre
10.09.2023 Massey's booster thrust simulator stand moved into mega bay 1 shortly after midnight

B10 lifted onto Booster puck shucker at build site at around 12:50

B10 started to move towards Massey's test site

LabPadre
09.09.2023 S31 stacked ond its forward dome section inside high sections (3 of 6 sections tall)

Third large deluge water tank shifted on its pedestals by LR11000X crane for final installation at OLS

LabPadre
08.09.2023 Replacement manifold for deluge water tanks lifted into position between 02:45-03:00

SN20/S20 lifting points started to being covered with TPS tiles

LR11000 detached from S26

FAA and SpaceX closed Starship 7/24 mishap investigation and issued statements about the process and necessary upgrades

Intermittent RC scheduled for 10 September 10pm-1am

Booster thrust pucker rolling back from Massey's to production site

LabPadre
07.09.2023 OLM work platform moved to build site early morning

Part removed from deluge tank farm

S31 fwd dome section moved into high bay at around 04:25 S26 rolled out to launch site

S26 connected to LR11000X

Chopsticks released S25 at around 15:00

New replacement manifold for deluge water tanks arrived at launch site

Intermittent RC scheduled for 8 September 10pm-1am

S26 lifted onto SoLS Pad B by LR11000X

LabPadre
06.09.2023 Ship lifting suid delivered to launch site early morning and Maarvin crane moved back over near Pad B for possible S26 stacking

Intermittent RC scheduled for September 7 10am-12pm, likely for S26 roll-out

HLS nosecone being painted white (RGV)

Eric Berger / FAA: According to Eric Berger, the FAA says that the Starhip mishap investication remains open.

Marine notices for both the Gulf and Hawaii have been pulled as of 9/6 and no future date is currently scheduled

OLM work platform lowered at 18:11 and removed from OLM area 3.5 hours later

LabPadre
05.09.2023 S25 roll out completed

Starship 9/25 stacked for the first time

S31 fwd dome section staged outside of high bay for stacking

B13 cmn dome section and a 4-ring barrel stacked; LOX tank stacking began - now 8/24 rings tall

Elon Musk: Starship is ready to launch, awaiting FAA license approval

LabPadre
04.09.2023 David avery: New Marine hazard notices for IFT-2 issued for 8–13 September 2023, 15:10-18:50; also for Hawaii

Two SPMTs with counterweights and ship-moving couplers moved to rocket garden for S25 roll out

S25 started to roll out from rocket garden to launch site for lifting onto B9

LabPadre
03.09.2023 Rollout cones deployed (S25 roll out) LabPadre
02.09.2023 Cowboy Dan (IFT-2): "Boat #SpaceX used for ops during first orbital flight test is inbound to #Starbase atm. The former GLADYS D had been offgrid last three weeks around Pensacola FL." LabPadre
01.09.2023 CSCC2 SAA listed near term planned Starship milestones (Barry Jenakuns):
  • First launch with payload in Q1 2024
  • Successful Starship Recovery Q3 2024
  • Starship LEO creweed space station PDR Q4 2028

Booster common dome section, possibly for B13, staged outside Mega bay 1. Several visible changes: extra LOX ullage vent on each side, modified autogenous pressurisation pipework

LabPadre

August 2023[]

Date Description Source Link
31.08.2023 S31 nosecone stacked on payload section inside high bay

"A structure believed to be the 'elevator floor' of an engine installation stand, previously seen in flyover pics of  the Sanchez site, was moved into the Ring Yard just before 06:30 CDT, and taken straight into MB1 - Rover cam" (Jon Tait, LabPadre)

"A structure believed to be the main ring of an engine installation stand, also previously seen in flyover pics of the Sanchez site, was moved into the Ring Yard at  10:40 CDT, and was also taken straight into MB1 - Rover cam" (Jon Tait, LabPadre)

S26.1 test tank lifted off its stand and likely set on the gorund in the burst pad area at Massey's

B9 FTS explosives delivered and work on FTS (Starship Gazer)

LabPadre
30.08.2023 S32 payload bay door installed

Tent lifted at Massey's S31 nosecone moved into high bay at around 13:45 S25 Logo added (upside down though) (@CosmicalChief) S31 payload bay moved into high bay at 20:05

LabPadre
29.08.2023 S25 TPS tile installation continued

"Booster Stabilization pins on the OLM used for placing and removing Boosters from the pad are being removed indicating no intention of B9 to be removed by anything other than its own power - Rover 2 Cam" (Anomalia - LabPadre)

LabPadre
28.08.2023 IFT-2 Upadate: "From what I'm hearing, the next SpaceX Starship launch attempt is still weeks away, pending FAA approval. Modifications, such as the water deluge system, need to be approved. As always, the process is fluid and can speed up or slow down depending on a number of factors but as of now 9/8 doesn't appear likely." (Christian Davenport)

B12 final stacking

LabPadre
27.08.2023 Back columns of mid bay cut through ahead of demolition

Mid bay demolished (blown up during a temporary road closure)

LabPadre
26.08.2023 Tent 1 demolition completedOLM work platform raised under B9 at around 02:45

Ship lifting pins deployed on chopsticks

LabPadre
25.08.2023 New E-Dome test article stacked in high bay

FCC license granted from 7 September 2023 to 23 February 2024 (FCC)

B9 static fire test #2S25 tilework on lifting points complete

Demolition of Tent 1 started to make place for the new Starfactory expansion

LabPadre
24.08.2023
23.08.2023 IFT-2 Update: "A new NOTMAR indicates the IFT-2 launch date is now NET September 8th." (NAVCEN)

B9 spin prime test #2

S30 fully stacked and lifted off the turntable onto the transport stand

LabPadre
22.08.2023 Can crusher removed from hot staging ring at Massey's

Intermittent RC issued for today from 8am-12pm or 12pm-4pm

B9 rolled out to OLS and lifted onto OLM

LabPadre
21.08.2023 B9 moved inside mega bay early morning LabPadre
20.08.2023 Demolition of mid bay began

BQD lines purged

LabPadre
19.08.2023 Barricades put up in front of mid bay ahead of possible demolition

Starfactory phase 1 and phase 2 buildings being connected (WAI, @CosmicalChief)

LabPadre
18.08.2023 S30 stacked onto its aft section in high bay - stacking complete

Tent 2 demolition completed

S29 first aft flap installed

New RC (intermittent) for 19 August from 10am-1pm or 5pm-8pm

S29 payload bay door removed at around 22:00

S29 new payload bay door installed at 22:30

LabPadre
17.08.2023 B10 moved from rocket garden into mega bay

Raptor engine installation on S28 underway, engine SN164 spotted (RGV)

SpaceX posted a long duration test fire of Raptor while gimaled 15 degrees (here); according to Elon Musk the purpose of this test was "Landing burn max gimbal deflection" (here)

B9 spotted with hot staging ring (RGV)

S30 aft section moved into high bay and placed oto the turntable

LabPadre
16.08.2023 Marine hazardous operations notice published for "rocket launch activities" for 31 August

LR11000 crane at build site raised to work on roof on mega bay 2

A girder for one of mega bay 2's bridge crane was moved into the ring yard at 14:18 and has been offloaded onto the cribbing in front of mb2

Demolition of tent 2 has begun

Hot staging ring with some shielding rolled towards mega bay

Hot staging ring for B9 lifted

LabPadre
15.08.2023 S25: workers began covering the windward side lifting points with steel plates, which will later be protected by TPS tiles

Booster header tank spotted, label "Property of Crew Starship, not scrap", heading towards lbj blvd and parked next to S22 nosecone [HLS]

Kevin Randolph: Second hot staging ring article spotted in the ring yard S29 moved out of the high bay

Jack Kuhr: SpaceX has filed the IFT-1 mishap report to the FAA

Four RBQD tests conducted at 21:30, 21:47, 22:14 and 22:36

LabPadre
14.08.2023 Ship cryo stand next to OLS berm removed at around 13:00, following the removal of the booster cryo stand on 9 August 2023. In the future, all cryo testing and thrust simulation tests will be performed at Massey's test site (Jon Tait) LabPadre
13.08.2023
12.08.2023 RBQD purge at 10:01

S22's old nosecone removed from mid bay last night, rolled to a new pad near the payload precessing facility. It has been outfitted with a significant amount of electrical work and some ducting or piping (Mouser)

S25: two leeward lifting points have received a cover, similar as observed on S24 ahead of the test flight (RGV weekly)

Highly modified S22 nosecone, believed to be a test article for HLS, lifted off the SPMT together with its short stand and set down on a new pad near the vehicle service garage at the northeast end of the village at around 21:50 (John Tait)

LabPadre
11.08.2023 Mega bay 2 bridge crane has arrived (RGV) LabPadre
10.08.2023 Third new water tank installed at the water-cooled steel plate supply system / water deluge tank farm at OLS

OLM work platform moved under OLM and raised at around 14:20

LabPadre
09.08.2023 LR11000 crane at build site laid down for boom extension to work on the roof of mega bay 2 at 08:50

S30 stacked on midlox section inside high bay, now 5/6 sections tall Third new water tank for new deluge water tank farm arrived at launch site at 20:29

LabPadre
08.08.2023
07.08.2023 New intermittent RC schduled for 7 August, 9pm-12am

B9 attached to chopsticks and lifted off OLM by chopsticks at 13:07 Chopsticks lowered away from B9 lifting points, and opening to release B9

B9 rolled back to the build site

LabPadre
06.08.2023 S25 rolled back to rocket garden where SN15 stood earlier

FIREX detonation suppressiom tested under B9 ahead of today's test Ship puck shucker stand moved back to massey's test site after S28 moved back to build site

B9 static fire

Second tracking dish being dismantled

LabPadre
05.08.2023 S28 arrived at rocket garden from Massey's, LR1750 crane picked up the ship lifting squid

S25 lifted off Pad B onto transport stand by LR11000 crane

S28 lifted onto raptor installation platform at Rocket garden by LR1750 crane

Mega bay 2: Last pre-assemblet corner section lifted for installation

S25 detached from LR11000

B9 igniter test at 19:55:53

Overpressure notice for static fire issued (B9)

LabPadre
04.08.2023 S30 stacked onto common dome

S30 mid-lox section moved into high bay for further stacking

B9 spin prime test and another test cycleShip QD and QD arm on OLIT performed a full speed retraction test at 18:05 S28 left Massey's, moved towards rocket garden

LabPadre
03.08.2023 OLM work platform lowered and removed from OLM area

Mega bay 2: 3rd corner section of 5th level lifted

S28 cryo proof test at Massey's test siteS25 ship QD disconnected ahead of lift off pad B

LabPadre
02.08.2023 S30 cmn dome section moved into high bay at around 10:40 am

One of the two main tracking dishes was disassembled

Mega bay 2: Final corner section of 5th level arrived at ring yard

RC: Intermittent rollout closure for 3 August from 9-11 am

LabPadre
01.08.2023 Can crusher "top hat" placed on hot stage test article at Massey's LabPadre

July 2023[]

Date Description Source Link
31.07.2023 S30 stacked onto fwd dome section in high bay, now 3/6 sections complete

RC: temporary and intermittent road delay scheduled for 1 August 9–11 am

LabPadre
30.07.2023 S26.1 leg skirt, now heavily reinforced, rolled into ring yard at 12:17, followed by hot stage test ring 3 hours later

B11 Hot stage test article and its components arrived at Massey's

LabPadre
29.07.2023 Raptor installation platform moved to launch site with engine shielding on top

Mega Bay 2: 2nd corner section of 5th level lifted; 3rd corner section of 5th level arrived at ring yard at around 20:53

LabPadre
28.07.2023 Chopsticks lifted ahead of deflector test

OLM full water deluge test (SpaceX picture here, SpaceX video here, Musk video here, NSF video here, LabPadre video here)

Chopsticks lowered onto resting point after deluge test S28 cryo proof test at Massey's

RC: Temporary / intermittent rc scheduled for 30 July 9pm-12am, 31 July 10pm-1am (1 Aug)

LabPadre
27.07.2023 S26 attached to LR1750 at 4:08 am

Mega bay 2: First corner section of 5th level lifted S26 removed from engine install stand, placed onto a transport stand at rocket garden

LabPadre
26.07.2023 OLM: Dog house cover reinstalled over pipework

S30 fwd dome moved into high bay at around 14:30

SN15 scrapping started: raceway cut at fwd dome weld, nosecone removed, later nosecone cut off its fwd dome

LabPadre
25.07.2023 LR1750 attached to SN15 at rocket garden

Chopsticks lowered to bottom stop between 18:15-52

A modified hot stage load head rolled out to ring yard

MB2: Second section of 5th level arrived at ring yard at 20:55

LabPadre
24.07.2023 Raptor installation platform reassembled in a shorter configuration after being cut apart a few weeks ago for modifications

Ship QD panel extended for first time since its reinstallation on OLIT

LabPadre
23.07.2023 S27 common dome apparently imploded, likely the reason for its scrapping (RGV)

B9 full cryo/prop load test

LabPadre
22.07.2023 B10 arrived to rocket garden shortly after midnight

MB2: First section of 5th level arrived at ring yard at around 21:27

OLM work platform lowered onto water-cooled steel plate at around 22:26

LabPadre
21.07.2023 S28 rolled out and waited at build entrance a few minutes after midnight

S30 nosecone moved into high bay for stacking

S28 moved to Massey's test site for testing

Chopsticks released and opened on B9 after lifting it yesterday; ship QD arm swung back in

S30 nosecone stacked on its payload section inside high bay, now 2/6 sections tall

B10 moved from Massey's towards rocket garden

LabPadre
20.07.2023 S30 payload bay section moved into high bay for stacking

S27 cut in half early this morning (5:53)

B9 rolled out to launch site

Chopsticks moved up and latched into B9's upper lift points

LR11000 at build site laid down for reconfiguartion for work on fifth level of MB2

S28 transport stand moved out of high bay as ship is being lifted likely to be put onto the thrust simulator from Massey's site

Booster transport stand stabilization pins tested ahead of B9 lift

New booster hot staging section spotted by Starship Gazer (here), revised design compared to May 25th

Massey's ship puck shucker moved into high bay and S28 was set onto it

B9 lifted onto OLM

Intermittent RC for 21 July 10pm-1am

LabPadre
19.07.2023 Mega bay 2: final section of 4th level lifted

New puck shucker test stand that was under construction at the ship cryo station at Massey's moved to build site

Three new intermittent rolllout closures for July 20, 6:30-9:00am, 12:30-3:00pm, 10:00pm–01:00am

LabPadre
18.07.2023 B9 moved from mega bay to rocket garden

New intermittent RC for July 19, 10pm-1am

B10 cryo tested at Massey's test site, both tanks partially filled

FIREX system tested on the OLM at 21:43

LabPadre
17.07.2023 Chopsticks raised ahead of testing

OLM deluge system initial testing (not at full power; SpaceX picture here, NSF video here)

Mega bay 2: 4th section of 4th level arrived at build site

LabPadre
16.07.2023 Two SPMTs with counterweights moved into mega bay 1

B9 moved to entrance of Mega bay 1

Tank delivered to launch site and installed at the water deluge area at the OLS

LabPadre
15.07.2023 New intermittent RC for July 16, 6-8pm

LR1750 crane unhooked from S26, hooked up to S27

Orbital tank farm spooled up with LOX and CH4 subcoolers chilling for the first time since IFT-1 for unknown GSE testing

LabPadre
14.07.2023 Mega bay 2: 3rd section of 4th level lifted into place

BQD extended

Raptor QD test at 23:20:24

LabPadre
13.07.2023 New intermittent RCs for July 14 (2-5pm) and July 15 (6-8pm)

BQD full speed retraction test at 19:21

LabPadre
12.07.2023 Purge of part of the deluge system was performed

A booster transport stand entered hwy4 from Sanchez site, moved back to SPMT storage area

Mega bay 2: 3rd section of 4th level moved from Sanchez to build site

LabPadre
11.07.2023 Grid fin moved into mega bay 1, installed on B12 CH4 tank

Mega bay 2: 2nd section of 4th level lifted

B12 second grid fin installed at CH4 tank

Structural test article with Pez Dispenser rolled out

LabPade
10.07.2023 Elon Musk commented a Ship 9-engine layout plan by CSI starbase: "Inner engine gimbal angle is limited in some directions, due to impacting outer engine nozzle, but probably ok" here

Elon Musk Update: "Looks like we can increase Raptor thrust by ~20% to reach 9000 tons (20 million lbs) of force at sea level." "And deliver over 200 tons of payload to a useful orbit with full & rapid reusability." link 1, link 2]

50 rockets flying every 3 days on average enables over a megaton of payload to orbit per year – enough to build a self-sustaining city on Mars.

LR11000X picked up ship lifting squid at Pad B

LabPadre
09.07.2023 Chopsticks lowered, ship QD arm swung in LabPadre
08.07.2023 OLS: Second manifold for water cooled steel plate placed under OLM for installtion

B10 arrived at new booster cryo stand at Massey's test site at 2:52

OLS: Third manifold for water cooled steel plate placed unter OLM for installation

Ground fabrication building reassembly began at far end of Sanchez site

Mega bay 2: 2nd segment of 4th level arrived at ring yard

OLS: Large Y-pipe that will feed water to 2 of the 3 manifolds for the water-cooled steel plates was lifted and moved into position

LabPadre
07.07.2023 OLM work platform moved under OLM

Mega bay 2: First segment of 4th level lifted

SPMTs moved under B10 for roll out

OLS: First of 3 manifolds for water cooled steel plate installed

B10 started to move to Massey's test site

LabPadre
06.07.2023 Old B11 fwd dome section moved into tent 1 (add: later hot staging test article)

OLS: Two water-cooled steel plate manifolds arrived at OLS, other parts also delivered

New intermittent RC for 7 July 24 (10pm-1am) [for B10 roll out]

OLS: Third Manifold arrived at OLS

LabPadre
05.07.2023 [1] S28 payload door reinstalled

GMK7550 and LR11000X cranes attached to water-cooled steel plate for lift onto vertical transport stand ahead of installation under OLM

New intermittent RCs for 6 July 2023 10am-12pm and 9-11pm

Water cooled steel plate moved under OLM and installed under it

LabPadre
04.07.2023
03.07.2023 Concrete work at OLM

B11 FWD with label "Hot stage load head" spotted in ring yard (RGV)

Foundation work at OLM: 171 trucks of concrete; together with the loads from June 25, this is about 5411 tons of concrete (Zack Golden)

LabPadre
02.07.2023
01.07.2023 Mega bay 2: 4th section of 3rd level lifted and installed

Ship QD plate lifted back onto SQD arm at 11:00am

Mega bay 2: First segment of 4th level arrived at ring yard

LabPade

June 2023[]

Date Description Source Link
30.06.2023 Ring with smooth dome and 24 holes moved into highbay

One of the extending work platforms on ship QD arm was removed

Water cooled steel plate for OLM deluge moved to launch site (21:54-22:15)

Ship QD plate moved back to launch site

LabPadre
29.06.2023 Tile-less ship payload bay moved into high bay for stacking, possibly for a stress test article [??]

First of several new horizontal CH4 tanks has been lfited and installed on its pedestals at the westwards extension of the OLS tank farm

Water cooled steel plate spotted for first time inside inventory tent (pictures by WAI and Starship Gazer)

New intermittent RC for 30 June 2024 (9-11pm)

LabPadre
28.06.2023 First of several new horizontal CH4 tanks arrived at OLS for the OLS tank farm extension

Mega bay 2: 3rd segment of 3rd level lifted and installed

LabPadre
27.06.2023 Elon Musk Update on hot staging: "Three center raptors of Booster will fire at ~50% thrust during hot staging"

Mega bay 2: 4th segment of 3rd level moved from Sanchez site to build site

LabPadre
26.06.2023 OLM foundation work: Pouring completed around 9:30 am, pumps left the launch site 30 minutes later; 132 Truck loads of concrete (Zack Golden)

S25 6-engine static fire

LabPadre
25.06.2023 Mega bay 2: 3rd segment of 3rd level moved to ring yard for installation LabPadre
24.06.2023 Booster QD backhood installed on OLM

Jeff Foust announced Musks and SpaceXs plans to introduce hot staging:

-"Musk said SpaceX has made a "late-breaking" change to Starship/Super Heavy stage separation, switching to a hot-staging approach where the ship lights its engines while a few booster engines are still firing. He estimates a ~10% increase in payload performance with this." (Foust)

-"That will involve an extension to the booster with vents for the ship exhaust and shielding to the top of the booster, he says. He estimates both the vehicle and pad upgrades will be complete in about six weeks. [Recall in late April he expected to be ready to fly in 2 months…]" (Foust)

-"Musk says they have made improvements to Raptor engines as well. He believes the next Starship/Super Heavy launch will have much higher chances of success, estimating 60% at one point." (Foust)

Mega bay 2: 2nd segment of 3rd level lifted and installed

B11 moved via hwy 3 and Sanchez site to rocket garden

LabPadre
23.06.2023 Booster transport stand moved from Sanchez site to ring yard

New intermittent RC for 23 June (10pm-12am)

Mega bay 2: 1st segment of 3rd level lifted, bolted down and detached from crane

Booster QD backhood moved back to launch site following post-launch inspections

LabPadre
22.06.2023 S28 second flaps moved into high bay and installed

Mega bay 2: 2nd segment of 3rd level moved to ring yard

LabPadre
21.06.2023 B12 CH4 tank stacked on final quad barrel (which was moved into mega bay earlier today), 13/13 rings tall

S25 flight like chill and spin prime test

LabPadre
20.06.2023 B12 aft section moved into mega bay for final stacking

OLM QD piping reinstalled

B12 LOX tank fully stacked inside mega bay

LabPadre
19.06.2023 Elon Musk announced a twitter space for subscribers about Starship and Starlink

B12 CH4 tank stacked on another triple barrel, 9/13 rings tall

OLS tank farm: CH4 deliveries resumed for the first time since flight test 1 (IFT-1)

LabPadre
18.06.2023 Ground fabrication building: last remaining beams removed LabPadre
17.06.2023 Mega bay 2: 4th segment of 2nd level lifted and installed, bolted down

New booster thrust puck delivered to Starbase

B12: another triple barrel moved into mega bay for stacking

LabPadre
16.06.2023 Mega bay 2: 3rd segment of 2nd level lifted and installed, bolted down

Mega bay 2: 1st segment of 3rd level moved from Sanchez site to build site for installation

LabPadre
15.06.2023 Mega bay 2: 2nd segment of 2nd level lifted for installation

B12 transfer tube moved into mega bay

B12 fwd dome section and triple barrel of CH4 tank moved into mega bay

Second elbow piece of water cooled steel plate manifold system lifted and installed

B12 CH4 tank assembly commenced: fwd dome and triple barrel stacked together in mega bay (6/13 rings tall)

OLM pad repairs advanced, rebar and concrete work RGV

NASA: NASA announced that it is working with SpaceX on potentially turning Starship into a space station. "This architecture includes Starship as a transportation and in-space low-Earth orbit destination element supported by Super Heavy, Dragon, and Starlink, and constituent capabilities including crew and cargo transportation, communications, and operational and ground support." This is part of a broader collaboration of NASA with seven U.S. companies to meet future commercial and government needs. The 7 companies are:

  • Blue Origin (space transportation capability)
  • Northrop Grumman systems (autonomous and robotic capabilities for research and manufacturing)
  • Sierra Space Corporation (commercial LEO ecosystem)
  • SpaceX
  • Special Aerospace Services (in-space servicing tech, propulsion, robotic tech AMU)
  • ThinkOrbital Inc. (ThinkPlatforms, CONTESA - welding, cutting, inspection...)
  • Vast Space LLC (tech and operations for microgravity and artificial gravity stations)
  • Eric Berger, NASA

B12 downcomer installed into LOX tank

LabPadre
14.06.2023 Mega bay 2: 2nd section of 2nd level lifted for installation, installation aborted likely due to high winds

S25 cryo proof test / spin prime abort

Mega bay 2: 4th segment of 2nd level moved from Sanchez to ring yard

LabPadre
13.06.2023 Elon Musk: "6-8 week" until next Starship test [IFT-2]

B12 LOX tank quad barrel moved into mega bay and stacked (now 20/24 rings tall)

Mega bay 2: 3rd section of 2nd level moved from Sanchez to ring yard

LabPadre
12.06.2023 S25 aft flaps untied and opened

Mega bay 2: 1st section of 2nd level lifted by LR11000 crane, installed and bolted down

Mega bay 2: Installed section detached from LR11000 crane and another one hooked up

LabPadre
11.06.2023
10.06.2023 Water deluge supply tank area: first tank moved to OLS, lifted into place

Water deluge supply tank area: second tank delivered to OLS, lifted into place next to first tank

LabPadre
09.06.2023 Stress testing framework removed from NC31 test article at Massey's test site

B12 LOX tank: barrel moved into mega bay for stacking

FCC: communications license for IFT-2 granted, 15.06.23-15.12.23

2 large tanks delivered to Starbase [water tanks for deluge area]

B12 LOX stacked onto another quad barrel (now 16/24 rings tall)

LabPadre
08.06.2023 OLM work platform left launch site around midnight LabPadre
07.06.2023 S25 detached from LR11000X

Jeff Foust citing Jim Free (NASA): "NASA is involved with Starship investigation, and just met with FAA. Do have concerns about their ability to meet Dec. 2025 date for Artemis 3. They have a "significant number" of launches to go before that mission."

Starfactory: Pre-assembled roof section lifted into place on the new starfactory expansion discord

B12 LOX tank stacked onto another quad barrel (now 12/24 rings tall)

LabPadre
06.06.2023 S29 removed off tunrtable, aft section put onto turntable for stacking

S29 lifted onto its aft section, now fully stacked

First section of "Heavy Metal" Building (current starfactory expansion) put vertically

LabPadre
05.06.2023 S34 nosecone left tent 3, all nosecones are now outside the tent LabPadre
04.06.2023 B12 common dome section and a quad-barrel moved into mega bay 1, and stacked - marking the beginning of the LOX-tank assembly (8/24 rings tall) LabPadre
03.06.2023 B11 CH4 tank removed from turntable, lifted inside mega bay ahead of final stacking

Over last 2 days, another 3 nosecones of S31, S32 and S33 left tent 3 ahead of its possible dismantling

S30 nosecone moved to the ring yard

B11 fully stacked inside mega bay

LabPadre
02.06.2023 Ship with 205mt tank for Starbase inbound to Brownsville Cowboy Dan

S29 thrust section moved into high bay for stacking

Tank delivered to Prot of Brownsville on UHL Falcon

Mega bay 2: Second segment of 2nd level moved to the ring yard

SpaceX: Starlink set an altitude and speed record for use in-flight during Starship's first flight test, providing connectivity at 123,600+ feet and while traveling at Mach 1.7

LabPadre
01.06.2023 B12 cmn dome section moved to mega bay staging pad for stacking

New turntable delivered to Starbase, likely for mega bay 2

S30 nosecone exited tent 3 fully tiled

First LN2 delivery to OLS tank farm since IFT-1

LabPadre

May 2023[]

Date Description Source Link
31.05.2023 Mega bay 2: 1st corner segment of 2nd level moved by SPMTs from Sanchez Site to ring yard LabPadre
30.05.2023 B12 first section moved to staging area in front of mega bay LabPadre
29.05.2023 Low bay demolished LabPadre
28.05.2023 Grover crane GMK7550 left launch site after midnight as the main pilling process under OLM was finished

LR11000 crane at build site went up

LabPadre
27.05.2023 B10 moved to rocket garden this morning Starship Gazer LabPadre
26.05.2023 Demolition of Ground fabrication building began in preparation of Starfactory expansion

B10 lifted up and put onto a transport stand that was moved into mega bay yesterday. First time a full Booster was lifted up and moved by both cranes

SpaceX Recap video released, confirmed S25 and B9 for IFT-2

Elon Musk: "Major launchpad upgrades should be complete in about a month, then another month of rocket testing on pad, then flight 2 of Starship"

LabPadre
25.05.2023 Booster transport stand moved into mega bay

S26.1 cryo tested at Massey's test site

Another starlink pez dispenser installed into a payload bay in front of low bay

S28 first aft flap installed in high bay

Cut outs in new ring section spotted LabPadre -> First hot staging ring spotted [Ringwatchers]

LabPadre

The Ringwatchers

24.05.2023 B11 at least three grid fins were installed over night

Elon Musk: "Starship payload is 250 to 300 tons to orbit in expendable mode. Improved thrust & Isp from Raptor will enable ~6000 ton liftoff mass."

LabPadre
23.05.2023 Raptor installation platform left launch site

Elon Musk confirmed that Ground Fabrication building, Propulsion buildings and Low bay will be removed for Starfactory expansion Zack Golden and Elon Musk

New grid fins delivered to mega bay, likely for S11 WAI]

OLM BQD retracted at 19:40

LabPadre
22.05.2023 LR11000 parts started to arrive at Starbase for construction of mega bay 2

Michael Sheetz: "SpaceX seeks to join the FAA as a co-defendant to fight the environmental lawsuit against the federal regulator over Starship, outlining potentially "severe" implications for the company. With @lorakolodny: https://www.cnbc.com/2023/05/22/spacex-joining-faa-to-fight-environmental-lawsuit-over-starship.html"

S26.1 Cryo proof test at Massey's

LabPadre
21.05.2023 Ship QD on SQD-arm has been removed by LR11000X

Back of BQD has been removed

S25 reattached to LR11000X

OLM: One of the main propellant lines for BQD was removed at 16:41

LabPadre
20.05.2023 B11 CH4 tank stacked on the final quad ring section, now 13/13 rings tall

S25 detached from LR11000X crane

LabPadre
19.05.2023 LR1300 crane began assembling the first level of mega bay 2 at its foundations

White high pressure tanks moved to launch site to be installed near the steel water plate water supply tanks

S29 stacked onto Mid-LOX section inside high bay, now 5/6 sections tall

McGregor: SpaceX released a video of a Raptor test firing into a water cooled steel plate, likely as a test for the water cooled steel plate that will be installed under the OLM

LabPadre
18.05.2023 S25 arrived at launch site; connected to LR11000X

S29 midlox section moved into high bay for stacking

Insallation of glass in mega bay top floor started

B11 CH4 tank stacked onto another 3-ring section, now 9/13 rings tall

LR1300 began lifting in positionfor reeving at build site

S25 lifted onto Pad B at SoLS (13:15-13:42)

S26.1 test tank underwent Cryo Proof Test at Massey's test site

LabPadre
17.05.2023 New intermittent RC for 17–18 May (11pm-3am) for S25 roll out

S25 started to roll out to launch site

LabPadre
16.05.2023 FCC: SpaceX filed a FCC permit request for IFT-2, start date NET June 15 Tyler Gray

S29 was attempting to stack ont the common dome again, first section to be stacked with new 2-point load spreader

B6 test tank was tipped over as scrapping of the recently ruptured tank continued

OLM: Water cooled steel plate (pre-)assembly underway RGV

S25 roll out started and aborted

LR11000 picked up ship lifting squid [for S25 lifting]

LabPadre
15.05.2023 Michael Sheetz / SpaceX team: Kathy Lueders, former top NASA human spaceflight official, joined SpaceX according to CNBC sources. She will be based at Starbase and will report directly to president & COO Gwynne Shotwell

Intermittent RC for 15 May revoked, new intermittent RC for 16 May (10pm-2am)

A Bruckner LR1300 arrived at Starbase, likely to assist with construction of the new mega bay

B6 test tank tested to destruction with water in what appeared to be a test of the FTS system

LabPadre
14.05.2023 LR11000X was risen again, having been laid down since a week before IFT-1 LabPadre
13.05.2023


Elon Musk gave updates on Raptor engine:

-Musk: Raptor V3 just achieved 350 bar chamber pressure (269 tons of thrust). Congrats to @SpaceX propulsion team! Starship Super Heavy Booster has 33 Raptors, so total thrust of 8877 tons or 19.5 million pounds. 1, graph included]

-Bergin: Epic! Was it the firing on the Tripod Stand? Been a busy day at McGregor!

-Musk: Yeah. To be frank, we did not expect the engine to survive a full duration run at that pressure. It is uncharted territory. 2

-Musk: Raptor chamber wall might have the highest heat flux of anything ever made 3

-Tim Dodd: As I’ve talked about in my “How to keep a rocket engine from melting” video and my video about Raptor 1 VS Raptor 2, SpaceX is employing regenerative cooling & a good amount of film cooling. Wonder if Raptor 3 completely eliminated the additional throat film cooling manifold yet

-Musk: No, we still have it. Chamber converging section desperately wants to melt next-level. We also have thermal barrier coatings. 4

-Evelyn Janeidy Arvalo: I wonder if Raptor V3 looks different or similar to Block 2

-Musk: If we can delete & integrate enough secondary structure (small, fiddly bits), then we can locally protect rest & delete engine heat shields 5

Elon Musk

LabPadre

12.05.2023 S29 stacked onto common dome using the new 2-point load spreader at 01:06, destacked again at 02:26

New intermittent RC for 15 May (10pm-2am)

LabPadre
11.05.2023 S29 common dome moved to high bay

B11 forward dome lifted and stacked onto a 3 ring tall section, CH4 section now 6/13 rings tall

LabPadre
10.05.2023 OLM: Approx. 100 ft/30m tall rebar lowered into place after piledriver completed drilling; concrete poured afterwards

HLS: Jim Free visited SpaceX to talk with the team about the HLS and to dive deeper on individual components. Pictures with HLS related info. Jim Free Catherina Koerner also took part Catherina Koerner

B11 fwd dome moved from the tents to staging area in front of mega bay

Squid removed from high bay bridge crane and replaced with 2-point lifter; 2-point lifter attached to S29 nose cone - would be 2nd lift with the new load spreader and the first time for stacking

LabPadre
09.05.2023 High bay 1: Scaffolding finally being removed WAI / Cosmical Chief LabPadre
08.05.2023 [none]
07.05.2023 OLIT cladding being reinstalled, interestingly the same, earlier removed panels are being used [Sparrow] LabPadre
06.05.2023 Piling/drilling machines delivered to OLP, new foundation work started LabPadre
05.05.2023 S26.1 cryo test at Massey's test site

S25 cryo test at Massey's test site

S29 stacked onto its fwd dome section

LabPadre
04.05.2023 S29 fwd dome moved into High bay for stacking LabPadre
03.05.2023 SoLS pad A thrust puck shucker removed

OLS tank farm: A hole on damaged LOX tank shell (Shell 4), that likely spilled LOX, has been patched with what appears to be a steel plate [Sparrow]

LabPadre
02.05.2023 OLIT damaged tower cladding removal began

OLM: New door cut into the OLM at the top of the new staircase for enabling crew access

OLM: Broken foundation rebar has been straightened out for repair RGV

OLM: "Doghouse" (cover for pipes at the base of OLM) cut free and lifted by crane. New blue pipes now going down into the crater Kevin Randolph

LabPadre
01.05.2023 OLM work platform (dance floor) and raptor install platform moved to the launch site

S29 nosecone stacked onto payload bay section; this marked the first operational stacking on the new turntable on the left side of high bay.

FAA: "Environmental groups sued the FAA today in federal court over its approval of SpaceX's expanded Starship launch operations next to a national wildlife refuge in South Texas without requiring greater environmental study." Joey Roulette

LabPadre

April 2023[]

Date Description Source Link
30.04.2023 First column for new mega bay lifted at Sanchez Site. "The new Bay is being built using the steel that initially was used [intended] for construction of the Roberts Road Mega Bay." [Sparrow] Starship Gazer LabPadre
29.04.2023 Storm at starbase

Elon Musk Starship Twitter Space [see OFT-1 for summary]

LabPadre
28.04.2023 S29 payload bay section moved into high bay for stacking

B11 aft section moved to mega bay at 09:51

S24 transport stand moved from launch site to ring yard Dag

RGV: A telehandler, forklift and multiple light towers are charred due to the fire RGV

B11 LOX tank stacked onto its aft section, LOX tank now 24/24 rings tall; CH4 tank stacking not yet started [Mouser]

LabPadre
27.04.2023 OFT-1: Footage from Evereyday Astronaut and Cosmic Perspective Released here

S29 nosecone moved into high bay for stacking

OFT-1 info: Nelson/Jeff Foust: "Nelson says SpaceX has told NASA that it can repair the pad and prepare the next Starship in about 2 months. Last week’s failure is “not a big downer”." Fire spotted at Massey's test site around 7pm, cause unknown, extinguished later in the night

LabPadre
26.04.2023 OLM: Scaffolding assembled

OFT-1 info: US Fish and Wildlife assessment of launch: "US Fish and Wildlife has made its assessment on the impacts of SpaceX's Starship launch:

-- 3.5-acre fire started south of the pad

-- 385 acres of debris on SpaceX land and Boca Chica State Park

-- concrete chunks and other objects hurled thousands of feet

-- no debris documented on refuge fee-owned lands

-- no dead birds or wildlife reported" Loren Grush

LabPadre
25.04.2023 S28 lifted off turntable using the new two-point lifting jig at 03:18

S29 nosecone moved from in front of windbread to ring yard at 09:55

Booster QD extended for first time since launch at 18:30 [Epic Spaceflight]

LabPadre
24.04.2023 Chopsticks moved down the OLIT, causing relief in the community as it was a sign that the pulley, cable and the winch didn't seem to significantly damaged

S27 rolled out to the rocket garden Kevin Randolph, WAI

New two-point lifting jig testing started on S28 in high bay

LabPadre
23.04.2023 Workers entered OLM at 09:57 LabPadre
22.04.2023 OFT-1 (aftermath continued)

S27 moved inside high bay

21.04.2023 OFT-1 (aftermath continued)
20.04.2023 OFT-1
19.04.2023 Lot of work on B7 north HPU cover and booster QD

OLM work platform (dance floor) lowered with visible scaffolding removed at around 16:04

OLM work platform departed launch site around 16:30

OFT-1 Updates:

-FAA: April 22 added to list of potential launch dates

-VixXi: "Cryo fuel delivery update. Total deliveries since "Scrub" up to midnight 18 April.

  • 53 x LN2
  • 23 x LOX
  • 4 x CH4"

-SpaceX, Lucid: "During the Starlink Group 6-2 launch, Jessie confirmed Starship could in fact have a second launch attempt as soon as tomorrow morning, but could likely scrub. (At T-5 minutes in the stream)"

-Flash: "neighborhood to evacuate again."

-LabPadre: Press members arrived at launch complex at 14:18

-SpaceX: "Teams continue working towards Thursday, April 20 for the first flight test of a fully integrated Starship and Super Heavy rocket"

LabPadre
18.04.2023 OLM work platform (dance floor) returned to launch site and raised just before 08:00

Extensive work on B7 HPU covers and OLM booster QD

SoLS Pad A thrust rams started to being removed at around 19:44

OFT-1 Updates:

-TFRs for April 20 removed; for April 23–24 posted

-ATCSCC advisory: Primary: 04/21/23, Secondary 21–28

-TFR for April 20 restored

-NOTMAR, Baylor: New NOTMAR posted for April 20–28

-ATCSCC advidory: April 20 added back to list as primary launch date

-Cameron County: "SpaceX is targeting  Thursday, April 20th for the integrated flight test of Starship from Starbase in Cameron County, Texas. [...] Residents of Cameron County and those in the nearby area may hear a loud noise resulting from the rocket’s 33 Raptor engines firing upon ignition and as the vehicle launches toward space, but what people experience will depend on weather and other conditions."

-SpaceX: "SpaceX is targeting as soon as Thursday, April 20 for the first flight test of a fully integrated Starship and Super Heavy rocket from Starbase in Texas. The 62 minute launch window opens at 8:28 a.m. CT and closes at 9:30 a.m. CT."

-Musk: "The team is working around the clock on many issues. Maybe 4/20, maybe not."

LabPadre
17.04.2023 Starship 7/24 OFT-1 integrated test attempt scrubbed, WDR instead

Tankers started delivering consumables to the OLS tank farm

OFT-1 Updates:

-ATCSCC advisory: new primary 19th, secondary on April 20–21

-TFRs for April 18–19 removed Space TFR

-SpaceX: "Teams are working towards Thursday, April 20 for the first flight test of a fully integrated Starship and Super Heavy rocket"

-SpaceX: "SpaceX has published the new official stream for launch, which will starts on <t:1681994700:f> in your local time.

The 62-minute window opens at 8:28 am, and closes at 9:30 am CT. https://www.youtube.com/watch?v=-1wcilQ58hI"

LabPadre
16.04.2023 OFT-1 Preparations:

-11:42 Tracking dishes pointing towards Starship 7/23

OFT-1 Updates:

-SpaceX: "Teams are completing final checkouts and reviews ahead of Starship’s first flight test attempt; weather is looking pretty good for tomorrow morning but we're keeping an eye on wind shear"

-Musk: "Launch attempt tomorrow"

-RGV: SpaceX issued media credentials

LabPadre

SpaceX

15.04.2023 Boom lifts haver returned to S24 and B7 FTS area at around 7:40

OLIT elevator's counterweight failed (sparks observed at 1:47:16; see here) and fell to the ground, crews inspected area

Temporary pressurization lines detached from S24 QD port

S24 lifted onto B7; fourth full stack of Starship 7/24

OLM work platform moved back to Shipyard, along with two SPMTs that were used to transport S24

B7 FTS installation completed late night

OFT-1 Updates:

-TFRs for Brownsville TX updated:

  • Fri, Mar 31, 7p CDT → Sat, Sep 30, 6:59p CDT: 10000 ft
  • Mon, Apr 17, 7a → 10:05a CDT: unl
  • Tue, Apr 18, 7a → 10:05a CDT: unl
  • Wed, Apr 19, 8:28a → 10:05a CDT: unl
  • Thu, Apr 20, 8:28a → 10:05a CDT: unl
  • Fri, Apr 21, 7a → 10:05a CDT: unl

-Cameron County: Issued a nose advisory for the test, beginning at 7:00 CDT and spanning the entire 150 minute launch window: "SpaceX is targeting as soon as Monday, April 17 for the first integrated flight test of Starship from Starbase in Cameron County, Texas. The 150-minute test window opens at 7:00 a.m. CT.

Residents of Cameron County and those in the nearby area may hear a loud noise resulting from the rocket’s 33 Raptor engines firing upon ignition and as the vehicle launches toward space, but what people experience will depend on weather and other conditions.

SpaceX’s live webcast will go live approximately 45 minutes before liftoff at spacex.com/launches. Live updates will also be available on SpaceX’s social media channels."

-Eric Garza: "Isla Blanca Park Temporary Operation Hours - Starship Launching: Effective tomorrow, Sunday, April 16, 2023, at 8:00 p.m., Isla Blanca County Park will be closed to all incoming visitors in preparation for the SpaceX Flight Activity scheduled for Monday, April 17, 2023."

LabPadre
14.04.2023 Chopsticks lifted to S24 lifting points

S24 and B7 FTS installation started

FTS installation on S24 completed at around 21:00

OFT-1 Updates:

-TFR: Unlimited flight TFR posted for Monday and Tuesday; 12:00-15:05 UTC

-NOTMAR: "New Marine Safety Information Bulletin (MSIB)/ Notice to Mariners (NOTMAR) issued for possible Starship testing on 17 Apr 2023 during 5:25a.m.-11:10a.m." Visit Boca Chica

-FAA: Launch License Issued [see article: FAA Launch License]

-SpaceX: "Targeting as soon as Monday, April 17 for the first flight test of a fully integrated Starship and Super Heavy rocket from Starbase in Texas → spacex.com/launches"

-SpaceX: released mission patch

-Berger: "SpaceX says the Starship launch window will run from 7am to 9:30am local time (1200-1430 UTC) on Monday."

-SpaceX: Official stream for launch published: https://www.youtube.com/watch?v=L5QXreqOrTA

-FAA: Programmatic Environmental Assessment amended (Written Reevaluation) for both vehicle's reentry plan [see: here, here; short summary by Alex:

  • Ship flight plan includes a passive decent with the Ship in the belly flop position until impacting the Ocean north of Hawaii. The impact is expected to result in structural failure resulting in an explosive event.
  • Second and Third flights of Starship will be with S26 and S27 (expected but now confirmed); not S25
  • Super Heavy will be landing on the surface of the ocean. SpaceX will NOT recover it and will instead try to sink it in any way possible
  • Ship 24 will have onboard flight recorders to be retrieved for data. This we kinda guessed from the hardware installed on its exterior but now it's confirmed.
  • A lot went into figuring out the impact to marine life due to Ship 24's impact with the water
  • As part of that study, they needed to study the way the transfer tube on Starship may be damaged due to sudden impacts. Something that they had previous experienced with SN10's hard landing
  • As part of that study, they needed to study the way the transfer tube on Starship may be damaged due to sudden impacts. Something that they had previous experienced with SN10's hard landing
  • This document covers the FireX system on the pad and it's supposed to be at least the first three flights. It doesn't mention the deluge system SpaceX is building so it makes me think this system may not debut until the fourth flight
LabPadre
13.04.2023 OLM work platform lowered around 11:55

LR11000X lowered once again

OFT-1 Updates:

-NOTAM for Space: "NOTAM for space found for Mexico. Valid from 17 Apr 2023 to 22 Apr 2023 (Window of 5 days)"

-Road closures for April 17–19 updated to list them as closures for flight operations

-Residents informed to evacuate on Sunday

LabPadre
12.04.2023 S24 destack continued LabPadre
11.04.2023 S24 destacked from B7 (Starship 7/24)

OLM work platform left back up under B7

S26.1 lfited onto Can Crusher for the second round of stress testing at Massey's; now 2 rings shorter as skirt section was removed prior to lift

LR11000X crane raised near SoLS tank farm

OFT-1 Updates:

-SpaceX: Launch stream for April 17 briefly appeared on YouTube

-SpaceX: "Teams are focused on launch readiness ahead of Starship’s first integrated flight test as soon as next week, pending regulatory approval – no launch rehearsal this week http://spacex.com/launches/"

-SpaceX: New info about telemtry, mission profile and timeline

-NOTAMs for Space: NOTAM for space for Mexico April 17–22

LabPadre
10.04.2023 LR11000X laid down near SoLS tank farm, possibly for WDR and launch

PEZ Dispenser installed into a payload section at 09:53

Portable camera rig sptted, may be used in an offical livestream

FIREX test at 18:08

SpaceX: Remastered animation of Starship released

OFT-1 Updates:

-Musk: "Starship launch trending towards near the end of third week of April"

-FAA ATCSCC Advisory: Times added again, and extended to April 22; Primary: 04/17/23 1200Z-1505Z; Backup(s): 04/18-22/23 1200Z-1505Z

LabPadre
09.04.2023 B7 additions were made to the stabilizer sockets, unclear why

OFT-1 Updates:

-Musk: "Starship is ready for launch Awaiting regulatory approval"

-FAA ATCSCC Advisory: updated: Primary: 04/17/23, Time TBD; no backups yet

LabPadre
08.04.2023 OLM platform lowered at 00:58

Musk Starship Update: "Will get bigger. Ship will probably stretch by another 10m or so."Twitter; "And we need to add 3 more Raptor Vacuum engines, because it’s inevitable" Twitter

LabPadre
07.04.2023 Flame diverter parts for OLM spotted at Starbase RGV

OLM scaffolding removed Eagle Eye Chuck

B11 downcomer/transfer tube installed Mouser

OFT-1 Updates:

-Navsafety NGA Mil: Hazard notices released for April 17–21; 1025Z-1610Z

Musk Starship and OLM Update: "High-strength stainless steel armor is needed to protect the launch stand from the world’s biggest blowtorch! Even steel will be eroded fast by the Starship booster plume. We will need to make a water-cooled steel jacket to achieve full reusability."

LabPadre
06.04.2023 S28 stacking in high bay completed

S26.1 at Massey's attached to crane for lift onto can crusher for another round of testing

OFT-1 Updates:

-SpaceX: "Starship fully stacked at Starbase. Team is working towards a launch rehearsal next week followed by Starship’s first integrated flight test ~week later pending regulatory approval"

-Musk: "Starship is stacked & ready to launch next week, pending regulatory approval"

-FAA ATCSCC Advisory: Now showing April 17 as launch date with backup on April 11–12 Romera; 1200Z-1505Z

LabPadre
05.04.2023 S28 thrust section moved into high bay for stacking

S24 stacked onto B7 for OFT-1; third full stack of Starship 7/42

Ship QD arm retraction test at 15:35 and reattached to S24 at 15:42

OFT-1 Updates:

-NOTAM for space for Mexico from April 10–12 NOTAMS

-Insprucker: "Spending time now working on webcast rehearsals for first test flight of Starship."

S28 stacking likely aborted

LabPadre
04.04.2023 Work platform raised underneath OLM at 2:38

S24 moved towards OLIT at 2am, moved between chopsticks at 02:50, aft flaps opened at 08:35

Chopsticks rose to S24 lifting hight at 09:15

Chopsticks locked into lifting pins of S24 around 10:08

Raptor Work Platform left launch complex towards build site [Epic Spaceflight]

Starship 7/24 OFT-1 updates/speculation:

-FAA most recent ATCSCC advisory indicates a possible OFT-1 of April 10 with backup launch dates of April 11 and 12

-Davenport: "For the SpaceX Starship launch attempt, 4/10 is possible, I’m told. The FAA safety evaluation is complete, the legal review is underway but there is an environmental issue to close out. That may or may not get resolved by Monday but it sounds like the license is almost there."

-Berger: "For what it’s worth SpaceX has told NASA it is targeting April 10, with backup days on April 11 and 12, for the Starship Orbital Flight Test. None of this is official without a launch license and the usual caveats apply. Who knew that wen hop applied to more than Easter bunnies?"

-FAA Spokesperson: April 10 date's appearance on the agency's ops plan advisory "should not be interpreted as an indicator that a determination to issue a license has been made or is forthcoming" for the SpaceX Super Heavy/Starship 7/24 orbital test flight. Stephen Clark

LabPadre
03.04.2023 06:33 FIREX test, another one at 08;41

B7 propellant load test

Ship pins on chopsticks extended out and arms opened for possible S24 stacking at 18:37

LabPadre
02.04.2023 B11 LOX tank: another 4 ring sectin had it's stiffener removed and moved into mega bay possibly for stacking (would be 20/24 rings tall) LabPadre
01.04.2023 B7 transport stand rolled back from launch site towards sanchez site

One Raptor engine moved to rocket garden, possibly for installation on S26

Starship 7/24 OFT-1 updates/speculation:

-Langbroek: "Navigational Warnings have apeared for the inaugural (and strictly speaking: suborbital) launch of SpaceX's Starship. It will go into a ~26.5 deg inclined orbit with splashdown in the Pacific Missile Range, Hawaii, some 1.5 hrs later, just before completion of 1 revolution." "26.36 degrees fits even better"

-Berger: "The last NET date I heard was April 10. So not this week, but they are getting rather close."

-Musk: "More than days away, but hopefully not many weeks away" -McDowell: Estimated flight trajectory

LabPadre

March 2023[]

Date Description Source Link
31.03.2023 S26 first raptor center installed, also first electric TVC Raptor to be installed on a ship

3 SPMTs moved to rocket garden ahead of S24 roll out

S24 roll out to OLS

Astrolab: "Today we announce a launch agreement with SpaceX - Our FLEX rover is headed to the Moon aboard a Starship landing system as soon as mid-2026. Once it completes its mission, FLEX will become the largest and most capable rover to ever travel to the [moon]"

Coast Guard: Hazard zone marked by Research Buoys are being placed by SpaceX in the general area of B7s splash down zone (OFT-1)

LabPadre
30.03.2023 OLM work platform lowered onto its stand at around 05:14

RC for today cancelled

B11 LOX tank lifted overnight and stacked on a 4-ring section, now 16/24 rings tall, next section moved to mega bay staging area

Temporary and Intermittent RC for April 1 (12am-3am)

SpaceX: Updated their Website with new information regarding the suborbital flights and construction of the OLIT and chopsticks

LabPadre
29.03.2023 B7 moved to OLM

OLM work platform lowered B7 lifted onto OLM

S26 second (SN212) and third Rvac engine moved for installation

Booster QD extended to B7

OLM work platform raised between 19:50-57

OFT-1:

-DutchSatellites: "The FAA is in the final stage of completing the launch license for Starship's Orbital Flight Test. SpaceX should have it in hand in under a fortnight."

-Davenport: "This tracks with what I’ve heard. Unless there’s an unforeseen problem, SpaceX should have the launch license for the Starship debut launch by April 14 or thereabouts. Then again, there always could be last-minute checks that cause delays."

LabPadre
28.03.2023 OLM Purge Test

SPMTs rolled under B7, counterweights loaded at around 03:40 S28 lifted and stacked on mid LOX section in high bay at 11:00; only downcomer and aft section missing

Booster QD retraction test in full speed at 15:02

Shipping containors moved near satellite dishes

Ship lifting pins on chopsticks retracted [vxtwitter]

NSF

Nic

LabPadre

[2]
27.03.2023 S32 scrapped aft barrel attached to crane (5 ring) [vid 28]

S24 worked on [vid 28]

S26 still attached to crane; preparations for engine installation with lfit platformmoved under it [vid 28]

OLM work continued [vid 28]

LOX delivery to OLS [vid 28]

Foundation work for new building near starfactory continued; earth work behind mega bay [vid 28]

SPMTs with counterweights moved to launch site, possibly to move B7

Helicopter arrived at build site which was previously used to patrol and clear around launch complex during major testing

RVac SN205 under S26 for installation

NSF Starbase Update:

-S26 moved from high bay to rocket garden, readied for lifting it on tall stand

-OLM legs extrensions filled with concrete, seeming quite late (they were added in 2021); pressure washer lifted onto OLM

-Signs for B7 return on OLM; FTS worked on, but explosive charges likely not yet added; HPU covers reinstalled again

-Foundation work for new building near starfactory continued

-More deluge manifolds at PPS; however not much work on deluge system at OLS

-B8 scrapped section attached to crane, lifted off transport stand

-B10 fully stacked

-S24-S27 have been stacked in two main sections (nc, payload, fwd dome, which are stacked on rest), S28 was now stacked in a strict top to down method instead of two separate parts; this way, the crane can rest attached to the nc during the whole process, furthermore welding robots will only need to work on the ground and not high up in the air; however, it remained unclear, how they would add the CH4 transfer tube, as it couldn't be lifted into the LOX tank from above anymore.

-S29? nosecone in tent 3 TPS installation, one flap installed at least

-S30 likely nosecone TPS tile installation; a payload section spotted as well in tent 3

-Starfactory: Ship fwd dome section, S30?, and booster aft dome section, B14?, and more barrel sections spotted

-Chopsticks scaffolding removed

-New stairs at OLM removed

-New fire suppression system tested, water being sprayed towards OLS tank farm

LabPadre
26.03.2023
25.03.2023 S26 lifted at rocket garden [vid 28]; placed on the new stand at around 1:52

Steel removed from OLM [vid 28]

Scaffolding removed under OLM [vid 28]

SPMTs with counterweights moved to launch site, possibly for B7 move to OLM [vid 28]

S31 PEZ dispenser installed into payload bay in front of tent 3

LabPadre
24.03.2023 S28 mid LOX section moved into high bay at 03:13

B11 LOX tank was lifted and stacked onto a 4-ring section, now 12/24 rings tall (13:14)

LabPadre
23.03.2023 [B10 fully stacked in mega bay]

Insulated pipe connected to crane at Massey's

WAI, Randoph: "B7 HPU covers have been reinstalled again. Again."

OLM new second set of stairs removed and transported away from launch site at 17:20

NSF

Nic

Jack

[3]
22.03.2023 S28 nc+payload [add: plus fwd dome] stacked on common dome section in high bay [vid 23] [add: new stacking method!]

OLM ventilation hose through shield access door; work near and on OLM [vid 23]

Ship fwd an booster aft sections in Starfactory [vid 23]

B10 CH4 tank stacked onto LOX tank, stacking completed at around 11:30

LabPadre
21.03.2023 Powerwasher lifted onto OLM, later lifted off again

B8 aft section lifted at production site

S25 cryo test at Massey's at around 23:00

McGregor: Tripod stand raptor test for 139 seconds; including throttling

LabPadre

NSF Nic

Jack

[4]
20.03.2023 OLM final panel for outer shielding installed [vid 21]

OLM concrete finally being pumped into the leg extensions [vid 21]

B7 worked on / inspected [vid 21]

Booster QD on OLM extended [vid 21]

Piling work for new building at production site continued [vid 21]

B8 scrapped aft section with header tank is attached to crane at sanchez site [vid 21]

Water deluge Manifold still being stored at Sanchez [vid 21]

Barrel section stand moved on SPMT at production site [vid 21]

S26 attached to new LR1750 crane at rocket garden [vid 21]

GTC-900 crane moved at rocket garden [vid 21]

B10 methane section attached load spreader and crane in mega bay [vid 21]

S28 nosecone attached to crane in high bay [vid 21]; cmn dome section moved into high bay at 18:49

Booster fwd dome spotted [vid 21]

Transfer tube outside tents [vid 21]

NSF Starbase Update:

-Elon Musk alluding to launch date: third week of April

-OLM work, shielding adding continued; New staircase being added at a northern leg; steel boxes being installed below the new outer shield, possibly related to some air vernting inside the mount; later, final outer shielding added

-Deluge installation continued

-Chopsticks worked on as well

-S24 tiles finally being installed

-High ship stand work continued, possibly for easier engine installation

-Piling and foundatin work for new builiding near starfactory continued

-Massey's: NC31 worked on; S25 attached to cryo station

-B7 one HPU cover removed again

-S26, S27, S28 in high bay worked on; B11 segments spotted

-S32 aft stiffened barrel scrapped for pucker made on wo 2795094 do not use for flight

LabPadre
19.03.2023 B11 stacking began with cmn dome lifted onto a LOX tank barrel; first operational stacking of the 2nd mega bay turntable and robot welder

S26 moved out of high bay at 23:30, arrived at rocket garden at 23:48, possibly to be lifted onto the new higher ship stand [vid 21]

LabPadre
18.03.2023 OLM work continued [vid 21]

Water deluge pipe lifted near OLM [vid 21]

B10 CH4 tank moved to mega bay for stacking at around 01:20

McGregor: Concrete pad / structure seen near horizontal stands, similar to the one spotted on February 7; raptor vs concrete test; south bay doors opened on super draco stand

LabPadre
17.03.2023 Mouser: "After a 4 ring section and a single went into Mega Bay, a 5 ring section emerged confirming a second welding robot and turntable have been installed in the front right of Mega Bay. The quint exits at 05:00 CDT..."

Remedios Storage Site near PPS work on the concrete Drilling for pilings and concrete foundation work continued next to Starfactory for a new building

Mega bay backside extension door has been installed rcently

S32 aft barrel section (scrapped for pucker), 5 ring

NSF Cape Update #21:

-Roberts Road:

--OLIT #3: Tower segments: floor panels for segments 1, 4, 5 being added; won't be for LC-40, and not for a catch only tower—Chopsticks #3 flipped for Shoulders installation; main carriage system structure put in place—Starfactory roof finished, wall looks complete

-LC-39a:

--LR11350 crane not reconfigured but dismantled [!]; may be a while until QD arm and OLM table to being installed; carriage system not yet installed to pulley system, cables missing

-LC-40:

--Rebar for new crew access tower spotted

-Blue Origin Campus:

--New hardware spotted such as domes, stand—Stand inside twocat—Reef pathfinder building, vertical assembly building progressed

-LC-36:

--New Glenn fairing transport container spotted; SPMTs; a lot of activity—Tents: hardware and tank sections spotted; possibly a header tank spotted

LabPadre

NSF Nic

Jack

[5]
16.03.2023 Elon Musk: "SpaceX will be ready to launch Starship in a few weeks, then launch timing depends on FAA license approval. Assuming that takes a few weeks, first launch attempt will be near end of third week of April, aka …"

McGregor: Tripod stand raptor test for 139 seconds

B11 cmn dome section moved to in front of mega bay at 13:13

S28: stacking of fwd dome under payload/nc sections completed, lifted off onto a stand

LabPadre
15.03.2023 SPMT moved to Massey's test site

NC31 worked on inside "nosecone jail", "Test structure is used to simulate flight loads on the nosecone"; at Massey's

S25 attached to cryo station at Massey's

S26.1 test tank worked on thourgh hatch at Massey's

OLM work continued

S26, S28 nosecone, S27 in high bay

B7.1 test tank moved at Massey's ahead of the intermittent RC for tonight

S28 stacking continued: fwd dome joined the payload bay and nosecone - first successful double lift for a ship

Another piece of the new turntable was moved out of mid bay and into high bay, furthering construction of second high bay turntable

Over the last 2 nights, both HPU covers were once again removed from B7

S26 moved arount the ring yard, then moved back into high bay

IFT-1: Jeff Foust cited SpaceX's Tom Ochinero: "so close" to launching Starship; waiting for FAA license so we can announce launch date. Jeff Foust

NSF

Jack

LabPadre

[6]
14.03.2023 OLM work continued, still one segment in outer shielding, gaps between segments have been filled; one staircase being added [?][vid 15]

Chopsticks worked on [vid 15]

S24 remaining TPS tiles at prvious lifting points being installed [vid 15]

Ship stand worked on at production site [vid 15]

Pile drilling work for new building near starfactory continued [vid 15]

Four raptor engines spotted today (Raptor 21, 22, 23, 24)

Two Grid fins moved to just outside mega bay; all 4 grid fins now there [B7]

LabPadre
13.03.2023 NSF Starbase Update:

-Deluge system pipes added

-OLM work

-Taller Ship stand worked on at rocket garden, possibly for engine installation

-B9 engine installation has started

-S28 nc stacked on payload bay section; (new nosecone method)

-NC31 installed in test rig at Massey's

Three Raptors delivered to Mega bay (Nr 18, 19, 20)

New intermittent RC for 15–16 March (10pm-1am)

LabPadre
12.03.2023 [none]
11.03.2023 [none]
10.03.2023 Max-Q testing rig (Nosecone Jail) placed around nosecone 31, NC31

Raptor delivery to mega bay continued (Nr. 17)

B7 lifted off OLM by chopsticks onto trasport stand; likely to facilitate OLM work

B7 moved away from OLM

B10 aft section rolled out again to mega bay

McGregor: 100 seconds Raptor test on vertical stand

NSF

Nic

LabPadre

[7]
09.03.2023 S26 inspected / worked on at production site [vid 10]

NC31 test nosecone moved from PPS to Massey's test site [vid 10]

S28 nosecone lifted in high bay, stakced on top of payload bay section [vid 10]; initially, SpaceX attempted to do the first ship double lift with payload bay hanging from the nosecone. For unknown reasons, this was aborted and the payload bay was lifted onto the turntable with a crane.

New intermittent RC for March 9–10 (10pm-2am)

SPMT with counterweights moved to launch site

Raptor engine deliveries to mega bay continued (Nr. 11, 12, 13, 14, 15)

B7 transport stand moved to OLM at 21:00

LabPadre
08.03.2023 Two point lifter tested at production site; "This is a new lifting rig to lift ships like the chopsticks without need for nosecone lift points [vid 10]

S27 lifted off turntable in high bay

S28 nosecone moved into high bay

More raptor engines moved into mega bay for installation on B9 (Nr. 5, 6, 7, 8, 9)

S28 payload bay moved into high bay

McGregor: 78 seconds Raptor test on tripod stand; 112 seconds Raptor test on tripod stand

LabPadre
07.03.2023 LN2 delivered to OLS tank farm

OLM work continued, one gap remaining, likely to facilitate access

B7 worked on near aft section

S24 work near fwd dome hatch at rocket garden

New LR1750 crane at PPS/Rocket garden

Stand structure with ship mounting points (6 ship clamps) attached to LR1750 at rocket garden

Scrapped B8 aft section at Sanchez site

Heavy duty structure (260 us tons, not for lifting) at production site

NC31 test nosecone worked on at PPS

B11 fwd dome section spotted

Bauer BG28H drilling rig work near starfactory

Raptor engine moved to mega bay for installation on B9 (Nr. 1, 2, 3, 4)

SPMT rolled down hwy 4

S26 moved out of high bay

New intermittent RC for 8–9 March 2023 (11pm-2am)

IFT-1: Elon Musk: Elon Musk at a Morgan Stanley conference says again that Starship's first full-stack test launch from Texas will happen "hopefully in the next month or so, we'll have our first attempt." Adds "80 percent chance of reaching orbit this year" (Joey Roulette)

McGregor: 120 seconds test on horizontal and 115 seconds test on vertical stand

NSF

Nic

LabPadre

[8]
06.03.2023 Water deluge pipe delivered to launch site [vid 07]

Base for a new turntable moved into high bay from mid bay

B9 disconnected from bridge cranse in mega bay

New ring with 6 ship clamps spotted at Sanchez site (Cosmical Chief, WAI)

McGregor: 113 seconds Raptor test on vertical stand

NSF Starbase Update:

-New LR1750 could help construction of a potential new mega bay

-Ship payload bay section spotted, not for flight, no TPS pins; built in Starfactory with new tooling

-S26.1, B7.1, B6 test tanks with S25 at Massey's; S25 possible there for GSE testing

-S28 lift points attached

-Foundation work at former shipyard / scrapyard; Bauer BF28H drilling rig - possibly for new mega bay

LabPadre
05.03.2023 [none]
04.03.2023 OLM outer shielding installed; two or so missing, one attempt near the QD failed, succeeded later [vid 07]

Starlink dispenser installed in S30 barrel section (payload bay section)

LabPadre
03.03.2023 OLM work continued; outer shielding panels added; 2 still missing

Black horizontal tanks delivered to launch site, looking like some preassure tanks; moved near the deluge tank area and offloaded

New MSIB / NOTMAR issued for possible Starship testing on 10 March 2023, 8am-8pm (Visit Boca Chica)

McGregor: Short Raptor test on tripod stand

NSF

Nic

LabPadre

[9]
02.03.2023 NC31 with testing cap installed to help simulate flight loads on the test article [vid 03]

Foundation work at production site, Bauer BG28H drilling rig working [vid 03]

S24 flaps closed and chained [vid 03]

OLM outer shielding: more sections installed; only 3-4 full sections remaining [vid 03]

McGregor: storm over McGregor

01.03.2023 S25 and several test tanks at Massey's test site; SPMT left Massey's, tanker truck delivery to it

Lifting point attached to S28 nosecone

McGregor: 107 seconds Raptor test on vertical stand; 134 seconds Raptor test on vertical stand; 111 seconds Raptor test on horizontal stand

NSF

Nic

Jack

[10]

February 2023[]

Date Description Source Link
28,02.2023 S26 lifted off SoLS Pad A by LR11000X [vid 01]

New LR1750 crane raised at production site near rocket garden [vid 01]

S25 shifting at Massey's [vid 01]

S26 lifting squid removed, LR11000X disconnected [vid 01]

NC31 test nosecone worked on at PPS [vid 01]

Payload bay barrel section spotted outside tents [vid 01]

S26 moved to production site [vid 01]

New intermittent RC for 28 February (7-9pm) for S26 move

LR1750 crane raised for the first time at Sanchez Site

McGregor: 179 second Raptor test on tripod stand

NSF Starbase Update:

-B7 HPU unit on north site installed as well; aft and engine section work continued; engine shielding, no Raptor swaps were necessary; HPU covers added

-B4 stand worked on

-OLM shielding work

-S22 scrapping continued with aft dome

-Buoyes: unknwon reason, could aid to monitor marine exclusion zone or for the booster splashdown zone

-Jeff Foust: According to Gary Henry, senior advisor for national security space solutions at SpaceX said, that the 31 engine SF was the "last box to check" befor launch

-B10 aft section rolled into mega bay and back to tent again

-OLM stairs added to easily access "Dance Floor" OLM work platform

Elon Musk: "Raptor start is now reliable on the test stand under most conditions. Now we’re working on dynamically adapting the start sequence based on increasingly difficult propellant inlet pressures & temps. Operating with low pressure, “warm” liquid oxygen is particularly important."

LabPadre
27.02.2023 S26 cryo proof tested

B6 test tank moved from Sanchez site to Massey's test site

Lifting squid attached to S26, 2 SPMTs arrived at launch site for transport

McGregor: Several short Raptor tests on tripod stand between February 23–27

LabPadre
26.02.2023 [none]
25.02.2023 S25 at Massey's test site [vid 01]

OLM outer shieliding installation continued [vid 01]

LR11000X detached from S26

NSF McGregor update

LabPadre
24.02.2023 OLM outer shielding installation continued [vid 01]

B7 south HPU cover test fit, new north HPU cover installed [vid 01]

Counterweights loaded onto an SPMT at production site [vid 01]

Plates placed on hwy 4 [vid 01]

S25 moved to Massey's test site [vid 01]

B10 (persumed) aft section appeared to have moved back into tent 1 after midnight

LR11000X attached to S26

McGregor: Short Raptor test on tripod stand

LabPadre
23.02.2023 S25 lifted off pad B by LR11000X

More outer shielding lifte onto OLM, work on new staircase at an OLM leg

OLM: new cover installed at the lower back end of the booster QD hood

Ventilation hose accidentally ripped

B10 aft section moved into mega bay (with header tank)

Starlink tooling loaded onto truck in starlink building; several Starlink satellites spotted in the building

B7 on HPU replaced [vid 01]

S25 rolled back to production site [vid 01]

Nosecone cage/jail separated into two pieces at Massey's test site, probably due to be used for the upcoming test of the NC31 (nosecone 31) test articel

New (3rd) intermittent RC for 24–25 February (11pm-2am) (for S25 move)

Lifting point removed from what is presumed to be B11 fwd section

McGregor: Short Raptor tests on tripod stand

NSF

Nic

Jack

LabPadre

[11]
22.02.2023 S27 stacked in high bay [vid 23]

Possible crane parts moved from launch site to production site [vid 23]

OLM shielding delivered to production site [vid 23]

Starlink loader moved out of starlink building on SPMT [vid 23]

Test nosecone NC31 lifted onto test rig [vid 23]

Liebherr crane parts accidentally delivered to launch site moved to production site [vid 23]

NSF Starship Analysis:

-Static fire recap; 31 engines of 33 fired; 50% throttle, flight will be at 90%; test produced 7.0 million lbf of thrust (~3600 metric tons), less than half of capability; total booster thrust at lift off is 2.26MN * 33 engines *0.9 = 67.12 MN

-Countdown: not much different than WDR; final OLM vent at 13:43:40, topped at 13:52:00 due to many attempts; from here to T0 1:22:00, for WDR 1:15:00, LOX tank was full in both tests

-TLDR: Fuelling Duration 1:15-1:25; expect ground service equimpent to struggle

21.02,2023 S26 Cryo Proof Test [vid 23]

S27 tank section moved inside high bay [vid 23]

20.02.2023 Booster sump with anti-vortex device delivered

S22 scrapping continued

Scaffolding installed at B7 LOX hatch

S25 worked on near QD

OLM work continued

Buoys spotted at production site

S24 work inside payload bay section

S27 aft section in high bay

NSF starbase update:

-New plumbing at CH4 side: possibly for extension / subcooler addition

-B8 aft section scrapping paused; work on transport stand however

-Starfactory contains payload bay sections

-OLM scorching; no crater in concrete underneath - lot of work; staircase shielding

-Pipe and earth work

-B7 raptor heat shielding removed

-S27 stacking

NSF

Nic

Jack

[12]
19.02.2023 Work on scaffolding around B4 [vid 20]

OLM work continued; preparation for adding more outer shielding; second shielding, now with an access door, added [vid 20]

18.02.2023 OLM work platform with Raptor shields lifted under OLM / B7 [vid 20]

NC31 test nosecone lifted onto test stand at PPS [vid 20]

Second replacement HPU lifted and installed on B7 [vid 20]

OLM outer shielding: first piece installed [vid 20]

17.02.2023 Ship QD arm moved away

Chopsticks raised; QD arm moved in again

Booster QD retraction tests

B7 spin prime test

NSF Cape Update #20:

-Roberts Road:

--OLIT #3 segments identified: west: sections 1–3; 4–6 to the east; section 1 has the chopstick stop; section 4-5 have concrete floors to access QD-arm; section 6 has a beam for pulley of carriage system; section 7 is only 2 levels high, section 8 (columns spotted) will also be 2 levels (instead of 3+1 for OLIT #1 and #2); columns for section #9 ready—Chopsticks #3 under construction, same length as for OLIT #2

--QD #2 more plumbing added—Starfactory looking nearly complete, roof being completed at the very south

-Blue origin: more New Glenn hardware suspectedly spotted; orbital reef building structural work; vertical assembly area yellow bridge crane 30tons installed; foundation work for composite assembly building; LC-36 structure work, possibly for transporter erector, dome and barrel section spotted

-LC-39a:

--Chopsticks installed on OLIT #2

--LR11350 Crane reconfigurations; either for QD-arm lift (scaffolding would need to be removed), or for OLM table

-LC-40:

--Crew access tower being worked on; ground has been cleared to the west of the TE in recent weeks, piles work going on for foundation

McGregor: 301 seconds test on horizontal stand

LabPadre

NSF

Nic

Jack

[13]
16.02.2023 OLM work platform lowered under B7 LabPadre
15.02.2023 B7 second HPU cover removed at 9 am [vid 17]

Foundation work behind high bay near PPS [vid 17]

Deluge equipment stored at PPS [vid 17]

S28 nosecone outside tent [vid 17]

Subcooler (Hippo) stored near satellite dishes [vid 17]

B7 new HPU worked on [vid 17] MSIB issued for testing on February 16–17

McGregor: Falcon 9 landing leg test stand with a leg installed and tested; 194 seconds test on tripod stand - longest known Raptor test on Tripod stand to date

LabPadre
14.02.2023 Raptor maintenance tower/work platform returned to launch site after having been at build site for a week

S27 nosecone and payload bay section stacked on its fwd dome at 20:40 in high bay [vid 17]

B7 missing HPU lifted; originally on B8 [vid 17]

Nosecone test article (NC31) moved to Sanchez site / PPS [vid 17]

McGregor: 53 [49?] second test on Tripod Stand

LabPadre

NSF

Nic

Jack

[14]
13.02.2023 Marvin crane LR11000X detached from S26 after 7am [vid 14]

Replacement HPU for B7 spotted next to OLM, labelled SN15 [vid 14]

B7 raptor shrouds removed [vid 14]

OLM stairs shielding added [vid 14] S27 nc+payload section; fwd dome section moved into high bay for stacking [vid 14]

Oil rigs Phobos and Deimos have been sold as announced by Gwynne Shotwell: "Gwynne Shotwell told reporters last week that SpaceX sold the rigs; "they were not the right platform." Still interested in sea-based launch platforms, but the company wants to start flying Starship first and understand it before proceeding." Jeff Foust], this comes after speculation due to both rigs listed in the departure list of Port of Pascagoula (Deimos on 20 Feb, Phobos on 12 March)

NSF Starbase Update:

-Installation of deluge GSE equipment; tanks possibly for helium or nitrogen to pressurize and push water to OLM; water pipeline with manyfold started

-S24 crane lifting points removed, metal plates added over it as cover

-B7 static fire recap; pad seems to be in gould condition; tank farm berm has some scortching as well

-Trench worked on west and south of OLP, likely related to deluge system

McGregor: Short Raptor test on Tripod Stand

LabPadre
12.02.2023 S26 connected to load spreader; QD adapter removed; lifted onto SoLS pad A by LR11000X [vid 14]

Scrapped ship section spotted [vid 14]

Barrel sections in and outside starfactory [vid 14]

Booster thrust puck outside tents [vid 14]

S27 nc+payload section near mid bay [vid 14]

Raptor engines in tent 1 [vid 14]

S22 nosecone and test nosecone near wind break; test nosecone (NC31) attached to a crane [vid 14]

Pipes lifted at OLS tank farm CH4 side; work near CH4 subcoolers [vid 14]

Work near SoLS pad B [vid 14]

Heavy work on and near OLM continued [vid 14] Ship QD attached to S26 on pad A

McGregor: NSF update: Test article worked on

LabPadre
11.02.2023 Musk on 31 engins SF and orbital launch with B7: "This test is at ~50% throttle. Launch attempt next month will be at ~90%."

B7 second HPU cover removed [vid 14]

S26 rolled out to launch site (around midnight) [vid 14]

LabPadre
10.02.2023 OLM work platform reinstalled at OLM [vid 14]

Inspection and work near and on OLM [vid 14]

Trench work south of OLP between water / deluge tank stands and OLM [vid 14]

Part labeled with "Flame Diverter" spotted at Starbase RGV B9 hooked to new load spreader using both bridge cranes in mega bay at 21:28

McGregor: 89 seconds test fire on Tripod stand, throttling around 1 minute mark; 158 seconds fire on vertical stand; 4 seconds fire on horizontal stand

LabPadre
09.02.2023 OLS deluge system pipes (parts for OLM) headed towards Starbase RGV

B7 31 engine static fire NSF vid]

McGregor: Two Short Raptor tests on tripod stand, one on horizontal test stand

LabPadre
08.02.2023 Shotwell: 33 engine static fire as a big mile stone for tomorrow, Starship's first flight expected "in the next month or so", "Mars hopefully this decade, maybe early next decade" Micheael Sheetz, B7]

Overpressure notice issued to residents for tomorrow B7 static fire attempt

Raptor work platform lowered

LabPadre
07.02.2023 Road closure (08:01 - 11:07)

LN2 tank delivered from port to Starbase during a road closure

McGregor: Raptors fire against concrete at horizontal stand; 90 seconds fire on vertical stand

LabPadre
06.02.2023 S28 nosecone outside tents

Raptor work platform behind tent 3

S27 worked on in mid bay

NC31 (test nosecone, without tip) in front of tent 3

Installation of water tank on bases west of OLP continued

OLM scaffolding being installed

SoLS pad B covering removed

Musk: "attempt to launch in March. Success is far from certain, but excitement is guaranteed." [Starship 7/24] MSIB issued for testing February 7, 09, 10, 13, 14, 17 (B7 static fire)

NSF Starbase update:

-Rocket garden: S24 brought there for final upgrades and protection

-SpaceX: Cargo variant 150 tonnes to earth orbit reusable, 250 tonnes expendable

-B7 one HPU still missing; 3 raptors replaced last week

-OLM wiring and cabling as well as painting continued

-Chopsticks hydraulics worked on

-West of OLP: new foundations built, either for expansion of tank farm, or area for new deluge GSE

-OLM work platform called "Dance floor" by SpaceX

-Concrete work near SoLS pad B; likely to upgrade the berm

-S22 scrapping

LabPadre

NSF

Nic

Jack

[15]
05.02.2023 4 GSE tanks delivered to the launch site; according to Zack Golden: "It's important to note that these are most likely not for storing water, but to function as gigantic water hammer arrestors. This system still needs a very large water supply that currently does not exist."

4 new GSE tanks lifted into place by Grover crane next to the OLIT on the previously built concrete foundations, this in connex with the new water deluge system (see here) [see vid 06]

MEGCs (multiple element gas containers) lifted [vid 06]

Raptor work platform (not to be confused with OLM work platform) moved to the production site [vid 06]

LabPadre
04.02.2023 Musk: "If remaining tests go well, we will attempt a Starship launch next month" [Starship 7/24]

OLS deluge system: Piping and high pressure tanks deliverd to launch site; first piping part installed into place near the concrete foundations

Tipless testing nosecone removed from low bay

S30 nosecone moved out of tent 3 with tiles in place, moved into low bay

LabPadre
03.02.2023 Marmac 2680 barge arrived after nearly 2 weeks journey from Port Canaveral at Brownsville with GSE equipment for OLS deluge system

Marmac 2680 barge with water deluge system parts (tanks, pipes, a manifold; and a start of a booster transport stand) for OLS offloaded RGV, NSF] - [see last NSF Cape update video]

S26 in high bay, B9 in mega bay

S22 nosecone scrapping near windbreak continued

Booster thrust puck delivered

Deliveries to production site

Earth work west of SoLS pads

S25 worked on

Foundation and earth work on launch site (south, between OLS and SoLS) continued, likely for deluge system

Purging/flushing of SoLS tank farm at 18:14

OLS deluge system: GSE equipment and piping started to being delivered and unloaded at OLS

B7 one HPU unit still missing

McGregor: 49 seconds test on tripod stand, after being inactive for 16 days for repairs due to damage and storms; several falcon related tests

LabPadre

NSF

Nic

Jack

[16]
02.02.2023 Concrete work west of Pad B on SoLS

OLM / B7 worked on

S27 payload-nc section; B10 methane section; S28 nosecone and mid LOX sections spotted

S22 nosecone attached to crane near tent 3 / windbreak

McGregor: Short test on vertical stand

NSF

Nic

Jack

[17]
01.02.2023 S27 nosecone moved out of high bay [vid 02]

Possible OLS deluge related pipes assembled at Sanchez RGV Raptor engine moved to launch site for replacement [vid 02]

OLM work platform lowered under B7 and removed, making place for raptor stand [vid 02]

Concrete work west of OLP [vid 02]

Rboost engine SN42 removed from B7 [vid 02]

S25 inspected [vid 02]

Grinding in B7's engine section [vid 02]

LabPadre

January 2023[]

Date Description Source Link
31.01.2023 S27 nosecone and payload bay welding completed, lifted off turntable in high bay

Musk: "Expendable upper stage may or may not fly, but it is an option"

LabPadre
30.01.2023 S24 tiling over the lifting point attachments started

Chopsticks and OLM worked on ahead of potential 33-engine static fire of B7, OLM legs being painted some more

New foundations west of OLP worked on, earth work [add: water deluge?] Cape: NSF Chopsticks summary: From 6–24 January

-Carriage rolled to LC-39a

-Cranes repositioned at LC-39a for chopsticks installation

-Carriage placed on support gantry

-Chopsticks (of shorter length than at Starbase) rolled out to pad

-Chopsticks scates installed on OLIT

-Chopstick arms installed on carriage

-Chopsticks installed on OLIT by LR11350

McGregor: Short test on horizontal stand

LabPadre

NSF

Jack

[18]
29.01.2023 Rocket garden: B4, SN15, S24, S20 [vid 30]

B8 and S22 scraps near starfactory [vid 30]

LR11000X not yet raised [vid 30]

S24 covers put in place over the lifting point attachments McGregors (NSF, not dated): Several short raptor tests during past week

LabPadre
28.01.2023 B7 replacement engine SN105 lifted into place

B7 second engine removed, second replacement engine lifted into place, at 9:20 OLM work platform moved up under B7 [add: replacement done with raptor stand, not work platform] [vid 30]

Removed engines moved to production site [vid 30]

S24 all six lifting points removed in preparation for orbital flight [vid 30]

Booster aft section with a header tank moved into tent 1 [vid 30]

LabPadre
27.01.2023 William Gerstenmaier: Booster 33-engine static fire could happen "maybe next week" Joey Roulette, B7]

Concrete work near OLM [vid 30] S27 nosecone stacked onto its payload bay section in high bay at 09:06

OLM work platform lowered under B7 in preparation of swapping two Raptors, Raptor cradle lifted onto the platform to hold the engine during the installation and removal[vid 30]

S28 nosecone moved to ring yard / high bay [vid 30]

Unknown raptor engine delivered to launch site [vid 30]

B7 raptor engine removed at 22:43

LabPadre
26.01.2023 S24 moved to rocket garden (not for decommissioning)

Work on starfactory wall Raptor engine delivered from production site to launch site, unknown if for B7 or S25

LabPadre

NSF

Jack

Nic

[19]
25.01.2023 Ship QD retracted from S24 [B7] ahead of possible destack, QD arm retract [vid 26]

B8 LOX tank scrapping begun, thurst section moved out of mega bay LR11000X crane lowered

Starship 7/24 destacked [vid 26]

Ship QD arm extended again [vid 26]

B8 aft section with header tank spotted [vid 26]

Chopsticks opened and released S24 [vid 26]

NSF Cape Update #19:

-LC-40: Excavator spotted; unknown purpose yet [could be for new OLIT #3 or a new crew access arm]

-BO: lot of work on new buildings (orbital reef pathfinder building, vertical assembly building); at LC-36, a 7m diameter structure was spotted, possibly for NewGlenn

-Robert's Road:

--OLIT #3 segments: 6 completed, 7th is a shorter one (lower part of the top section), columns for even shorter top section spotted—Chopsticks: left for LC-39a; QD arm pieces still in work, end part missing yet, but much pipes installed; possibly parts for chopsticks #3 and carriage system already there—Starfactory: highest section progressed, roof of rest nearly complete

-LC-39a:

--Chopsticks and Carriage rolled out; carriage put on red frames for assembling the different parts of the chopsticks—Tanks missing, moved to turning basin next to VAB; 4 white horizontal water tanks, high pressure tank clusteres; deluge equipment (manifolds and pipes) spotted near it, resmebling the one installed at LC-39 OLM (!!); 3 big tanks labelled with LN2 possibly for Massey's. Much of this hardware has been removed from the old foundation area where SpaceX was working on a Starship tower previously right next to the big falcon ramp. Barge turned up and loaded the equipment, heading to Brownsville

LabPadre
24.01.2023 B7 and S24 depressurized and repressurized as seen from dents [vid 26]

OLM leg pipe covers being painted [vid 26]

OLM raptor work platform moved up under Starship 7/24 S24 transport stand moved to OLM

RC (intermittent) added for Jan 26, 8-10am

SpaceX: "After completing Starship’s first full flight-like wet dress rehearsal, Ship 24 will be destacked from Booster 7 in preparation for a static fire of the Booster’s 33 Raptor engines" [B7, S24]

Cape: Chopsticks for OLIT at LC-39A installed by LR11350 [SpaceflightNow]

LabPadre
23.01.2023 Starship 7/24 full Wet Dress Rehearsal

NSF update on road to orbit for Starship:

-4 more remaining milestones: Static fire of 33 engines in destacked configuration; additional single-species prop system testing; full WDR; FAA license

-S24 stiffener rings on Rvac engines have been removed recently, so another static fire of ship is doubtful

-TPS tiles finishing and crane attachment point removal pending

-Restack and some more testing possibly

-FAA launch license: Unknown state

-Launch might need several attempts

LabPadre

NSF

Jack

[20]
22.01.2023 S22 nosecone lifted in high bay during scrapping [vid 26]

Mini helicopter delivered to Starbase LabPadre Cape: LC-39A: Chopsticks now free standing on support structure, both cranes detached; Barge with Starship GSE left KSC turn basin [Spaceflight Now] [add: with equipment for OLS deluge system at Starbase]

McGregor update of past week (no dates provided): 1000 tests passed since NSF coverage 9 month ago started; Preburner test on tripod stand; relight test on tripod stand; Electric TVC test on tripod stand, 94 seconds fire; several explosions, some RUDs, some to test new blast shield; sea level engine test on horizontal stand for 167 seconds; Rvac tested on horizontal stand for 113 seconds; preburner test on vertical stand, sea level engine test on vertical stand for 117 seconds; RUD at vertical stand; possible HLS thrusters spotted and tested, fired for about 34 seconds

LabPadre

NSF

21.01.2023 Nosecones worked on near and in tent 3; S28 ready, likely S29 TPS tiles being added [vid 26]

B8 fwd dome moved out of mega bay indicating full scrapping of CH4 tank section [vid 26]

S27 in mid bay [vid 26] S22 scrapping began, aft section cut off [vid 26]

OLM worked on at several areas [vid 26]

Rebar and foundation work near SoLS pad B [vid 26]

B7 HPU units have been removes [vid 26]

S25 flaps opened [vid 26]

Testing TFR posted for January 23 with a notable 4000 ft addition to regular 10000 ft TFR

OLM platform lowered under Starship 7/24

LabPadre
20.01.2023 B7 one of the hydraulic pressure unit (HPU) covers was removed

B8 methane tank cut off in mega bay

Starlink payload box moved back to processing building Kevin Randolph/LabPadre]t

S25 detached from LR11000X and squid

New MSIB/NOTMAR issued for Starship 7/24 testing for 23 and 25 January 8:00 - 20:00 (extended range)

S27 tank moved from high bay to mid bay (partially completed)

Cape: LC-39A: 2nd chopstick arm lifted into place and flipped upright, installed, completing the general assembly of the chopsticks

McGregor: Raptor RUD

LabPadre
19.01.2023 S27 nosecone moved

B8 confirmed inside mega bay for scrapping B10 CH4 tank rolled out of mid bay overnight

B7 hydraulic power unit (HPU ) worked on [7/24]

OLM worked on

Starlink satellites spotted in Starlink building

B8 moved out of and back into mega bay; HPUs missing

Raptor engines with electic TVC inside tent 1, RSN202 identified

OLM work platform lifted under Starship 7/24

Cape: KSC turning basin: large barge loaded with various Starship GSE pars, such as horizontal liquid and gas tanks, water piping, incomplete booster transport stand; LC-39A: Chopstick carriage skates installed on OLIT; One of the chopstick arms lifted and flipped upright for installation on carriage [Spaceflight Now]

LabPadre

NSF

Jack

Nic

[21]
18.01.2023 FIREX system tested on OLM [vid 19]

S22? transport stand move out of high bay [vid 19]

S22, S26 and S27 in high bay [vid 19]

Booster methane sump and transfer tube spotted [vid 19]

Large black pipe parts delivered to production site [vid 19] [add: water deluge?]

S28? nosecone with flaps and TPS tiles attached to crane in front of tent 3 [vid 19] S27 stacking in high bay, now 3 sections high

Starship 7/24 propellant load test, CH4 tank on booster loaded more than last time

B8 rolled out of rocket garden for scrapping [vid 19]

S28? mid-LOX section worked on; aft flap root measured [vid 19]

McGregor: 30 seconds fire on vertical stand

LabPadre
17.01.2023 OLM work platform lowered from under Starship 7/24

LR11000X connected to S25 S25 lifted onto SoLS pad B by LR11000X

B8 SPMTs moved under it

S22 SPMTs moved under it, HPU cover removed Kevin Randolph WAI; aft flaps have been removed

S22 left rocket garden, moved in front of high bay

Mega bay extension work on the inside continued

Nosecone in front of wind break briefly lifted

OLS: Pad cleaned by sweeper

Tanker deliveries to OLS tank farm

Common dome and booster aft dome at production site

MSIB issued for testing on 18–20 January, 8:00-20:00 with extended range on 18 January

S27 stack (midlox and cmn sections) moved from mid bay to high bay for further stacking; thrust section moved also into high bay, lifted onto turntable

LabPadre

NSF

Nic

[22]
16.01.2023 OLM and booster QD worked on [vid 17]

Launch site front gate fell over [vid 17]

Squid for LR11000X delivered to launch site (for S25 lifting)

LabPadre
15.01.2023 Raptor engines with electric TVC spotted in tent 1 [vid 17]

Maria from Starship Boca Chica confirmed that an important testing event will occur on Wednesday, January 18, with villagers being asked to leave Boca Chica Village by 7:30am. Possibly a Starship 7/24 WDR or even Static Fire.

LabPadre
14.01.2023 S25 transported to the launch site

OLM worked on S29 or S30 PEZ dispenser installed outside tent 3

OLM work platform lifted under Starship 7/24

Starlink dispenser installed in a payload bay for an unknown ship [vid 17]

Elon Musk: "About five full stacks" this year to be built

NSF McGregor Flyover:

-Concrete blast target spotted near McGregor test site

-Tripod stand: blast shield for exhaust redirection and water deluge shown; relight tests

-Rvac and sea level Raptor engine on horizontal test tands; northeast stand indicated by "train vent", Rvac; for north stand, there's a massive concrete foundation with a blast target next to it to be installed - possibly to test raptor plume on flat surfaces for a good solution at the launch sites

LabPadre

NSF

[23]
13.01.2023 OLM FIREX test on 6.30am

Starship 7/24 partial propellant load test [vid 14]

Intermittent road closure issued for 14 January, 8-10am

NSF Starbase Flyover: (Jan 10th)

-Production Site:

--Booster aft dome, fwd dome; 2 fwd ship domes; S27 nosecone; ship mid-LOX sections with aero covers and TPS tiles (S28?); B10 CH4 tank in mid bay; booster thrust puck; nosecone and payload section at wind break; booster header tank and transfer tube part; mega bay workstations for corners to be installed

-Launch Site:

--Pad has been levelled at the south end of OLS [add: possibly for OLM water deluge?]

-Massey's:

--Foundation work

LabPadre
12.01.2023 OLM FIREX test at 06:58 am

Elon Musk on Starship 7/24 timeline: "That's a good guess", on question by Chris Bergin (NSF): "Does this sound about right, Elon? Cryotest today, then WDR next week. Destack for 33 engine Static Fire. Final TPS work on Ship 24. Re-stack. Launch License. Possible end of Feb/Early March if all goes well (per your previous timeline)?"

SpaceX on Starship 7/24 timeline: "Team are stepping into a series of tests prior to Starship's first flight test in the weeks ahead, including full stack wet dress rehearsals and hold down firing of Booster 7's 33 Raptor engines"

Pipe sections for a possible underground water deluge system for Starship Launch pad at Starbase arrived at Massey's test site last week, possibly to upgrade the OLM after the first or second orbital launch; 4 out of 6 corner pieces present, 2 Tee's laying in front of those. Zack Golden

GSE testing ahead of further Starship 7/24 testing

Cape: Chopsticks rolled out from Robert's Road to LC-39A OLIT [Spaceflight Now]

LabPadre
11.01.2023 S22 one aft flap removed at rocket garden

Starlink Box moved out of Payload processing facility

Cape: LC-39A: Top dome of big tank (purpose still unconfirmed) lifted into place [Spaceflight Now]; Roberts Road: 6 OLIT #3 segments look complete Greg Scott]

LabPadre
10.01.2023 B9 rolled back to mega bay

S29 nosecone tip removed, indicating it will be used with the nosecone testing rig at Massey's Kevin Randolph, WAI

S22 TPS tiles and insulation being removed Starship Gazer

LabPadre
09.01.2023 B7 lifted onto OLM;

Chopsticks lowered from B7; ship lifting pins on chopsticks extended [very good visuals!!] S24 moved to OLP; chopsticks fully lowered again; moved between it, chopsticks raised and attached

Booster QD attached to B7

Starship 7/24 stacked

Ship QD connected to S24

Intermittent road closure issued for January 10 2-5pm

McGregor: 39 seconds fire on tripod stand; Rapid relight test on tripod stand 39+7 seconds

LabPadre

NSF

Nic

Jack

[24]
08.01.2023 OLM equipment removed

SQD arm swung out, chopsticks lifted B7 rolled out to launch site, moved between chopsticks

Chopsticks lowered to the bottom

Chopsticks lifted again, attached to B7; lifting preparations, QD plate removed

Elon Musk: "Massey’s gun range is being turned into a rocket test facility. Perfect match."

LabPadre

NSF

Nic

Jack

[25]
07.01.2023 Test rig removed from OLM and lowered to the ground

Two SPMTs moved into wide bay ahead of possible B7 roll out

S24 disconnected from LR11000X [vid 08]

Elon Musk orbital announcement: "We have a real shot at late February. March launch attempt appears highly likely."

LabPadre

NSF

Jack

Nic

[26]
06.01.2023 OLM testing continued [vid 07]

Booster QD opened; clamp testing ficture lifted out of the OLM after multiple load test of all 20 clamps [add: not yet complete]

New concrete form at base of OLIT inspected [vid 07]

Booster thrust puck spotted at production site [vid 07]

S26 and S25 in high bay [vid 07]

B7 preparations in mega bay for roll out [vid 07]

Barrel sections spotted in starfactory [vid 07]

Welder worked on a transport stand [vid 07]

Single ring with hatch cutout moved [vid 07]

S27 nosecone and an unknown single with a lot of tringers on it an pipes sticking out of it next to it [vid 07]

PA: Ship QD blowdown [vid 07]

OLM hold down clamp testing continued though the night [vid 07] S24 disconnected from LR11000X

Cape: Chopsticks carriage rolled out to launch site, later flipped at LC-39A [Spaceflight Now]

LabPadre
05.01.2023 S24 attached to LR11000X

B10 methane section left mega bay at 06:44, entered mid bay at 07:07

S24 detached from Ship QD, lifted off Pad B by LR11000X (13:10-13:18)

Chopsticks rose and lowered twice between 3.15 and 3.40 pm; tested

OLM testing continued

Intermittent closure posted for January 8, 3-5 pm

Deep caisson drilling rig being assembled at Masseys, possibly for a Raptor test stand RGV

SpaceX raised another $750 Mio San Antonio Express News

LabPadre

NSF

Nic

[27]
04.01.2023 S25 payload door cover lifted into place to weld the door closed

OLM clamp load tester (Versabor) installed onto 2 clamps and disconnected [vid 05]

Work on OLIT near and on the Ship QD arm [vid 05]

OLS tank farm berm work continue [vid 05]

OLS tank farm worked on [vid 05]

S25 payload door welded shut [vid 05]

MSIB issued for January 10, 12, 13 for testing

B7 moved inside mega bay [vid 05]

LR11000X moved and lifted squid next to S24 [vid 05]

First load test performed on OLM clamps by new structure at 19:12

Cape: LC-39A: Chopsticks assembly jib constructed for OLIT chopsticks installation

LabPadre
03.01.2023 S25 payload door cover moved to high bay

2 SPMTs with no counterweights moved to ring yard and parked in front wide bay

S28 common dome fliped WAI, Randolph

S26, fully stacked, moved off the turntable inside high bay

New load test mechanism lifted inside of OLM at 23:04

LabPadre
02.01.2023 SPMTs with tons of counterweights moved under OLM

Mass simulator for OLM assembled near OLM Starship Gazer; Hydraulics to lift counterweights, possibly suspending over two clamps at a time Evert-Jan N

LabPadre
01.01.2023

2022[]

December 2022[]

Date Description Source Link
31.12.2022
30.12.2022 Two SPMTs moved to launch site at 2:19am

S26.1 concluded its testing at Masseys, possibly returning to PPS soon RGV

LabPadre
29.12.2022 B9 Cryo Proof Tested

Parts for the stabilizer clamps of more booster transport stands delivered RGV, Jake, Zack Golden]

McGregor: 100 seconds Raptor test with elctric thrust vector control (TVC) on tripod stand; 109 seconds Raptor test on vertical test stand; 110 seconds Raptor test on horizontal test stand; New concrete structure being built in front of the horizontal raptor stand, appearing to be directly in the path of the center bay exhaust

LabPadre

NSF

28.12.2022
27.12.2022 B10 methane transfer tube (downcomer) moved to wide bay and installed into B10 LOX tank LabPadre
26.12.2022
25.12.2022
24.12.2022
23.12.2022
22.12.2022 B7: 20 RBoost engine covers moved away from the shielding storage between Dec 15th and 22nd. They possibly went into wide bay for installation on B7 [The Ring Watchers, 27 Dec]

New hardware assemblede, likely a jig for lifting ships, so tile removal wouldn't be necessary anymore Starship Gazer, Thomaseo1

The Ring Watchers
21.12.2022 B9 First Cryo Proof Test

Many Raptor 2 engines spotted in tent one with the new electric TVC hardware, possibly for B9 Starship Gazer

McGregor: RUD of Raptor Vacuum engine on horizontal stand; 40 seconds Raptor test on tripod stand

LabPadre

NSF

Nic

[28]
20.12.2022 B9 worked on at cryo station [vid 21]

OLS tank farm berm hight extension work continued, more concrete poured, now reaching western end [vid 21]

CH4 deliveries to OLS tank farm [vid 21]

OLM work continued [vid 21]

S25 payload door worked on [vid 21]

B10 LOX tank lifted and stacked onto a quad section, now 20/24 rings tall

McGregor: 40 seconds Raptor test on tripod stand

LabPadre

NSF

19.12.2022 S25 and S26 worked on in high bay; S25 work through payload bay access hole

2 SPMTs that transported B9 moved back to production site

Gantry crane outside tent 3 moved by another crane

LR11000X moved across launch site towards SoLS

New subcooler delivered to production site (for OLS); "Subcoolers use liquid nitrogen to chill Starship's methane and oxygen propellants before prop loading and flight"

McGregor: 47 seconds Raptor test on Vertical test stand (boost back duration?)

NSF Cape update #18:

-Roberts Road:

--Starfactory work continued, roof of large lower part nearly completed, beams for the taller area halfway completed—No progress on mega bay—Chopsticks no major work; new hardware spotted near the QD arm, unknown purpose [add: possibly new chopsticks?]

--5 OLIT #3 segments complete, outfitting underway, 6th under construction

-Cidco Road:

--TPS tile worked on hear likely—Two sets of 4 black metal stands spotted, used for the build up of tower sections; insulated pipes spotted as well

-LC-39A:

--Only few changes

LabPadre

NSF

Nic

Nomadd

[29]
18.12.2022
17.12.2022 Booster QD and Ship QD arm testing continued; ship QD retracted as well [vid 19]

McGregor: Rapid relight test of Raptor engine on Tripod stand, 40 + 40 seconds

NSF
16.12.2022 S26 final stacking: nosecone stacked on tank section [vid 19]

Booster QD and Ship QD arm retract sequence, looks like to be a test of how these systems will behave during a launch [vid 19]

Concrete forms on OLS tank farm hight extension removed [vid 19]

S24 closeup shows several areas of missing or damaged tiles [vid 19]

B9 connected to cryo station [vid 19]

McGregor: Rapid relight test of a Raptor engine on tripod stand, 40 + 16 seconds

LabPadre

NSF

15.12.2022 S24 flaps tested again

B9 disconnected from wide bay crane ahead of roll out S24 single-engine static fire

Ship QD arm moved after S24 static fire test

B9 rolled out to launch site cryo station, no Raptors installed yet, starlink dish mounted on a chine

OLS: Booster QD on OLM and Ship QD arm retracted at full speed in a launch configuration test at 18:36

McGregor: 40 seconds Raptor test on tripod stand

LabPadre

NSF

Nic

Nomadd

[30]

[31]

14.12.2022 S24 flaps tested ahead

Overpressure notice issued to residents for potential S24 static fire SPMTs moved to wide bay for potential B9 roll out

Cape: Possibly the cable chain for the OLIT at LC-39a installed [Spaceflight Now]

Cape: 6th tower segmant for OLIT #3 under construction at Robert's Road, the first 5 segments look more or less complete Greg Scott

McGregor: 40 seconds Raptor test on tripod stand; 136 seconds test on horizontal stand

LabPadre

NSF

Nic

[32]
13.12.2022 Gravel delivered at production site [vid 14]

S28 nosecone had its flaps installed, outside tent 3 [vid 14]

B9 worked on in mega bay [vid 14]

Mega bay extension work continued [vid 14]

Starfactory work continued [vid 14]

Booster transport stand and a ship mid LOX section (tiled, unknown Ship] behind it [vid 14]

Test article spotted in front of mid bay [ship aft skirt test article?] [vid 14]

PPS tent work continued [vid 14]

MSIB issued for testing on Dec 15th

McGregor: two 47 seconds Raptor tests on vertical stand, possibly for booster boostback burn; 39 seconds fire on tripod stand

LabPadre

NSF

12.12.2022 S24 disconnected from LR11000X at 5:45 am

Delivery at launch site

OLM work continued

OLS tank farm berm height extension work continued, forms on one side removed

SoLS pad A with hydraulic rams

Prefab underground conduit stored at launch site (246SP)

S24, damaged tiles next to payload hatch

S26.1 test tank with structural test stand (can crusher) and top (cap) moved to Massey's Gun Range [vid 14] B10 quad section moved into wide bay for stacking

B10 LOX tank lifted and stacked onto a quad section, now 16/24 rings all

LabPadre

NSF

Nic

Nomadd

[33]
11.12.2022 NASA deputy admin Pam Melroy: "They're [SpaceX] beyond the we're-probably-going-to-blow-up-the-pad phase", she also added she was aware of "how hard it is to develop a new location to launch rockets from. Safety is everything. ...And I think they're just experiencing some of those things." Davenport LabPadre
10.12.2022 S24 scaffolding now completely removed around it and SoLS pad B [vid 12, with a complete timelapse] LabPadre
09.12.2022 SPMT under ship stransport stand at rocket garden

Mega bay backside extension work continued

Barrel sections spotted inside starfactory

Test Tank 13 (TT13) [add=S26.1] moved to Sanchez site (PPS) at 01:07 Starlink box moved out of Payload Processing Facility

McGregor: Very short raptor test on tripod stand

LabPadre

NSF

Nic

[34]
08.12.2022 OLM heavy work continued, work on shielding and concrete below it [vid 09]

OLS tank farm berm hight extension work continued, concrete being poured below it, rebar work [vid 09]

S24 scaffolding continued to be dismanteled [vid 09]

Ship QD on QD arm worked on [vid 09]

Yusaku Maezawa announced crew of DearMoon mission. The selection includes Tim Dodd, the Everyday Astronaut Maezawa

Ship Aft Test article moved to PPS at 21:00

McGregor: Tripod test stand tests resumed after upgrades and testing; 47 seconds Raptor burn #3 on horizontal stand

LabPadre

NSF

07.12.2022 S24 work continued, scaffolding continued to be removed; work around the crane attachment points

OLM work continued at several areas, such as the complex pipe manyfold area; replacement cryo pipe lifted onto OLM

McGregor: 47 second Raptor firing on vertical stand, possibly a booster boostback burn duration test; 29 seconds Raptor test on tripod stand

NSF

Nic

Nomadd

[35]
06.12.2022 S24 work continued, inside CH4 tank, scaffolding continued to being removed [vid 07]

OLM work continued, concrete work under it; more pipe covers added at the legs [vid 07]

OLIT: three levels of shielding plates have been completed recently [vid 07]

OLS berm hight extension work continued [vid 07]

Top of mega bay still worked on, a lot of scaffolding still there [vid 07]

Mega bay extension construction continued [vid 07]

Work on new tent at PPS continued, especially on the side walls [vid 07]

Ship aft skirt test article on can crusher/structural test stand tested, with sheriff blocking the access to the area [vid 07]

S28 and S30 nosecones in tent 3, S29 nosecone attached to crane in windbreak [vid 07]

B6.1 test article, made of a booster fwd dome section on top of a ship aft dome section [reverse?], completed stacking in mid bay [vid 07]

Old payload bay pathfinder seems to be getting modified [vid 07]

B7, B9 and B10 in mega bay [vid 07]

McGregor: 47 second burn #2 on vertical stand; there were 11 total 47 secs tests this week

LabPadre

NSF

05.12.2022 OLM more shielding added, work also on inside; unknown section lifted to it

QD arm worked on

OLS berm work continued, additional height being added (concrete forms prepared)

S24 scaffolding removal started

S25 worked on in high bay via access hole, work platform not yet removed

S28 and S29 nosecones in tent 3

Trash cleanup along dunes

McGregor: 98 seconds Raptor test on horizontal stand

LabPadre

NSF

Nic

[36]
04.12.2022
03.12.2022 Chopsticks lowered and opened [vid 05]

B7 rolled back to the production site [vid 05]

B7 moved into mega bay [vid 05]

Ship aft skirt test article worked on at PPS, structural test stand top has been added [vid 05] S25 PEZ dispenser welded shut RGV

No news ad Cidco Road site, MKK2 nosecone still exists WAI

LabPadre
02.12.2022 B7 second engine removed and replacement engine lifted to B7; removed engines left launch site

B7 lifted off OLM by Chopsticks

B7 rolled to the landing pad area [??]

Load spreader moved to production site

Mc Gregor: Raptor RUD on vertical stand; cryo proof test of new tanks on tripod stand [unknown date]; small engine tested, potentially for Starship HLS; small engine test stand shown (photo gary blair); firing of a raptor engine on horizontal stand for 84 seconds

LabPadre

NSF

Nic

Das

[37]
01.12.2022 2 raptor engines moved to launch site, raptor fixture delivered as well [vid 02]

S24 work continued [vid 02]

OLS concrete berm work continued [vid 02]

OLM work continued [vid 02]

OLIT and cladding work continued [vid 02]

Delivery of a large unknown object (curved) [vid 02]

S28 nosecone, tiled but no flaps installed yet, outside tent 3 [vid 02]

S29 nosecone, no tiles and no attachment points, outside tent 3 [vid 02]

S25 worked on in high bay [vid 02]

B9 worked on in mega bay [vid 02]

Ship aft skirt test article lifted onto structural test stand (can crusher) [vid 02]

B7 transport stand moved to launch site B7 raptor work platform lowered; later lifted again; an engine was removed, replacement engine lifted into B7 [vid 02]

Mc Gregor: Raptor test on vertical stand, 60 seconds

LabPadre

NSF

November 2022[]

Date Description Source Link
30.11.2022 OLM raptor work platform lifted under B7

OLM worked on, inspections of charred areas

Work on roof of GSE bunker at OLS

OLIT cladding (two levels, and one on third)

OLS concrete berm worked on

S24 work continued

S25, and S26 nosecone in high bay; S26 without tiles and flaps, but with antenna tiles

B9 worked on in mega bay

S28 nosecone in wind break, S27 nosecone outside

Ship QD arm retracted, chopsticks lowered to base of OLIT

Mc Gregor: Raptor firing on horizontal stand, 84 seconds

LabPadre

NSF

Nic

[38]
29.11.2022 B7 static fire test (11 engines, 13 seconds) LabPadre

NSF

[39]
28.11.2022 OLM work platform lowered from B7

OLM FIREX system tested extensively B7 cryo test (possibly scrubbed/aborted static fire)

S25 disconnected from bridge crane in high bay

Overpressure notice issued to residents fot B7 static fire attempt

Mc Gregor: Very short raptor firing on horizontal stand

LabPadre

NSF

Nic

Nomadd

[40]
27.11.2022 S27 nosecone section (8 rings + nc) moved from mid bay into high bay for stacking [vid 28]

Ship aft test tank [sic!] moved from wide bay to mid bay [likely the mean S26.1, or TT13; the ship aft test tank is small, not 8 rings tall]

Overpressure notice issued to residents fot B7 static fire attempt

LabPadre
26.11.2022 S24 scaffolding now reaching to the mittle of the ship [vid 28]

Tent that was used in repairs of OLM removed [see yesterday]

LabPadre
25.11.2022 S24, basket lowered; typically containing equipment or replacement parts

Temporary tent between OLIT and OLM dismantled again

Tent nearest to the water look like it has some air handling equipment to potentially help the interior be a cleanroom type environment [vid 28]

OLM more shielding added to cover the piping; more shielding on OLIT as well [vid 28]

S26.1 test tank? and S27 common and mid-lox section in mid bay [vid 28]

B10 section in mega bay, B8 with view from below in rocket garden - good view of engine section plumbing! [vid 28]

SN15 with removed flap skin shown [vid 28]

Ship skirt with stringers shown [vid 28]

Cape: 5th tower segment for OLIT #3 construction underway Greg Scott]

NSF

Nic

[41]
24.11.2022 S24 scaffolding rose around the ship, batches of TPS tiles removed from aft section [old info]

OLM worked on [vid 25]

LabPadre
23.11.2022 S24 worked on [vid 25]

Nosecone moved into the wind break (the one with tiles on it) [vid 25]

MSIB issued for testing on 28–29 November S25 lifted off stand in high bay for RVac installation [?]

LabPadre
22.11.2022 Nosecone moved outside [vid 25]

Second nosecone moved outside [vid 25]

NSF Cape Update #17:

-LC-39A—Drainage plans issued by SpaceX: Details of ponds and future buildings shown—LOX tank inner shell dome and pipes added, scaffolding removed—Drawworks for OLIT #2 spotted near it—Suspected water tank near CH4 area painted black, pipes laid out to the south of it

-Roberts Road—OLIT #3 segments: 4 completed, fifth under constructions, parts for 6th ready; 2 new foundations for tower segments added, unknown reason—Chopsticks: Rail system installed—Tip of QD-arm next to it—Starfactory, southernmost part being constructed, more wall and roof pannels added—Mega bay work didn't continue

NSF
21.11.2022 Still quite stormy [vid 25]
20.11.2022 Temporary tent installed near OLS, likely supporting concrete work under the OLM [vid 25]
19.11.2022 S25 rolled back to its stand in high bay after engine installation [vid 25]

Storm at Starbase [vid 25]

New Raptor 2 engine delivered to Launch site EpicSpaceflight Can crusher lifted off test tank? at PPS [compare 11 Nov] RGV

LabPadre
18.11.2022 B10 LOX tank stacking begun: cmn dome and aft #2 sections stacked, now 8 rings tall [The Ring Watchers]

Cladding installation on OLIT has begun [Chris Kleindl]

Work around S24 continued, three rows of tilesnear the bottom removed

S25 lifted in high bay, possibly to install the Raptor Vacuum engines

Cape: OLIT drawworks installed at the LC-39A OLIT base

LabPadre

NSF

Chris K

[42]
17.11.2022 New test tank spotted outside mid bay (add: TT13 or S26.1) [vid 18]

S24 worked on, more scaffolding added around aft sections, work also on rest of ship [vid 18]

B6.1 test tank compression ropes removed from structural test stand after testing [vid 18]

OLM inspection and work continued [vid 18]

LOX cryo-pump motor delivered to OLS tank farm CH4 side (lifted at 18:00); according to NSF for LOX site [vid 18]

B10 cmn dome section lifted and moved in front of mega bay to collect the next section, after that, both pieces were lifted back to the welding table [vid 18]

McGregor: Raptor engine tested on vertical test stand

LabPadre

NSF

16.11.2022 Methane CH4 deliveries to OLS tank farm [vid 18]

Ship aft sleeve worked on in tent 2 [vid 18]

Tent construction at PPS continued with another beam added [vid 18]

Rocket garden: B8, B4, SN15, S22, S20/SN20

McGregor: Raptor engine tested on horizontal test stand

15.11.2022 Booster cmn dome section spotted outside mega bay

S24 on pad B, and the pad receiving upgrades (add rather S24), a lot of scaffolding around the pad and ship aft section

OLM work platform raised under B7 at 16:40

OLM damage inspection after B7 static fire; legs toasted quite a lot

Ship transport stand near S24 Artemis: NASA awarded SpaceX a second contract option for Artemis moon landing. Option B award is valued at $1.15 bio [NASA]

B6.1 test tank tested Ring Watchers, NSF], area closed by Sheriff for testing

LabPadre

NSF

Chris

[43]
14.11.2022 Three raptor center engines moved into high bay for installation on S25

MSIB issued for testing on November 14–16

B7 14 engine static fire NSF; next is 20 seconds firing with max oxygen fill to test autogenous pressurization, possibly one more static fire, then orbital launch attempt [Musk]

OLM testing [vid 15]

S25: all three Rvac engines moved to high bay for isntallation

LR11000X attached to S24 at 19:29

S28 and S29 nosecones spotted, S28 with tiles [vid 15]

LR11000X attached to S24 [vid 15]

OLM testing continued [vid 15]

B6.1 test tank tested

LabPadre
13.11.2022 Overpressure notice issued to residents for tomorrow's testing [Mary]

OLM work platform lowered from under B7

McGregor: NSF view of horizontal test bays for Raptor

LabPadre

NSF

Chris K

Nomadd

[44]
12.11.2022 Raptor engine that was removed from S24 and speaker array moved away from launch site [vid 13]

Chopsticks raised ahead of static fire attempt of B7 [vid 13]

OLIT tower entrance with equipment shown; Box installed at the base of OLIT, likely serving to protect piping and other components from Raptor exhaust (box shielding) [vid 13]

Cladding for OLIT stored at launch site [vid 13]

Deliveries to production site (grey tube like structures) [vid 13]

SoLS pad B upgrade work while S24 is on the pad [vid 13]

Ship Loadspreader shown at launch site [vid 13]

OLM legs received mor shielding to protect the pipes running down the legs [vid 13]

B10 fwd section visible in mega bay [vid 13]

LR11000 lifted plumbing to Ship QD arm on OLIT, after that the crane returned to SoLS Pad B and picked up the loadspreader [vid 13]

11.11.2022 OLM work platform lifted under B7

OLM work continued, likely adding more shielding S24 one raptor center engine removed and taken to build site [Epic Spaceflight cam]

Micheal Sheetz: Leadership at starbase recently shaken up with COO Gwynne Shotwell and VP Mark Juncosa now leading the facility; senior director Sam Patel moved back to Florida and Omead Afshar joined from Tesla as production VP; Juncosa's visit over the summer uncovered alarming findings about progress toward's a first launch attempt; furthermore, 10-25% pay bump was offered to HQ employees to relocated to Starbase

LabPadre

NSF

Chris

Nic

[45]
10.11.2022 Overpressure notice issued to residents for today's testing

White horizontal ferus propellant tank left production site via Gate A1 on SPMT, likely towards Massey's site [vid 11] Ballast left launch site on SPMT early morning [vid 11]

LR11000X detached form S24 [vid 11]

Work on a test tank [see Test Tank November 2023] and can crusher/structural test stand at PPS [vid 11][add B6.1]

QD arm moved, chopsticks raised and opened [vid 11]

B7 spin prime test including FIREX [vid 11]

New test tank assembled in wide bay, name unknown, calling it test tank 13, TT13 the ring watchers [add: S26.1, consisting of S28 aft section]

McGregor: 300 seconds Raptor Vacuum long duration test (roughly equal to a Starship orbital insertion burn); new larger vertical tanks installed on tripod stand

LabPadre

NSF

09.11.2022 Work on raptor platform under B7

S24 moved to SoLS pad B area (09:12-09:55)

Starlink box moved out of payload processing building

S28 starlink dispenser lifted into wind break/low bay

S24 attached to LR11000X at 14:15

Delivery to payload processing building; seems to be loaded with starlink satellites already, Starlink Block 2 satellites spotted

Nosecone TPS tile work in tent 3, flaps missing yet

S27 aft dome (4-ring) moved outside mega bay

S24 lifted onto SoLS pad B at 17:40

OLM work platform lowered from under B7 [vid 11, on 10th?]

B6.1 test article assembled with a ship aft section [see B6], Ring Watchers

LabPadre

NSF

Chris K

Nic

[46]
08.11.2022 OLM platform moved up to B7

S27 payload bay door installed

Starship 7/24: S24 destacked from B7

New test article (2 rings with stringers) moved from ring yard to PPS near can crusher

Chopsticks released and lowered

S25 lifted off pad A and moved from SoLS to production site into high bay for engine installation

Large new LOX cryo tank arrived at port of Brownsville from Cape Canaveral, transported to SpaceX's testing site at Massey's Gun range Starship Gazer

McGregor: 3 consecutive 14 second Raptor tests; yesterday and today, all white vertical tanks have been removed from the tripod stand

LabPadre

NSF

Chris K

Nic

[47]
07.11.2022 OLM raptor work platform lowered from B7 and removed from OLM [vid 08]

Ship QD attached to S24 [vid 08]

Starship 7/24 Cryo Proof Test; B7 CH4 tank [vid 08] S25 Cryo Proof Test; LOX tank

FIREX tested on OLM

LabPadre
06.11.2022 2 SPMTs with counterweights moved to launch site [vid 08]

OLM legs painted as they have been charred on previous static fire test [vid 08]

Starship 7/24 work near connection points [vid 08] B10 one grid fin already installed in mega bay RGV

LabPadre
05.11.2022 OLIT: some cladding for OLIT spotted RGV LabPadre
04,11.2022 Some cladding for OLIT arrived at launch site RGV

Consumables delivered to OLS tank farm S28 nosecone in tent 3 agian

S26 transfer tube installed in high bay

SpaceX: 200th Raptor 2 engine produced

Raptor 2 engines SN133 and SN128 delivered to production site [RGV]

MSIB issued for testing on 7, 8, 10 November

NSF

Nic

Chris K

LabPadre

[48]
03.11.2022 Mega bay backside extension construction continued [vid 04]

S28 nosecone outside tent 3; work on nosecones inside tent 3 continued [vid 04]

B9 construction in mega bay continued [vid 04]

S27 nosecone still outside [vid 04]

PPS new tent construction work continued, nearing completion [vid 04]

Starship 7/24 Cryo Proof Test; 2 cycles - CH4 tanks then LOX tanks partially loaded

McGregor: Rvac engine fired for 4 min, 40 sec; Shielded raptor spotted on vertical test stand; more engines tested

NSF
02.11.2022 Raptor 2 engines SN131 and SN153 delivered to production site WAI]

S25 Cryo Proof Test; LOX (fully) and CH4 tanks tested OLM word platform lowered [vid 04]

McGregor: Raptor engine prepared for installation on stand

LabPadre

NSF

01.11.2022 S27 midlox and common dome stack moved out of high bay to mid bay

S26 midlox and cmn dome stack moved out of mid bay to high bay

S25 Cryo Proof Test (First); LOX and CH4 tanks tested

S26 cmn dome + mid LOX section lifted onto aft section in high bay at 19:04 McGregor: Raptor engine tested on tripod stand

LabPadre

NSF

Nic

John

[49]

October 2022[]

Date Description Source Link
31.10.2022 OLM raptor work platform lowered

B8 rolled back to Rocket Garden without testing [vid Nov 01]

Starship 7/24 Cryo Proof and SQD Test [vid Nov 01]

McGregor: Raptor relight test

NASA, Artemis: details on remaining steps ahead of first orbital launch Eric Berger; "NASA is tracking 4 Starship / Super Heavy launches. 1. was supposed to be early summer, now December, so SpaceX has lost a few month there. Then Starship-to-Starship propellant transfer. Then longer duration missions. Then entry development."; "Mark Kirasich says it'll take 12-18 hours for Starship with 2 crew to get down to the lunar surface after undocking from Orion on Artemis III. Then 6 days on surface and 12-18 hours to get back up to Orion. Other 2 crew remain on Orion the whole time." Smith; "some sort of an independent backup system for the elevator on the lunar lander." Smith "First test of cryo fluid transfer in orbit planned during second spacex Starship orbital flight." Klotz

LabPadre
30.10.2022 Interesting sounds on OLS [vid Nov 01]
29.10.2022 LR110000X moved to pad A, [vid Nov 01]

S26 thrust section moved into high bay for stacking

2 SPMTs moved to launch site

S25 connected to LR11000X by load spreader [vid Nov 01]

RGV: EDOME at Massey's was tested earlier this week to failure RGV

S25 disconnected from load spreader and LR11000X [vid Nov 01]

Lifting squid transported to production site [vid Nov 01]

Booster engine shielding lifted and installed on B7

B9 chines installed [vid Nov 01]

LabPadre
28.10.2022 B9 fully stacked in wide bay at 22:21 [vid Nov 01]

S25 some testing (possibly ambient proof test)

4 raptor engines deliverd to production site; SN66, SN146, SN186 identified RGV

MSIB issued for testing Oct 31- Nov 4

McGregor: Raptor relight test

LabPadre

NSF

27.10.2022 B9 LOX tank removed from turntable and put on booster transport stand in wide bay

McGregor: New tank installed near tripod stand

Raptor work platform raised [vid Nov 01]

LabPadre

NSF

26.10.2022 S26 nosecone moved out of high bay into mid bay

S27 mid-LOX and cmn sections moved into high bay and stacked; S27 stacking began Barrel section moved into tent 2

Delivery of unknown objects to production site

B6 test tank attached to crane

Mega bay secondary building at backwall has progressed

New tent construction started at PPS

Starship 7/24 Cryo Proof Test; Both CH4 tanks tested

NSF

Nic

Jack

LabPadre

[50]
25.10.2022 S26 Nosecone worked on in high bay [vid 26], lifted off turn table

S27 Nosecone (likely) at production site, has hexagonal antenna tiles installed [vid 26]

B9 Fwd tank spotted in mega bay [vid 26]

Stand worked on at Rocket Garden / PPS [vid 26]

Gravel work at PPS [vid 26]

Nosecone TPS tile work in tent 3 progressed (S28?) [vid 26]

Booster transport stand worked on at PPS [vid 26]

4-ring barrel section spotted in tent 1 [vid 26]

Ship QD arm work platform moved into position [vid 26]

LabPadre
24.10.2022 Starship 7/24 Cryo Proof Test (First); Both LOX tanks tested

Musk: S24&B7 still planned for orbital test "unless it is damaged in testing. What really matters is that ship & booster production line is spooling up. Also, each new ship & booster has incremental design improvements."

LabPadre
23.10.2022 B10 methane tank lifted and stacked nto a quad section, now 13/13 rings tall

OLM work platform lowered from under B7

LabPadre
22.10.2022 B7 transport stand moved back to production site NSF

Nic

Jack

LabPadre

[51]
21.10.2022 Raptor platform moved away from OLM/B7, raptor engine has been installed during the night [vid 22]

Starship 7/24 interface inspected [vid 22]

S26 nosecone lifted into high bay [vid 22], stacked onto fwd dome

Medevac helicopter arrived at Starbase, crews trained [vid 22]

S27 nosecone spotted outside of tents [vid 22]

SoLS Pad B work continue [vid 22]

OLM work platform raised under B7

Cape: Inner dome for the new vertical tank at LC-39A installed (large tank near OLIT/LOX site) [Spaceflight Now]

NSF Cape Update #16:

-Roberts Road:

--OLIT #3: Three segments under construction, chopsticks rails with black colour spotted; southernmost segment is bottom segment with resting extension for chopsticks—Insulated pipes spotted near tents, likely for OLIT—Mega bay not yet progressed, but more beams staged—Starfactory work continued—Chopsticks arms look complete, actuators installed; rail work continued; one of four grabbing arms added to carriage system; QD arm cryo piping being installed

-Pad LC-39A:

--Deluge system for OLM installed—Methane tank farm connection work continued; likely water tank next to it [not the big one next to OLIT] painted black—West of main ramp, work continued as well, new cryo bunker being built, more tanks being added, possilby for LN2 storage

LabPadre
20.10.2022 S24 lifted by chopsticks, restacked onto B7; Starship 7/24 stacked for the second time

S25 lifted on; QD connectedto SoLS pad A for its testing campaign; no engines installed yet; both lifting operations took place nearly at the same time

S24 QD connected and worked on [vid 22]

SoLS Pad B upgrade or repair work undergoing [vid 22]

Ship QD extended and retracted again [vid 22]

Barrel section moved into mid bay [vid 22]

LR11000X detached from S25 [vid 22]

S26 nosecone (incl barrel) moved into high bay [vid 22]

Raptor engine moved to launch site [vid 22]

MSIB issued for testing from October 21–28

S26 LOX tank removed from turn table in high bay, moved to mid bay

S27 payload bay moved out of tent 3, S27 nosecone moved from low bay to ring yard

Raptor platform lowered from OLM/B7

Cape: LC-39A: Three large horizontal GSE tanks from the starship tank farm were removed, moved to the turn basin, and shipped out for unknown reason NSF

McGregor: Raptor rapid relight test on tripod stand, relight possibly aborted; new propellant tank lifted into place; raptor static fire on vertical raptor stand (long duration) NSF

NSF

Nic

Jack

LabPadre

[52]
19.10.2022 S25 rolled out to the launch site; now two boosters and two ships at launch site for the first time [vid 20]

S25 attached to LR11000X, tensioned [vid 20]

S26 fwd dome section moved into high bay

McGregor: Raptor static fire test on tripod stand, potential failed relight; second test with same engine 23 minutes later NSF

LabPadre

NSF

18.10.2022 S25 worked on in high bay [vid 20]

Ship QD retraction and extension extensively tested [vid 20]

Ship QD arm access platform extended [vid 20]

LR11000X rotated and lifted ship lifting squid [vid 20]

LabPadre
17.10.2022 S24 still attached to chopsticks

B10 CH4 tank lifted and stacked onto 3-ring section, now 9/13 rings tall

McGregor: Raptor rapid relight test on tripod stand NSF

NSF

Nic

Jack

LabPadre

[53]
16.10.2022 Work platform lifted under B7/OLM [vid 17]

LR11000X moved to SoLS [vid 17]

Ship QD arm retracted [vid 17]

Two SPMTs with counterweights moved to ring yard

Ship lifting squid moved to launch site

B10 3 ring section moved into mega bay for stacking

S24 lifted off B7 by chopsticks; Starship 7/24 destacked, possibly due to problems ship QD [vid 17]

LabPadre
15.10.2022 Work and inspection on OLM/B7 continued [vid 17]

Gravel and dirt work at SoLS [vid 17]

Mid LOX section spotted outside tent 3 [vid 17]

S27? Nosecone moved outside tent 3, 6 hexagonal tiles (antenna) spotted on it [vid 17]

S28? nosecone TPS work inside tent 3 has progressed [vid 17]

Work platform lifted under OLM/B7

McGregor: Raptor rapid relight test on tripod stand NSF

LabPadre

NSF

14.10.2022 S25 and S26 worked on in high bay [vid 17]

Ship transport stand moved to OLM [vid 17]

Nosecones for likely S27, S28 and S29 spotted in tent 3, on S28 nosecone, tile installation appears to have started, rest have no tiles yet [vid 17]

Scaffolding around S24 QD removed this morning

McGregor: Two more long duration raptor static fire test on tripod stand with TVC testing NSF] ("possibly testing new electric TVC that SpaceX is developing to reduce mass and complexity")

NSF
13.10.2022 B9 moved in mega bay

Ship QD extended, full speed retraction test, and extended again over night

Starship 7/24 unknown testing; likely aborted due to some problems; chopsticks closed in on S24 after testing

Expansion work behind mega bay continued

Minor work on starfactory continued

Ship aft test artickle skirt on structural test stand worked on (test tank), moved to dome yard CSI

Another ship aft skirt which was used to test mating mechanisms worked on near gate A3

Transport stand moved by SPMT on Remedios Avenue

S24 scaffolding added around ship QD connection

McGregor: Two long duration raptor static fire test on tripod stand with TVC testing NSF] (1:34 min?)

NSF

Jack

Nic

LabPadre

[54]
12.10.2022 Ship QD disconnected and reattached to S24

B9 grid fins installed [likely the ones that were previously slated for B8] [vid 13]

Drone inspected Starship 7/24 [vid 13]

Ship QD extended and retracted 8 times over night [vid 13]

S28 payload section PEZ dispenser installed [vid 13]

Ship QD arm access platform extended [vid 13]

S24 lifted off B7; interstage inspected by crews (possibly due to problems with mating mechanisms); then lowered back on B7 again [vid 13]

Ship aft skirt test article placed onto B6 test tank

B10 fwd dome section moved into mega bay; CH4 tank stacking began in mega bay: Triple fwd section lifted, stacked onto another triple section, now 6/13 rings tall

McGregor: Raptor long duration static fire test on horizontal test stand NSF

11.10.2022 Ship aft skirt test article moved from ring yard to Sanchez site [13th]

S26 cmn dome section moved into high bay, mdilox attached below cmn dome section, lifted onto turntable in high bay

Ship QD arm and QD movement tested several times

Starship 7/24: S24 stacked on B7 by chopsticks after some issues [see main article]; QD arm extended; QD attached to S24 later

B9 two grid fins installed (those were previously slated for B8!)

NSF

Nic

LabPadre

[55]
10.10.2022 B10 methane tank, first section moved into mega bay and lifted onto turntable

Ship QD arm moved away, B7 lifted bay chopsticks onto OLM; stabilizer pin movement on transport stand and chopsticks very clearly visible on NSF footage; chopsticks lowered; Booster QD opened and attached to B7, Ship QD arm extended towards B7

Raptor engine under OLM/B7 unwrapped, lifted for installation on B7

QD arm moved away from B7

Raptor engine returned to production sit

S24 moved between chopsticks for lifting

NSF

Nic

LabPadre

[56]
09.10.2022 S26 nosecone moved from High bay to mid bay [vid 10]

Raptor work platform lowered under OLM

Raptor moved under OLM on old work platoform

LabPadre
08.10.2022 Mc Gregor this week: Potential lunar starhip thruster fired; Raptor 2 horizontal test fire; Several Raptor 2 tests on vertical stand; Tests on raptor tripod stand NSF

S24 TPS tiles replaced and repaired [vid 10]

S25 payload bay door tested, opened and closed 6 times over about an hour [vid 10]

NSF
07.10.2022 Two Raptor engines delivered to launch site [Epic Spaceflight Hoop cam]

Chopsticks rotated and raised ahead of B7 arrival

B7 rolled out to pad, between Chopsticks; chopsticks closed and lifting points latched into position; view on upgrades on engine shielding pic Starship Gazer; 20 covers still missing, indicating that OLM work hasn't finished yet; installation expected after 33 engine SF

MSIB issued for October 10–14

Industrial mobile generator delivered to launch site

Ship QD arm QD plate extended and retracted as a test!

Road closed between 11:44 and 13:00; B7 lift aborted

OLS tank farm: several methane pumps waiting for installation Zack Golden

Cape: LC-39A: Huge hexagonal deluge system that was spotted earlier was lifted by LR11350 over the OLM and lowered around it SpaceflightNow, Zack Golden, incl animation]

NSF

Nic

LabPadre

[57]
06.10.2022 [NSF recap video:

S25 has been workded on in high bay; hexagonal antenna tiles have been installed

Several flat domes in front of tents

Ground work behind mega bay continued, new brown columns lifted at the exterior of the bay, new building?

Ship aft skirt on structural test stand including cap, ropes being connected

OLM work continued the whole week; seemed to slowly wrap up

Ship QD arm worked on; also on QD plate

OLS tank farm: several deliveries of CH4

S24 TPS tiles repair work]

B7 moved inside mega bay [vid 07]

NSF

Nic

LabPadre

[58]
05.10.2022 S28 nosecone TPS tile installation spotted in tent 3; meaning after tile-less S26 and S27, they are installing TPS tiles again on S28

Chopsticks swung away from OLM and lowered at 17:25-55

OLM balance device used Zack Golden

OLM clamp retraction test at 23:25 video

NSF Cape Update #15:

-Roberts Rd:

--Starfactory: Foundation nearly complete, big parts of columns installed, roof and wall progress also significant—Hydraulic actuators spotted near chopsticks for installation; Retention pond next to it—Dams have been built to prevent damage from storm Ian—OLIT segments: New parts for OLIT #3 spotted, 6 pads already prepared with footings; 3 options for location: LC49 (no work yet, environmental review still pending), LZ 1 & 2 from SpaceX north of LC-36 (possibly as a dedicated catch tower), LC47 (between SpaceX LC-40 and ULA LC-37; not much known about)

--Mega bay: foundations complete, lot of columns staged for stacking soon—Car park north of Hangar X paved

-Hangar M: OLM #3 segments spotted; OLM #2 construction inside

-LC-39A:

--OLIT has been fully stacked—White horizontal Propellant tank installed next to the big concrete tank (which according to NSF is for LOX; others say for water)

--Hexagonal structure complete with parts sticking up, likely for water deluge on OLM, as it fits a hexagonal cut out around the OLM legs—Retention pond being worked on right next to OLM—Piping between methane site and tower looks more complete—Red truss sections spotted next to LR11350 and tents, likely for chopstick assembly just as at Starbase

LabPadre
04.10.2022 S26 nosecone lifted onto its barrel section on the turntable in high bay

Cape / Jessie Anderson: "We are building here at HLC-39A the launch pad for Starship, the same Pad that will see the first Test flight of the Starship Lunar Lander for NASA's Artemis Program." [Crew5 launch stream]

LabPadre
03.10.2022 S24 attached to LR11000X via ship load spreader (Squid) LabPadre
02.10.2022 BQD on OLM finally retracted after being open since September 22 for testing and shielding installation

Cape: Air Force Station: At least 9 columns for a third OLM have been spotted at Hangar M Harry Stranger

LabPadre
01.10.2022 S26 nosecone moved back into high bay

OLM: Pneumatic valves added to the pre-press mainfold (three lower LOX prepress pipes) Zack Golden Rocket garden: Concrete base for new display stand under construction RGV]

Animation explaining possible Starlink load ChameleonCircuit

Houston Texas: Column for potential future OLIT [#3] at the cape spotted on a highway [Reddit SpaceXLounge]

LabPadre

September 2022[]

Date Description Source Link
30.09.2022 S24 disconnected from pad QD, lifted off SoLS pad B by LR11000X onto transport stand; later unhooked from lifting squid and moved towards OLM by two SPMTs; several missing tiles spotted; parked at the OLS cryo station [QD pannel missing]

OLM work continued

S26 New design for FTS enclosures spotted The Ring Watchers]

Massey's gun range: EDOME test tank cryo proof tested; popped; first test at this site RGV

NSF

Nic

LabPadre

[59]
29.09.2022 B8 fwd section still without grid fins [vid 30]

OLM work continued [vid 30]

SPMT with ballast moved to launch site [vid 30]

LabPadre
28.09.2022 OLM extensive upgrading work continued [vid 30]

S26 payload bay section moved onto robotic welding station in high bay [vid 30]; no pez dispenser installed or a door cut out

S26 nosecone moved into high bay (again), moved back out of high bay again

B9 LOX tank stacked onto thrust section, now 24/24 rings tall Kevin Randolph, WAI

McGregor: Raptor 2 rapid relight test on tripod stand; 8 seconds in between, second burn for about 5 seconds NSF]

LabPadre
27.09.2022 S24 has been connected to LR11000X

S26 nosecone moved to high bay

New nosecone exited tent 3

B9 spotted in mega bay, it appears to be the first booster to use electric TVC (thrust vector control) as no hydraulic power units have been installed

Can crusher top placed on top of the ship aft test article Randolph

NSF

Nic

Nomadd

LabPadre

[60]
26.09.2022 B7 hooked up to both bridge cranes in mega bay at around 1 am

B9 thrust sectin moved into mega bay early morning OLM work continued extensively; covers were installed at the hold down clamp openings (blast shielding to protect the interior) [vid 27]

Ship aft test article moved from dome yard to Sanchez site/PPS; lifted onto the can crusher/structural test stand at PPS/Sanchez site Kevin Randolph, WAI

S24 scaffolding removed late niht

LabPadre
25.09.2022 LabPadre
24.09.2022 Massey's Gun range: Horizontal storage tanks and fill lines have been recently installed; possible engine and test tank test site RGV LabPadre
23.09.2022 OLM work platform lifted at 17:40

S24 PEZ dispenser permanently closed with new cover welded on to it Starship Gazer]

OLS tank farm CH5 and LOX pump swapping out continued Zack Golden

OLS tank farm LN2 delivery [vid 27]

Extensive OLM work [vid 27]

LabPadre
22.09.2022 OLM nitrogen purge test at 08:30

OLM fire suppression/deluge test with LN2 and water at 08:43

OLM booster QD opened; OLM Nitrogen Firex and detonation suppression walves and two of the QD walves (CH4 prepress and GOX fill/drain [possibly also using just LN2]); stystem tested extensivelsy

Chopsticks lowered

B7.1 and EDOME test tanks have entered hwy 4, headed towards Massey's gun range site

Chopsticks lowered at 11:25

S26 nosecone left ring yard for second time

OLM work platform lifted at around 17:40

OLS tank farm: Cryo pump removed at CH4 side [vid 27] [date?]

McGregor: Raptor engine tested on vertical test stand, which has two testing bays, allowing for rapid swap and testing schedule NSF]

NSF

Nic

LabPadre

[61]
21.09.2022 Payload door cover delivered to S24

S24 payload bay door cover lifted and installed

B7/OLM QD retracted

S27 starlink dispenser installed in payload bay section

S26 nosecone and barrel section outside tents

Ship flap with tiles (already installed on delivery) spotted

Production site building expansion worked on

B7 transport stand pins raised again, chopstick stabilizer arms engaged, B7 lifted off OLM onto transport stand

B7 transported back to production site, into mega bay for upgrades

B9 downcomer moved into mega bay for installation

S27 payload section moved into tent 3

S25 second aft flap lifted into high bay for installation

OLM: Nitrogen LN2 nozzles have been removed, likely to protect them from contaminated water during upcoming first test of the newly installed water deluge system Zack Golden

OLM fire suppression tests at 20:15 and 21:04; started with the original spyral nozzles, followed by the new system slowly ramping up the flow; name "Firex and Detonation Suppression" according to control panel for the water walves that has been installed in early September - so it's not a deluge system Zack Golden]

Cape: Drawworks for chopsticks prepared for installation on pad LC-39A after it was removed from Deimos Zack Golden, FarryFaz]

Elon Musk: First booster at 39A "Probably Q2 next year, with vehicles initially transferred by boat from Port of Brownsville to the Cape"

NSF

Nic

LabPadre

[62]
20.09.2022 B7 raptor engines SN49 (boost), SN82 (center) removed; later moved to build site

B7 Raptor boost engine SN82 lifted under OLM for installation

Chopsticks lifted and connected to B7 [vid 21]

Transport stand lifting pins raised; chopsticks lifted; B7 lift aborted [vid 21]

S25 first aft flap lifted into high bay for installation

NSF

Mary

Nic

LabPadre

[63]
19.09.2022 Chopsticks raised ahead of B7 testing [vid 20]

B7 spin prim and static fire tested with seven engines; additionally, the grid fins moved ahead of the test; some damage to the OLM legs (paint?)

Chopsticks lowered [vid 20]

Nosecone (S27?) rolled out of tent 3 [date? vid 20]

B8 rolled out to the launch site (grid fins and engines not yet installed) [vid 20]

S24, still connected to LR11000X, worked on [vid 20]

New OLIT blinking warn-lights spotted [vid 20]

Transport stand moved to launch site (possibly for B7 roll back) [vid 20]

S25 lifted and moved in high bay [vid 20]

Cape: New tanks delivered to LC-39A Rev Hawx

NSF [64]
18.09.2022 S26 nosecone moved in front of high bay again LabPadre
17.09.2022 Chopsticks lowered

B9 LOX tank stacked onto another quad section, now 20/24 rings tall

LabPadre
16.09.2022 Water truck sprayed water around the OLM [?] [vid 20]

B7.1 moved back to the production site [vid 20]

B7 spin prime tested (seven engines)

Chopsticks raised at 18:50

Cape: OLIT at LC-39A now complete with last segment stacked and installed this morning [Spaceflight Now]

15.09.2022 S24 temporary work platform installed below payload door

S25 spun in high bay (twice)

Crews worked on a tracking station on mid bay

B9 CH4 tank spotted in mega bay

S26 nosecone outside high bay (no tiles); later moved back to the windbreak again and connected to load spreader; lifted into windbreak

NSF

Nic

LabPadre

[65]
14.09.2022 Cape: Booster QD hood delivered to LC-39A, also brackets for OLM skirt welded onto the legs [Aaron Jones, Zack Golden]

First barrel section spotted in the new starfactory, possibly a ship payload bay Ring Watchers

S26 nosecone [old S27 nosecone] spotted in front of tents, moved later to the other side of the bay/tent area [vid 15]

OLS tank farm consumables delivered [vid 15]

Roof worked on at production site [vid 15]

Raptor van departed, grid fin moved at productin site [vid 15]

Metal pieces lowered from OLM, work platform lowered and moved [vid 15]

B9 LOX tank section lifted and stacked on a quad; now 16/23 rings tall [vid 15]

S25 welding work continued in high bay; weld inspected by crews [vid 15]

Ship QD arm tested

LabPadre
13.09.2022 Raptor work platform raised at 01:58 under OLM/B7

S24 worked on, unclear why it was attached to LR11000X

B8 with chines installed in mega bay

Starfactory worked on inside; this part of the building looks finished

OLM work continued, especially on water pipe installation for deluge system

OLS tank farm LN2 delivered

McGregor: Raptor Blast Shield tested on tripod stand to destruction after being spotted on the horizontal test stand; used to protect other engines from shrapnel if one fails in flight NSF

Cape: Transport stands to be delivered to roberts road from Port Canaveral Greg Scott]

NSF

Nic

LabPadre

[66]
12.09.2022 Raptor work platform lowered under B7/OLM [vid 13]

S25 tank section lifted onto welding turntable ahead of stacking [vid 13]

Structural test stand moved back to production site on 2 SPMTs [vid 13]

Starfactory: wall paneling soon finished [vid 13]

Chopsticks raised ahead of B7 testing [vid 13]

B7 spin prime tested, possibly all 33 engines (unconfirmed) [vid 13]

S25 nosecone finally lifted and stacked on tank section [vid 13]

Cape: OLIT segment 8b attached to LR11350 [Spaceflight Now]

LabPadre
11.09.2022 Cape: OLIT segment 8b rolled out from Roberts road facility to pad LC-39A

Two SPMTs moved to launch site

NSF Cape Update #14:

-Roberts road:

--Starfactory progressed: roof on northern part as well as north wall panels installed; wall and roof framings installed further south—Mega bay: Concrete foundation complete, many columns ready for lifting, LR11000X2 and another smaller crane ready for lifting; concrete square foundations ready for prefabricate building segments—Chopsticks rails installed (the chopsticks are smaller than in boca chica); hydraulic accumulator installed on carriage system—OLIT segment 8b/9 looks finished, pulley installed, SPMTs under it for roll out [rolled out this night]

-LC-39A:

--OLIT now 8 segments tall (only final segment missing)

--Cryogenig tank construction continued—Methane site to the north: Sphere now fully painted white, new tank being constructed, possibly for methane; new transfer lines connect the methane site to OLIT—New subcoolers spotted next to the horizontal tanks that were installed next to the OLIT, and a bit north, a possible GSE bunker is being built—Hexagonal structure to the south has pipes installed

LabPadre

NSF

10.09.2022 LR11000X moved towards S24; lifting squid moved to launch site; attached to S24 at 11:21

Another work platform moved into mega bay, lifted and installed Cape: OLIT segment 8a lifted and stacked at LC-39A

LabPadre
09.09.2022 B7.1 structural test stand cap removed, moved to production site by an SPMT; later loadspreader and LR11000X connected to B7.1, lifted off structural test stand

OLM work continued, more pipes added

Raptor maintenance platform under OLM/B7

B7 inspected at the top of fwd dome

Chopsticks: shift lifting pins currently deployed

Burned land after S24 static fire from yesterday

MSIB posted for testing on September 12 and 14

NSF

Nic

LabPadre

[67]
08.09.2022 Booster aerocover delivered

Walkway sections, likely for mega bay, moved

Raptor engine spotted near tent 1

Booster aft dome and EDOME spotted around tent area

Ship common dome section (sleeved) moved

Chopsticks raised ahead of testing

B7 spin prime test of multiple engines

S24 six engine static fire for about 6 seconds NSF video; grass fire developed afterwards; several tiles lost

Chopsticks lowered after testing

After road opened late night, fire fighters moved in to control the fire; controlled burns were started; fire ended not before the next morning

NSF

Mary

Nic

LabPadre

[68]
07.09.2022 OLM work continued with a lot of man lifts; new plumbing installed again

Ship QD arm and QD worked on

S24 inspected and worked on through access hole at fwd dome

B7.1 structural test stand cap ropes disconnected from stand

B8 work continued in mega bay

S25 nosecone hooked to high bay bridge crane

Raptor truck left starbase

NASA HLS update

Overpressure notice issued to residents for testing tomorrow

Raptor work platform lowered from OLM/B7 at 20:13

NSF

Mary

Nic

LabPadre

[69]
06.09.2022 B10? cmn dome section spotted, filepped; likely new EDOME used (elliptical dome)

S26 nosecone in tent 3 TPS tile completely uninstalled

B8 worked on in mega bay

Mega bay top work continued, wall soon to be finished

Two large horizontal LN2 tanks moved from Stabase to Massey's Gun Range, speculations that SpaceX is planning to build a new Raptor engine testing facility there

B7.1 cryo proof tested

McGregor: Raptor 2 engine tested to failure on horizontal stand and tripod stand NSF

NSF

Mary

Nic

LabPadre

[70]
05.09.2022 narrated update video NSF

LabPadre

04.09.2022 Cape/Brownsville: Tug and barge from port Canaveral arrived at Brownsville to load 4 unknown tanks. Same barge previously delivered tanks to LC-39A LabPadre
03.09.2022 B9 LOX tank stacked on another quad section (now 12 of 23 rings tall)

S24 Raptor vacuum engine RV SN115 lifted and installed after being delivered to launch site

LabPadre
02.09.2022 B7 New raptor engine delivered at 01:31 am, installed; raptor platform lowered at 5:22 am

Raptor platform raised under OLM/B7

Cape: LR11350 raised after reconfigured to lift the 2 final OLIT tower segments [Spaceflight Now]

Raptor vacuum engine RV SN65 removed from S24, transported back to production site

Marine Safety Information Bulletin MISB posted from September 6–9 for testing

McGregor: Two Raptor 2 engine tested to failur on horizontal test stand and tripod stand NSF

McGregor: Raptor 2 preburner test on vertical test stand [NSF]

LabPadre
01.09.2022 Overpressure notice issued to residents for testing

B7.1 test tank cryo tested S24 fwd flaps moved at 11:00 am

B7 one raptor engine removed (engine that wasn't tested yesterday)

McGregor: Raptor 2 test on vertical test stand [NSF]

NSF

LabPadre

August 2022[]

Date Description Source Link
31.08.2022 Cape: 8th segment for OLIT moved to LC-39A

Raptor maintenance platform lowered from B7 and moved to the landing pad area

B7 static fire test with multiple engines for the first time on OLM for 5–6 seconds; possibly 3 engines intended and 1-2 aborted S24 cryo tested on Pad B; possibly aborted static fire test

B8 smaller chines added at 9:49 in mega bay

McGregor: Raptor 2 test to failure on tripod stand NSF]

McGregor: Raptor 2 test on vertical test stand [NSF]

NSF

LabPadre

[71]
30.08.2022 Overpressure notice issued to residents for testing today

Raptor work platform lifted under B7/OLM

Overpressure notice issued to residents for testing on August 31

LabPadre
29.08.2022 B7.1 lifted onto can crusher test stand at around 3:30 am

S25 nosecone and payload bay section being stacked on fwd dome section at around 4 am

Raptor work platform lowered under B7/OLM at around 6 am

LR11000X disconnected from S24

B7.1: Can crusher cap lifted onto test tank, ropes/straps lowered and attached to the base

Chopsticks raised above B7

B7 cryo testing; no static fire test despite overpressure notice

LabPadre
28.08.2022 Can crusher attached to a new hydraulic gantry, lifted onto an SPMT, moved towards B7.1

Overpressure notice issued to residents for testing on August 29

Elon Musk: OLM is now responsible for starting all 33 engines via QD instead of COPVs. Also they are working to "achieve robust engine containment in case of RUD to protect booster, other engines & launch ring", likely referring to the new engine chill line

Cape: LR11350 lowered for reconfiguration ahead of stacking the top segments

Cape: Another large diameter outer ring section stacked on the large new tank at LC-39A

LabPadre
27.08.2022 Second raptor work platform moved into the left side of mega bay

Hydraulic gantry that begun assembly yesterday has this morning been brought down without moving the can crusher [for B7.1 testing]

LabPadre
26.08.2022 Raptor work platform lifted under OLM/B7

Chopsticks lowered to the bottom at arount 1 am

LR11000X moved to S24 at Pad B; picked up the ship loadspreader and attached to S24 (likely to support structure during depressed work inside)

OLM work continued after yesterdays testing; raptor work platform has been raised under B7

S25 tank section and nosecone worked on in high bay

B9 first LOX tank section moved to mega bay, cmn dome attached to bridge crane for stacking with it

Mega bay top level work continued; more wall pannels have been added

MiG-17 flyover by Jared Isaacman and Polaris team

Gantry crane assembled over structural test stand at OLS

B7.1 test stand moved at launch site; hydraulic gantry installed to lift can crusher [for B7.1 testing]

S24 LOX hatch opened at 16:25

Cape: New ring section lifted onto the very large new tank at LC-39A; LR11350 stacked 7th OLIT section [spaceflight now]

NSF

Mary

LabPadre

[72]
25.08.2022 Chopsticks detached from B7, opened and raised; damaged scaffolding on OLIT during lift

USAF F-22 Raptor demonstration team flew over Starbase

B8 worked on in mega bay

S25 fwd dome section moved into high bay, lifted onto the turntable in high bay at 13:55

B7 spin prime tested twice on OLM with likely 3 engines

S24 spin prime tested on Pad B

B7.1 rolled back to the launch site, new top vent valves have been installed

SpaceX: T-Mobile partnership announcement at an event at the rocket garden

B9 CH4 section lifted onto a new stand at 18:40; cmn dome wheeled in front of Mega Bay

B2.1 test tank cut in half

Marine safety information bulletin MISB posted for August 29-September 1 for testing

NSF

Mary

LabPadre

[73]
24.08.2022 OLM raptor platform lifted under OLM/B7; lowered again

OLM pad area cleared of any debris ahead of B7 testing

OLS GSE vented

SoLS pad A, part lifted onto SPMT

EDOME test tank moved back to rocket garden without being tested

S26 payload section outside tents

S25 fwd dome section fully tiled still waiting for stacking

SN16 scrap section spotted

Starfactory more wall pannels being added

B9 LOX tank segment spotted outside mega bay

B7 ignitor test

S24 cryo tested; pad B deluge tested (possibly spin prime abort); S24 ignitor tests

Overpressure notice issued to residents for testing on August 25

Mega bay: first walkway installed on the back wall, following the installation of the first work platform

McGregor: Raptor engine SN144 tested to destruction at McGregor tripod stand NSF

Hawthorne HQ: "SpaceX is testing their HLS Starship elevator design. [...] Google Earth and satellite imagery show that SpaceX has created a mock set-up that resembles the 9 metre Starship to test their astronaut lunar elevator" Toby Li

NSF

Mary

LabPadre

Toby Li

[74]
23.08.2022 B7 disconnected from bridge crane; Ship QD arm retracted on OLIT; Chopsticks raised ahead of B7 stacking; booster QD lines purged

First raptor work platform moved into mega bay at 15:36 B7 rolled back to the OLS with all 33 engines installed, much of the engine covers is still missing and will need to be added ahead of a flight test (Raptor engines SN70, SN49, SN84, SN51, SN44, SN63 identified); rolled to the OLS and between the chopsticks arm

S25 nosecone has been disconnected from high bay bridge crane, work continued

B8 spotted in mega bay

Starfactory work continued; more wall pannels added

Grove crane moved

S24 work continued

OLM booster QD is open

B7 and OLM prepared for lifting; connected to chopsticks and lifted slightly; stabilizers attached, guide pins on stand retracted; lifted, rotated and lowered onto OLM

OLM booster QD attached to B7 at 22:48, raptor service platform raised under OLM [vid 23]

Hawthorne HQ: New details released of the HLS Starship crew elevator development. NASA HLS Program Manager, Lisa Watson-Morgan spoke today on its progress: NASA is working hand in hand with SpaceX. The elevator is redundant and multi-fault tolerant. Currently testing with crew. Toby Li]

NSF

Mary

Nic

LabPadre

Toby Li

[75]
22.08.2022 S24 aft section work continued

OLM work continued

OLS earth work to the east of the pad

SoLS earth work near Pad B

New OLM shielding spotted at launch site

SoLS Pad A worked on, refitting it for cryo tests

B7 in mega bay; inner engines now installed; work continued

S26 quad section spotted outside tent

S25 nosecone in high bay worked on

Chopsticks rotated forth and back

Elon Musk: Starship to orbit is a main goal for this year

NSF

Mary

Nic

LabPadre

Elon Musk

[76]
21.08.2022 [no NSF video]

Cape: Roberts Road: New LR11000 crane raised; Pad LC-39A: Segment 7 for OLIT attached to loadspreader and LR11350

LabPadre
20.08.2022 [no NSF video]

Marine Safety Information Bulletin MISB issued for testing from August 22–25

LabPadre
19.08.2022 Blue origin's ship jacklyn arrived in Brownsville for scrapping

Ballast remvoed from an SPMT at production site

Starfactory work continued, especially on roof; west wall pannels beginning to be added

Chine segments for future boosters spotted at production site

Booster common dome sleeved [B10?]

Unknown jig moved out of tent

B7 worked on in mega bay, workers near grid fins

OLM booster QD open

Chopsticks work continued; tested (raised and lowered again, horizontal movement tests)

NSF

Nic

LabPadre

[77]
18.08.2022 OLIT welding work

S25 nosecone section lifted in high bay and stacked onto payload section

S24 aft section worked on; QD and through hatch

Mega bay rooftop work continued

B7 worked on in mega bay

OLM work continued, new plumbing has been added [add: for engine chill vent collection]

Chopsticks: cylindrical actuator for moving up the track worked on

Launch site main gate entrance worked on

Both new and old Rapotor work platform moved to SoLS Pad A

Elliptical dome test tank at launch site

chopsticks raised, rotated slightly and lowered againg

Starfactory roof construction work continued, pannels added; some tooling already moved into ist

Telehandler delivered

SKY perfect JSAT has selected Starship for launch of the Superbird-9 communication satellite in 2024 to geostationary transfer orbit

Cape: Starfactory roof and wall sections being added, top OLIT section nearly complete, high bay foundations completed; tracks for a new Starship transporter spotted Greg Scott

NSF

Mary

Nic

LabPadre

[78]
17.08.2022 OLM and Chopsticks work continued; engine chill vent line installation continued

Launch site main gate entrance work continued

Raptor bell SN22 spotted at launch site

S25 aft (LOX) tank work continued as well as on nosecone which is still connected to high bay bridge crane; nosecone section lifted onto turntable to make way for stacking onto fwd dome section; CH4 transfer tube for the header tank moved into high bay for installation Kevin Randolph

B7 and B8 (hidden) in mega bay, worked on

Starfactory work continued, stair assembly next to it

Nosecone lifting jig form S25 spotted

Gaseous nitrogen trailer moved

Raptor SN37 test fires at McGregor NSF

NSF

Mary

Nic

LabPadre

[79]
16.08.2022 SoLS west side earth work continued

OLM new plumbing lifted and installed [add: new engine chill vent line]

LN2 delivered to OLS tank farm

OLIT work on several segments

Launch site main gate: road work continued

Chopsticks catch actuators spotted at launch site; chopsticks work continued; catch actuators installed later

OLS tank farm: New cryo pump installed at CH4 subcooler site; electric cryo pump motors spotted and installed

LR11000X moved from OLS to SoLS

Ship QD arm moved

B10 fwd dome sleeved on sleeving stand

S26 payload bay section spotted

B7 work in mega bay continued

Starfactory work continued; western wall work began and roof work continued

S26? nosecone: TPS tiles seem to get uninstalled! The Ring Watchers

Cape: OLIT segment 7 rolled out to LC-39A [Spaceflight Now]; parts of a new LR11000 for roberts road spotted on a highway in Florida Justin

NSF

Mary

Nic

LabPadre

The ring watchers

[80]
15.08.2022 S25 nosecone and tank sections worked on in high bay; welding work as noseceon is still connected to bridge crane

B7 spotted in mega bay, where it is getting its 13 inner engines installed for further testing; engines worked on (literally)

Booster fwd dome sleeve moved out of tent toward sleeving stand; attached to crane

Ship flap mounts spotted

Starfactory work continued, especially on roof

Raptor gimbal hardware delivered "These are single cardan joints that go on Raptor Center engines, allowing them to gimble"

Nosecone worked on in tent 3 with TPS tiles being added [possibly S26]

Chopsticks: catch hardware added, a silver actuator that moves the track upwards before a catch happens

S24 engine section worked on a lot

OLM work continued after B7 left

SoLS: ground work to the west continued

Cape: LR11350 raised after reconfigurations [SFN Stream]

NSF

Mary

LabPadre

[81]
14.08.2022 S25 nosecone stacked in high bay onto the payload section [vid 15] LabPadre
13.08.2022 S25 nosecone moved into high bay for stacking at 2:54 am

Chopsticks moved for the first time at 12:45 after the hydraulic failure [vid 15]

LabPadre
12.08.2022 Multiple Raptor engines were moved into the mega bay for installation on B7: SN83, SN99, SN26, SN102, SN104, SN72, 5 not identified

B7 connected to LR11000X via load spreader; booster Qd retracted; booster trasport stand moved into place; ship QD arm retracted; B7 lifted and placed onto transport stand (engines spotted: SN41, SN53, SN86, SN34, SN85, SN39, SN47, SN44, SN51, SN84, SN49, SN70, SN28, SN42, SN21)

S25 methane transfer tube installed to tank LOX section in mid bay

S25 nosecone lifted out of windbreak, placed onto a new transport stand; payload bay section moved into high bay at 9:20 am for stacking

B7 rolled back to the production site, rolled into mega bay

S28 smooth fwd dome spotted in the dome yard RGV

Elon Musk: video of inner engine installation Elon Musk

New MISB posted for testing from August 15–18

Cape: LR11350 lowered for reconfigurations [Spaceflight Now]

NSF

Mary

Nic

LabPadre

RGV

[82]
11.08.2022 Raptor work platform lowered back down under OLM/B7 at 06:55 [vid 12]

B7 preparation work for more testing [vid 12]

SoLS concrete work [vid 12]

S25: both aft flap jigs moved from mid bay into high bay for installation at 10:23 and 13:06

B7 long duration static fire with a single engine (likely same engine as on August 9), testing autogenous pressurization; 20 seconds long video [vid 12]

SPMTs moved to launch site to for B7 transport [vid 12]

LR11000X moved towards OLM/B7 [vid 12]

NSF Cape update #13:

-Roberts Road:

--OLIT: Segment 6 prepared for roll out [see yesterday]; segment 9 or 8b construction has began; segment 7 is prepared for roll out, segment 8a will soon be ready as well; cryo pipe assemby tents moved closer to the building area, coils of wire spotted near them—Chopsticks laid on their sides, possibly for installation of rail segments (interface with booster and ship lifting point); grabbing parts that hold on to the OLIT columns spotted next to carriage system—Ship QD arm work potentially finished as scaffolding removed—Concrete foundation work for mega bay soon finished; makeshift ramp installed—Starfactory work continued at a fast pace, slowly growing towards the south, more concrete floor being poured

-Pad LC-39A:

--OLIT: segment 5 (QD arm segment) lifted yesterday—Tank nearby is being constructed on the stand; double shelled design speaks for a cryogenic tank; the two white horizontal tanks have been installed nearby—Hydrogene Sphere work continued (future methane tank)

LabPadre

NSF

10.08.2022 B8 seen in mega bay

S25 nosecone worked on; nosecone barrel/payload section seen

B7.1 test tank worked on via work platform/scaffolding in mid bay

S25? methane transfer tube spotted

Starfactory work continued

Elliptical dome moved, the first common dome with this new design

S25 tank section worked on in high bay; removed from turntable ahead of transfer tube installation; transfer tube spotted outside high bay

Chopsticks: chain between the arms removed at 14:45-15:00

OLS tank farm: one of the methan pump motors has been removed

Raptor work platform raised under B7/OLM

Chopsticks work continued; likely to repair the damage

SoLS earth work in the very west

Overpressure notice issued to residents for testing on 11 August

Cape: Segment 6 of OLIT stacked by LR11350 at LC-39A

NSF

Mary

Nic

LabPadre

[83]
09.08.2022 Cape: OLIT segment 6 rolled out to LC-39A [Spaceflight Now]

Can crusher cap's tank connected to LR11000, removed at 08:12

S24 work on engine section SPMT moved to production site

Starfactroy work continued

B7 static fire on OLM with a single engine for about 3 seconds; a first for both B7 and the OLM video

S24 static fire on SoLS Pad B with two engines for about 3 seconds video

Jarrod McLachlan announced that they are working on rideshare configurations for Starship, but nothing there was nothing concrete to announce to date Jeff Foust

NSF

Mary

Nic

LabPadre

[84]
08.08.2022 LR11000X moved away from OLS to SoLS after having lifted B7

S25 tank section spotted in high bay; section welded; S25 fwd dome section spotted outside tents

Ground work at the production site

S25 nosecone barrel section moved by a crane from low bay to front tent 3

Starfactory work continued; new columns and roof beams added; all 3 bridge cranes appear to be installed

Booster aft section spotted in front of tent 2

Mega bay work at the top continued

Ship transfer tube for S27 spotted (wrapped up), left tent area

OLM and B7 worked on heavily

Raptor work platform removed from the OLM

S24 spin prime tested twice

Chopsticks raised during S24 test

B7 spin prime tested twice with one engine (twice the same engine)

NSF

Mary

Nic

LabPadre

[85]
07.08.2022 Ship transport stand moved into high bay

MISB posted for testing form August 8–11

LabPadre
06.08.2022 Chopsticks lowered

B7 connected to LR11000X via load spreader [vid 08] Booster QD retracted (hood closed) [vid 08]

B7 lifted onto OLM by LR11000X as chopsticks were broken [vid 08]

New picture of Phobos and Deimos by SpacejunkieH]

LabPadre
05.08.2022 Four raptor engines delivered: SN108, SN80, SN81, SN66; later some lifted into mega bay

S26 common dome section flipped; after being sleeved on sleeving stand

SPMT moved into mega bay to move B8 away from the entrance

S26 fwd dome sleeve moved

S28 aft dome section flipped

OLM and chopsticks work continued

S24 aft flap inspected

Starfactory construction work continued

Earth wall spotted at the launch site

B7 moved in mega bay

S25 part lifted in high bay 1, likely for stacking

B7 rolled out to launch site; outer engines installed; arrived at 00:16 on 6 August

Chopsticks broke and leaked hydraulic fluid at 12:34 am; object was spotted falling down and bouncing off the booster QD hood; possibly part of recently installed actuators failed; drone inspected the chopsticks [6 August]

B7 moved away from the orbital launch site as a lift with chopsticks wasn't possible anymore [6 August]

S25 stack (cmn and midlox) stacked onto thrust section at 20:32

NSF

Mary

LabPadre

[86]
04.08.2022 OLM worked on a lot

OLS berm concrete pouring work continued

B10 aft section flipped in front of tents

Ship/booster? methane transfer tube delivered

S25 aft section rolled out of tent 3 to the high bay, fully covered with TPS tiles

Chopsticks welding work continued

S24 engine section worked on, TPS tiles inspected

SN16 scrapped section spotted

SoLS pad B (S24) water deluge tested at 18:49

Cape: Huge tank (water?) construction began at LC-39A with first large ring segment lifted [Spaceflight Now]

NSF

Mary

Nic

LabPadre

[87]
03.08.2022 B7 and B8 spotted in mega bay [vid 04]

B10 aft section (now sleeved) and a ship fwd dome spotted outside tent; aft section attached to crane [vid 04]

Starfactory work continued, also on the roof [vid 04]

OLM work continued, a work platform spotted below the mount [the same as raptor platform; vid 04]

SN16 aft flap left Starbase [Kevin Randolph WAI]

S26 payload bay TPS tiles work started in tent [Kevin Randolph WAI]

LabPadre [88]
02.08.2022 QD arm: Ship QD umbilical worked on

OLM work continued

Chopsticks welding work; moved at 16:00, first time the right arm moved since the actuator swap

Object lifted near structural test stand "can crusher" (likely a QD-pipes holder)

Crane mats delivered to launch site

B7 spotted in mega bay

Mega bay: top levels covered in scaffolding as work continued

Nosecone spotted in tent 3 with TPS tiles being installed [add: likely S26]

Tent next to mega bay continued to be dismantled

Starfactory work continued

Starlink loader moved out of starlink building/payload building; potentially starlink satellites Block 2.0 left starbase

Booster load spreader moved to launch site

Musk: "A successful orbital flight is probably between 1 and 12 months from now"

NSF

Mary

Nic

LabPadre

[89]
01.08.2022 S24 aft section work continued, aft hatch open

Damageed engine shrouds from B7 spotted at launch site

Old raptor platform spotted

GSE hoses lifted onto flatbed

B5 aft section finally lifted off transport mount, scrapping continued

Starfactory construction work continued; parts of the bridge crane have already been installed

B8 worked on in mega bay, B7 isn't visible in mega bay

Tent next to mega bay being dismantled

B7.1 test tank worked on in mid bay

Propellant production plant worked on

GSE hoses lowered next to S22

NSF

Mary

Nic

LabPadre

[90]

July 2022[]

Date Description Source Link
31.07.2022 [no NSF video]
30.07.2022 Scrapped booster engine shrouds spotted

S24 work on engine section continued

Chopsticks work continued

OLM work continued, pipes worked on; new maintenance platform was installed

S27 methane sump and transfer tube spotted at production side

B8 moved within mega bay, likely making way for B9 stacking

Stair segments spotted outside production site

Starfactory work continued

Starlink loader building painted

NSF

Mary

LabPadre

[91]
29.07.2022 SPMT moved to launch site at 00:16

Cape: OLIT section 5 stacked by LR11350 and being secured at LC-39A

Chines delivered for boosters

B7.1 attached to LR11000X via loadspreader; lifted onto a transport stand, rolled back to production site and later into mid bay SPMT moved to launch site, new raptor platform moved under OLM; later extended and raised

B9 last CH4 section moved into mega bay

OLM work continued

Chopsticks work continued

Raptor engines SN50, SN109, SN116, SN120 delivered

LNG purification stack near Stafactory prepared for shipment; secured on a truck, transported away

Stafactory work continued

B5 aft section spotted

B9 fwd sections moved within the mega bay; For the first time, there was a dual lift, featuring B9 CH4 tank and final quad stack; lifted to the welding turntable to complete stacking of the upper 13 rings

Grid fin loaded for shipping

Last vertical tank/absorption column left Starbase, heading to McGregor

NSF

Mary

LabPadre

[92]
28.07.2022 B5 all grid fins removed from fwd dome section

OLM venting in the night; construction continued Chopsticks work continued

S24 work near the aft section continued

B7.1 test tank valves worked on

Bridge crane parts delivered to Starfactory (main girders and walkway; 2 20 ton bridge cranse)

Starlink building being painted white

S25 nosecone worked on near flap

S22 maintenance? work inside

S24 fwd and aft flaps extended

Booster thrust plate delivered

Cape: LR11350 connected to OLIT segment 5 prior to stacking at LC-39A

NSF

Mary

LabPadre

[93]
27.07.2022 Pad closed after PA at 04:12 "to stop the work" for unknown reason

Chopsticks: vertical dampeners to absorb the shock during catching installed Starship Gazer]

B9 CH4 section moved into mega bay, stacked on a triple section in mega bay; now 9/13 rings tall

QD arm worked on B7.1 prepared for testing on structural test stand; work on vent valves on the top

B7.1 cryo tested via OLS tank farm

Raptor engines moved around at production site; SN100, SN43 identified incoming

SoLS pad A booster adapteo used for BN3 testing disassembled at production site

Starfactory work continued

MSIB posted for testing from August 1–4

Cape: OLIT segment 5 rolled out to LC-39A

NSF

Mary

Nic

LabPadre

[94]
26.07.2022 Ship transport stand parts delivered

OLM worked on

B7.1 test tank: valve assembly has been added; tape spotted on a weld

LR11000X moved towards SoLS

B9 CH4 section not stacked on the triple ring section, but rolled back out in front of mega bay, still 6 rings tall

NSF Cape Update #12:

-Roberts rd:

--Starship factory: Roof sections spotted previously now installed, building starting to rise, slight tilt to the north (south side taller), concrete foundations continued to be poured, some flooring already being installed; in the south more insulation work of power lines and fluid conduits—Chopsticks: both arms have shoulders installed; noticeably shorter than in Boca Chica—Ship QD, extra structure for umbilical spotted—OLIT sections: Fourth OLIT section moved to Pad 39A; Fifth OLIT section (QD-section) prepared to roll out, pair of SPMTs ready; 8th section under construction (shorter section), one roof level already installed; short columns and cross beams, likely for 9th segment spotted nearby—Mega bay concrete foundation work continued

-LC-39A:

--OLIT: tower has grown, OLIT is now 4 segments tall; some scaffolding removed between first and second segment; concrete work seems more or less finished at the base—Giant tank on the west: More rings have been delivered; the mystery structure looks like a base for this tank; purpose still unknown—Nearby, two concrete stands for two horizontal tanks have been spotted; the tanks have been spotted arriving on a barge—Berm construction started to the north of the OLIT area, likely separating it from and protecting the methane tank area—Methane tank farm area: Some clearing and ground work spotted north of the old hydrogen sphere; additional horizontal tanks and subcoolers seen south of it

-LC49:

--No work seen as approval work ongoing

NSF

Mary

Nic

LabPadre

[95]
25.07.2022 OLS tank farm: another pump was removed in the night

Raptor engines (SN29, SN68, SN36 identified, fourth one not clear) loaded onto truck; likely from B7

Ship fwd dome worked on near tents

Starfactory construction work continued

Mega bay (high bay 2) concrete work on top level

Mysterious items delivered to production site (black structures with holes on each side)

EDOME spotted at production site

OLM and chopsticks work continued heavily

OLS berm work continued with concrete being poured

OLS tank farm LOX delivered

LR11000X moved towards B7.1 test tank; ropes disconnected from bottom of test stand, structural test stand cap removed from B7.1 by LR11000X

New MSIB posted for testing from July 25–28

NSF

Mary

LabPadre

[96]
24.07.2022 [no NSF vid]

Starlink loader box moved back into payload processing building

Two SPMTs with counterweights exited mega bay

23.07.2022 OLS tank farm: pump removed during the night

Raptor boost engine moved from mega bay to tent 1 SoLS tank farm vented as consumables were delivered; earth work near it at the west side of the launch site

OLM and chopsticks worked on heavily; new parts added to the carriage system near the OLIt rails

OLIT worked on, scaffolding

Pipies delivered to production site

S24 engine section worked on

S25 LOX tank spotted in mid bay, moved into high bay

S26 mid LOX section spotted with TPS tiles installed but no flap installation points yet

"Raptor 2 has swiched from hydraulic to electric thrust vector control actuators", tests with this new system might have started at McGregor tripod stand (NSF)

Starlink loader box moved out of payload processing building

Two SPMTs entered mega bay

NSF

Mary

LabPadre

[97]
22.07.2022 Mega bay first glass panels lifted to the top

OLM reparation works ramp up; paint removed from the legs OLS tank farm berm continued to be covered by concrete [large parts have been done already]

Chopsticks worked on

S24 worked on at QD and around LOX hatch

Raptor platform painting continued at launch site

LR11000X maintenance work

Raptor engines SN95, SN101, SN102, SN104 delivered to production site; Raptor engines SN48, SN66, SN80, SN81 loaded for leaving [likely from B7]

Ship aft dome (likely S27) prepared for sleeving; aft dome sleeve connected to crane; sleeved with the help of hammers

Starfactory work continued, some workers on the roof

Gas storage structures spotted, "These structures are used to store potentially flammable or explosive canisters" [black cage like structures]

A raptor boost engine moved into mega bay

NSF

Mary

LabPadre

[98]
21.07.2022 OLS tank farm propellant delivered, several trucks

OLM raptor work platform painted white

Chopsticks and OLM worked on

SN16 scrap aft section near starfactory

Starfactory construction work continue

Ship aft dome prepared for sleeving [likely S27, see vid 22]

OLS tank farm vented, B7.1 test tank tested to failure; loaded with LN2 and structurally tested; popped after S24 test concluded, then detanked

Ship QD tested at the same time as B7.1

S24 Spin prime tested twice (at the same time as B7.1), first test likely only with one engine and partially filled LOX tank, second test likely only with two engines

Cape: 4th OLIT segment stacked at LC-39A by LR11350 [Spaceflight Now]

NSF

Mary

Nic

LabPadre

[99]
20.07.2022 MSIB posted for testing from July 20–21

New Raptor engines delivered and moved into tent 3 (SN88, SN106, SN93), old engines, likely damaged ones, left site (SN60 spotted, two others not identified) Ship LOX tank section with TPS tiles spotted [S25?]

B10? aft sleeve fipped; booster aft dome lifted onto sleeving stand and sleeved

OLS work nearand on OLM and chopsticks continued

Hydraulic accumulators spotted on chopsticks

New weather station on OLIt looks complete

S24 ignitor test

S24 Spin prime tested twice; likely with all 6 engines; LOX tank fully loaded for second test, no frost on CH4 tank

Cape: 4th OLIT segment rolled out to LC-39A

NSF

Mary

Nic

LabPadre

[100]
19.07.2022 Propellant delivered to SoLS tank farm as well as to OLS tank farm

OLS earth work on the eastern end

Chopsticks worked on

Starlink loader moved into new building ["payload building"?] by SPMT

Booster aft dome worked on at production site

Starfactory building work continued, especially on roof

B7 inspections continued in high bay 2/wide bay; 13 engines have now been removed

Stringers delivered for a new booster

OLS tank farm vented, followed by OLM; B7.1 test tank tested, loaded with LN2, ropes of the structural test stand used to simulate launch forces

NSF

Mary

Nic

LabPadre

[101]
18.07.2022 S24 vented, opening and closing to be observed

S24 spin prime tested ("spinning up the turbopump(s) of an engine without ignition"); LOX tank frosted up for this test, but no frost on CH4 tank

Starfactory construction work continued

S25 payload section moved out of tent 3 and was connected to a crane near S25 nosecone; both parts have TPS tiles installed

High bay 2/wide bay worked on inside

Ship aft section with TPS tile mounts moved

Starlinks loaded into payload integration box in a tent Kevin Randolph WAI

B7 raptor engines SN50, SN59, SN68 moved into tent 1 after being removed from the booster; 12 engines removed in total

NSF

Mary

LabPadre

[102]
17.07.2022 Actuator removed from rear chopstick (after front chopstick actuator has been replaced recently); later the rear chopstick actuator was replaced

S24 TPS tile worked on, more tiles added near aft flap

OLM still charred from B7 explosion; work continued

Ship domes spotted outside tents, as well as booster aft dome

More beams lifted onto top of new high bay/mega bay; crane moved to another section to continue construction

B7 inspected in high bay 2/wide bay

Ship aft barrel with QD spotted at production site, behind an old payload bay pathfinder

Starfactory construction work continued

B7 first raptor engines started to be removed

NSF

Mary

LabPadre

[103]
16.07.2022 [no NSF video]

B9 CH4 tank stacking began [RGV]

LabPadre
15.07.2022 Bosoter QD adapter connected to B7

B7 rolled back to the production site for inspection and repairs after the testing anomaly from July 11; moved into mega bay/high bay 2

S25 work continued on several areas

OLS tank farm venting

S24 inspected by drone

Raptors SN99 and SN76 delivered, possibly as replacement on B7

Starfactory construction continued

B10? aft dome spotted; B10 cmn dome sleeve spotted [Kevin Randolph]

Chopsticks: Second hydraulic accumulator mounted Kevin Randolph]

NSF

Mary

Nic

LabPadre

[104]
14.07.2022 Chopsticks opened ahead of B7 lifting operation, closed again (possibly to test the new actuator)

Engine shrouds removed from B7

Delivery on Remedios ave

Dirt work near production site

Booster test stand (triangle with two levels) worked on at PPS

Stair work for mega bay/high bay 2

Raptor platform moved away from OLS

Ship payload section spotted in high bay 1

High bay 2/mega bay more scaffolding installed, likely walls to be added to top level soon

S24 TPS tile installation continued

Chopsticks left arm actuated for the first time since actuator was replaced

B7 raptor engine moved to production site

Booster QD rectracted, ship QD arm retracted, chopsticks raised, closed in on B7, attached to lift points; B7 lifted off the OLM by chopsticks, onto booster transport stand (by the help of the pins!); removed engine shielding visible; then chopsticks disconnected from B7

MSIB issued for testing from July 18–20

Cape: New LR11000 crane being delivered for Roberts road Boca's Brain]

NSF

Mary

Nic

LabPadre

[105]
13.07.2022 New chopstick actuator installed as replacement of the old one that was recently removed

B7 engine section inspection continued via raptor platform, the whole day

OLM, some piping seems to be damaged as well

S24 TPS tiles being added on SoLS Pad B; also work near aft flaps

SPMTs moved to the launch site, under the booster transport stand, likely for B7 transport back to production site

B8 fwd dome section spotted; camera attached at the top

Mega bay/high bay 2 more scaffolding added at the top

Raptor engines (newly delivered) moved into the tents

Starfactory work continued

B5 scrapping continued

Raptor transport fixture delivered to launch site

Single raptor engine moved to launch site; replaced another (outer ring) engine on B7, unknown reason why this was done at the launch site; after that, the raptor platform moved away from B7 and OLM [vid 14]

Elon Musk: Orbital flight "if testing goes well, as soon as next month"

NSF Cape Update #11:

-Roberts Rd:

--OLIT section 4 & 5 prepared for roll out as scaffolding is being installed on the top and equipment has been installed; 7th segment strutcurally now complete; GSE pipes slowly disappearing as they are being installed—Mega bay foundation being poured, clearing made, likely for a pad to fabricate sections of the bay—Chopstick arm receiving a shoulder; carriage system being worked on, now the two parts have been joined together—Ship QD arm construction began near the chopsticks—Starfactory: roof beams and some sections already prefabricated and positioned next to the foundations; concrete poured and conduit laid—NASA plans: SpaceX plans to expand the roberts rd facility to the north; huge expansion "in support of optimizing production and launch of their reusable launch vehicle fleet"; 100 acres of land, consisting of facilities for: vehicle and payload processing, fabrication, storage, manufacturing and shipping and receiving

-LC-39A—OLIT 3rd segment installed; elevator being installed—Some ground work near the base of OLIT, possibly propellant lines and wiring laid—Barrel sections spotted near the mysterious stucuture near the main ramp, likely fit with it—Hexagonal piece in the south looks finished; it will likely be used to stabilize the OLM legs as they are filled with concrete and the during the curing process

NSF

Mary

Nic

LabPadre

[106]
12.07.2022 Mega bay/high bay 2 work at the top continued, new parts lifted

Deliveries to production site

B5 scrapped parts still outside at production site; some pieces moved out of mega bay to scrapyard

Starfactory work continued on many man lifts

Unknown structure spotted at production site: 5 vertical white tanks, connected to 6 smaller, black, vertical cylinders

Ship common dome washed outside tents; then put on sleeving stand

Nosecone being worked on in tent 3

Tube delivered to production site (rusty)

B6 test tank worked on (near the fin holes)

OLM and B7 inspection; the damage on the OLM legs is visible but likely not significant; other damage spotted: raptor trailer, argon storage, potential engine cover, generator, welding equipment, OLM railings, cabinets, small pipework on the OLIT, chopsticks scaffolding, ventilation hose, lamps, OLT control panels, scorching [Oscar Sparrow]

Raptor platform (old) moved under B7/OLM

Chopsticks: left arm secured with orange strap

New chopsticks arm hydraulic actuator delivered to launch site at 21:42

FAA/NASA: SpaceX has filed for a proposal to expand their Roberts road site at Cape Canaveral see here and here

NSF

Mary

Nic

LabPadre

[107]
11.07.2022 New raptor work platform unfolded and refolded early morning

OLM covers delivered to launch site (16) B7 worked on inside

OLIT weather station has been installed on the top

Raptor platform (old) moved to B7/OLM

Old chopstick actuator shipped away

Starfactory work continued

Work on top of Mega bay/high bay 2 continued

Nosecone cage/test structure moved out of Starbase

B7 Spin Prime test with all 33 engines, resulted in a huge explosion and some damage on B7 engine section and likely OLM; also a small fire developed around the orbital pad while venting and LOX dumping continued; site inspected by several drones

NSF

Mary

Nic

LabPadre

10.07.2022 S24 worked on near the missing row of TPS tiles, new tiles added

LR11000X moved, possibly to protect from potential static fire from S24

A chopstick arm actuator removed for potential upgrades/replacement; later left launch site

B7 engine work continued on via raptor platform and lifts

OLS tank farm venting

OLIT work on its top ahead of installing a weather antenna [ultrasonic anemometer], later installed

CH4 delivery to OLS tank farm

New chopstick actuator delivered to production site, likely to replace the one removed; looks much more robust

Starlink loader (white box) worked on

MSIB issued for testing from July 11–14

NSF

Mary

LabPadre

[108]
09.07.2022 OLM and OLS tank farm venting

PA at 4:35: "Attention at the orbital pad! Pad is now clearing for Thunderbird."; venting at 6am Chopsticks tested (raised, opened, rotated, lowered while enclosing B7); after that, the ship QD moved in place again

S24 inspected; tiles added near fwd flap

B7 work continued

Starfactory work continued

Mega bay/high bay 2 work continued, more scaffolding installed at the top

Raptor platform raised and lowered under B7/OLM

Everyday Astronaut: Starbase Tour with Elon Musk part 4 released

Cape: SpaceX submitted plans to widen the Saturn causeway by 10 feet to be able to roll out larger hardware down the road (e.g. tower segments) Harry Stranger]

FCC filings: Starlink communication during orbital test via multiple terminals mounted on ship and booster Michael Baylor; New flight profile details: booster [B7?] will do either partial return and land in Gulf of Mexico or do a full return with a catch attempt; Ship will reach about 250 km altitued, then powered landing in Pacific Michael Baylor

NSF

Mary

Nic

LabPadre

[109]
08.07.2022 New OLM work platform (raptor platform) moved from production site to launch site; there are side pieces that fold upwards to provide a larger working area

OLS tank farm consumables delivered

B7 work continued

OLM work continued

EDOME test tank moved

Old raptor platform raised and lowered under OLM/B7

Starfactory work continued

Work on a weather station

B5 fwd section spotted

S25 nosecone outside tent 3; TPS tiles have been installed

B8 has been stacked (hidden in mega bay/high bay 2); now fully stacked

B10 fwd dome spotted

Test tank worked on at PPS [?]

Chopsticks and QD arm tested

NSF

Nic

LabPadre

[110]
07.07.2022 B8 bridge crane attached to CH4 tank in mega bay

B7 engine section work continued

Loud venting heard at OLS

OLS tank farm venting

S24 connected to new Pad B QD; disconnected form LR11000X

Booster fwd dome sleeve moved at production site into tent

Ship aft dome section/sleeve in front of tents

B8 stacked in high bay 2/mega bay; CH4 tank lifted (final stacking)

Three Raptor 2 engines delivered, one identified as SN73

B7 ambient proof test; venting from OLS tank farm, OLM and B7 preassure vents [vid 08]

Raptor platform moved under B7/OLM after the test [vid 08]

NSF

Mary

Nic

LabPadre

[111]
06.07.2022 S24 lifted onto SoLS Pad B for more testing; later the transport stand and the two SPMTs moved away [lifted at 6:26, touched down on Pad B at 6:44]

MSIB/NOTMAR issued for testing on 6–7 July

B7 raptor engines worked on; likely shielding installation via raptor platform; later the raptor platform moved away

Barrel section with TPS mounts in front of tent 3, orange tape spotted on it [S25 payload section??]

Work on new building at production site continued

Material delivered

B5 scrapping continued in high bay 2/mega bay

Pressurization trailer spotted

Booster thrust assembly flipped [apparently the thrust puck plus some more additions to one side]

Starfactory work continued

B7 ambient proof tested (no cryo load but venting observed, as well as minor venting at the tank farm), followed by igniter tests

B8 fwd section (13-rings tall CH4 section) moved into mega bay/high bay 2

S25? nosecone with flaps and TPS covers spotted in tent 3 along with two other unfinished nosecones [is it the same as in June 29's video? if so, progress has been extremely fast]

B7 grid fins tested [vid 07]

NSF

Mary

Nic

LabPadre

[112]
05.07.2022 S24 rolled to the launch site

Roll out continued, rolled next to SoLS Pad B; lifting squid connected via LR11000X; hoses disconnected from ship

NSF

Mary

Nic

LabPadre

04.07.2022 S24: Starboard "S24" decal applied, also an X has been added above the communication tiles [vid 05] LabPadre
03.07.2022 S24 tape applied to mask off an area for application of paint! (according to NSF)

Starfactory work continued

B5 remains in mega bay

B7 worked on; both on engine section and near cmn dome section; engine shields being installed via raptor platform

LOX deliveries to OLS tank farm

OLM work continued, some lines vented

OLS tank farm: Shell 2 (original water tank) has some scaffolding installed

OLS berm being worked on

NSF

Mary

LabPadre

[113]
02.07.2022 S24 work continued in high bay 1

B5 scrapping continued, only aft section remaining on stand

Starfactory work continued

Work in and around the new production site building continued

Chopsticks work continued

Earth work at OLS around OLM

OLM work continues, especially on small piping/wiring

B7 work on engine/aft section via raptor platform

Tanker truck to OLS tank farm

NSF

Mary

LabPadre

[114]
01.07.2022 Starlink loader lowered from S24 after being tested

OLS tank farm deliveries of consumables

Raptor platform again under B7 and OLM as work on engine section continued

OLM work continued

Scaffolding on chopstick carriage system

Chopsticks worked on

S24 worked on in high bay 1; payload bay closed again

Crane/SPMT storage site: work on finishing the new building

B5 scrapping continued, fwd section detached

S25 payload section still outside tents

Starlink loader: loading rails extended (!)

NSF

Nic

LabPadre

[115]

June 2022[]

Date Description Source Link
30.06.2022 S24 disconnected from loadspreader in high bay 1

Raptor platform moved away from OLM

Starlink loader (white box) moved from tent 1 to high bay; prepared for lifting in high by 1

B5 cut in half in high bay 2/mega bay

Deliveries to production

B4 prepared for roll back; then left launch site, rolled back to production site; entered rocket garden

OLM work continued; venting seen

OLS tank farm ground piping worked on

Starlink loader (white box) lifted and tested in high bay on S24; payload door opened for that

OLS tank farm/B7 unknown testing with road closure, pad clear and tank farm venting

McGregor: Raptor 2 engine test on vertical test stand NSF]

NSF

Mary

Nic

LabPadre

[116]
29.06.2022 SPMTs moved under B4

OLS tank farm commodities delivered

B7 worked on at the top and in other parts; also worked on inside through LOX access hole

OLM work continued

B7 LOX access hole closed; raptor maintenance platform moved under B7/OLM and work on engine section; later the platform was removed and moved back next to EDOME test tank

OLS tank farm plumbing worked on

Container rigged for moving at launch site

Mytery parts delivered to launch site

Mega bay/high bay 2 work continued

S24 worked on in high bay 1 (still attached to crane)

New style flat dome and 2 ship fwd domes in front of tents and worked on

A loadspreader moved into tent 1

S25 payload section work continued

New nosecone worked on in tent 3, possibly for S25

Work on new production site building continued

Underground pipes laid at production site

B7 tested and vented (no frost or condensation)

Cape: Third OLIT tower segment lifted and installed by LR11350 at LC-39A

NSF

Mary

Nic

LabPadre

[117]
28.06.2022 S24 lifted and moved in high bay 1 [engine installation complete?]

B5 now in mega bay/high bay 2

Barrel section in high bay 1

Starfactory work continued

5-ring barrel section moved to scrap yard

Transfer tube moved around the production site

B5 grid fins reinstalled in the high bay 2/mega bay

S25 payload bay section worked on outside at production site

S24 work continued

B7 worked on at the fwd dome area

B7 venting

B7.1 test tank tested, filled with cryo

NSF Cape Update #10:

-Roberts Rd:

--After the roll out of two OLIT sections, the foot stands returned to the assembly site at roberts road, and were place on the concrete footings again, the new concrete bases for segment 8 and 9 are still not used—Chopsticks and carriage system spotted to the north of starship factory—Third OLIT segment prepared for roll out with scaffolding, stairs and cryo pipes installed [rolled out as of releas-date of this video]; 5th section receives stairs; 7th segment beginning to be built with 3 columns up and some cross beams installed; column for shorter top level (8 or 9) spotted; pipe work continued—Mega bay foundation work continued significantly (panels and rebar fro concrete)

--Starfactory: foundation work ongoing, rebar work likely finished; wiring and conduits worked on

-LC-39A:

--A new LR11000 crane has been raised and lifted the first two segments on to the OLIT base; crane still attached to second segment; place for drawworks being inclosed with walls and roofs—Work ongoing on mysteryous structure being build on the ocatgonal foundations seen a few weeks ago; also, a hexagonal structure was spotted at the old landing pad (potentially related)

NSF

Mary

Nic

LabPadre

[118]
27.06.2022 Raptor maintenance stand removed from under B7/OLM, moved next to the EDOME test tank

Two nosecones an d a payload section in tent 3

S24 has been connected to crane in high bay 1

High bay 2 work continued

B8 methane section spotted in mid bay

S24 lifted in high bay one, likely placed on a stand to allow vacuum raptor installation

Starfactory work continued

B5 rolled to the high bay 2/mega bay; one grid fin removed before entering

Alarm at launch site indicating pad clear ahead of B7 test

B7 ambient/cryo proof test, although no condensation/frost formation on the booster, a lot of venting though from tank farm, OLM and booster [cryo??, likely ambient?]

CAPE: Third tower section of the OLIT at LC-39A rolled out [Spaceflight Now]; Parts for ship QD arm spotted Cullen Desforges

NSF

Mary

Nic

LabPadre

[119]
26.06.2022 Raptor platform under B7/OLM raised, later lowered again; raptor shielding removed for some work on engines, then reinstalled

OLS tank farm venting

Raptor igniters tested again on B7/OLM; several more in the afternoon

Engine shield with label spotted: "Do not use Needs modification grindouts"

Raptor TVC (thrust vecor control) mounts spotted

Worker on OLM controls venting (his hand moves in time with venting on OLM)

S25 payload section attached to crane

OLS tank farm venting a lot

Raptor vacuum engines (3) moved into high bay for installation on S24

NSF

Mary

LabPadre

[120]
25.06.2022 Raptor stand has moved below B7, OLM

B7 igniters tested (not visible, only audible sign)

LR11000X is in front of SoLS Pad B

SoLS tank farm worked on, a part (column or long tank?) moved to the landing pad

Starfactory work continued

SPMT moved near B5

Buckner LR11000 disassembly continued "Bucky"

S24 work continued in high bay 1

Engine shields delivered

Ship load spreader lifted in high bay 1, likely to lift S24 to allow engines to be installed [vid 26]

NSF

Mary

Nic

LabPadre

[121]
24.06.2022 Chopsticks disconnected from booster, lifted, moved aside and lowered; Ship QD extended towards B7 (although stabilising arms haven't been reinstalled yet); booster QD on OLM extended towards B7 very slowly

OLM inspected

Raptor platform moved to OLS [vid 25]

Work on OLS tank farm (cutting or welding) and OLM [vid 25]

MSIB issued for testing on June 27–30

NSF

Mary

Nic

LabPadre

[122]
23.06.2022 OLM was venting a lot, also from QD

OLM work continued next morning, a cable pull has been installed to lift heavy equipments onto it

B7.1 work on top of the structural test stand cap

B7 rolled out from mega bay to launch site after repair work has apparently been completed

LR11000 (Buckner) disassembly at production site continued

Ship payload section being welded in the high bay

Work on the new production site building continued

S25 payload bay section: crane still attached to Starlink dispenser

Mega bay/high bay 2 work continued at the top, the roof has been completed

S24 work in high bay 1 continued

Chopsticks lifted before booster B7 arrived, then B7 moved in between the chopsticks; chopsticks closed and moved into position; lifting preparations started; B7 lifted during the night [footage continues in vid 24]

Raptor 2 RUD on tripod stand at McGregor NSF

Cape: OLIT segment 2 lifted by LR11350 and stacked [Spaceflight Now]

NSF

Mary

Nic

LabPadre

[123]
22.06.2022 Booster QD on OLM has been opened, work on it

OLS tank farm venting

B7.1 Pistons from the structural test stand extended upwards and connected to the ropes from the cap

OLS tank farm worked on; tanker deliveries (LOX and LN2); berm concrete work began

S25 common dome in mid bay; Starlink dispenser installed into S25 nosecone barrel

Starfactory work continued

Booster aft cap delivered

LR11000 crane parts leaving Starbase

Cape: Second OLIT section rolled out to LC-39A; another piece of the chopsticks has been delivered to roberts road facility [Spaceflight Now]

NSF

Nic

LabPadre

[124]
21.06.2022 OLS tank farm venting a lot

Can crusher (structural test stand cap) installed on B7.1, ropes not yet connected at the bottom

OLM legs painted

OLS tank farm LOX delivered

SoLS tank farm CH4 delivered

SoLS Pad B QD work continued

Masonry work on OLS tank farm wall

Buckner LR11000 lowered at production site, possibly to be disassembled and shipped away after mega bay construction

Mega bay/high bay 2 work continued

Mystery object moved at PPS

Starfactory work continued

New building at the production site (near SPMT yard), work on the inside

Cape: OLIT segment 1 lifted by LR11350 crane and installed at LC39-A [Spaceflight Now]

NSF

Mary

Nic

LabPadre

[125]
20.06.2022 High bay 2 work continued, roof soon to be finished

Ship aft dome spotted outside tent, scrubbed later

Starfactory work continued

S24 work in high bay continued

Unknown structure and a container moved at production site

New produciton site building work continued

Ship fwd dome moved into tent

Several deliveries to production site

Two ship nosecones spotted in tent 3

B7.1 being secured to the structural test stand, ropes lowered from the cap

Cape: LR11350 crane raised ahead of stacking the first OLIT segment for LC-39A [Spaceflight Now]

NSF

Mary

Nic

LabPadre

[126]
19.06.2022 B7.1 lifted from transport stand onto structural test stand; the structural test stand cap then was lifted onto the top of B7.1 by LR11000X

OLM covers delivered to launch site

[vid 20]

LabPadre
18.06.2022 Chopsticks tested, lifted and lowered

[vid 20]

OLIT scaffolding installed on the top for potential antenna

Elon Musk: Raptor 2 has about 20% more thrust and 20% less mass, "but focus has been heavily on production rate & reliability"

LabPadre
17.06.2022 New potential load spreader parts delivered (new design)

Steel I beams delivered

OLM work continued

B7.1 is next to B4 at launch site

EDOME test tank worked on

Ship aft dome sleeve spotted in front of tents, possibly for S27

S24 in high bay work continued

Starfactory work continued

Ground work for future expansion

Cladding for new building at production site soon completed

OLS tank farm tanker deliveries

B7.1 work inside and outside

Chopsticks being prepared for stacking operations, parts wrapped up in red covers

New transfer tube part spotted

Tank assembly delivered

Work at the Air separation unit antenna

High bay work continued at the top

Mystery box [add: starlink loader] moved down hwy 4 to tent 1

Elon Musk: First countdown for orbital flight hopefully "next month" [add: yes of course...]

NSF

Mary

Nic

LabPadre

[127]
16.06.2022 Starfactory work continued

Common EDOME spotted at production site

S24 work in high bay continued

B7.1 spotted in high bay

High bay 2 work continued

Ship aft dome sleeve moved out of tents, lead-in ring attached

Deliveries to production site

Ship common dome sleeve moved into tent

Transformers moved to production site

Test stand cap moved to launch site to be installed on a test tank [add: B7.1]

LR11000X moved at launch site

OLM: work on booster QD and other parts

Chopsticks work continued

SoLS Pad B QD work continued; QD port has been wrapped up

Work on top of the EDOME test tank

B7 skinnier chines installed

B7.1 test tank put on a transport stand in high bay 1, then moved to the launch site [vid 17]

Cape update by Greg Scott: Bruckner LR11350 is being assembled; new mystery structure being worked on next to falcon tower (possibly new tank); OLIT sections assembly work continued

NSF

Mary

Nic

LabPadre

[128]
15.06.2022 OLM work continued ahead of planned B7 roll out

Chopsticks work continued, work on the downward facing stabilisation pins and their cameras

OLS earth work

SoLS Pad B QD work continued, earth work nearby

Some work on B4 engine section

Deliveries of pipes? to produciton site

S25 work in mid bay continued

Starfactory work continued

Nosecone part spotted as well as an old payload door prototype

PPS shown near gate A3

Cape, KSC: First OLIT section rolled out to LC-39A

NSF

Mary

Nic

LabPadre

[129]
14.06.2022 SoLS Pad B work on new QD continued

OLM significant work continued, some work inside and around the QD; also on the OLM legs around the new protection covers

Chopsitcks work continued

New equipment delivered to OLS tank farm

Post removed at OLS tank farm, which proved to be quite difficult

Some work or inspection on EDOME test tank

Booster common dome flipped [B9??]

4-ring barrel section moved at production site [B9??]

High bay 2 work continued, roof still not finished

S24 worked on in high bay 1

S25 payload bay section seen in front of tents

Work on the new building/structuer at the SPMT yard continued

Elon Musk: We will have a second Starship stack ready to fly in August and then monthly thereafter [add: no]

NSF

Mary

Nic

LabPadre

[130]
13.06.2022 One Bridge crane worked on in Megabay/High bay 2

Ship aerocover spotted

Booster header tank spotted in front of tents

Gravel moved at PPS

Cladding work on high bay 2 continued, soon to be finished

S25 in mid bay worked on

4-ring barrel section in front of tents

Starfactory work continued

S24 in high bay 1 worked on

SoLS Pad B work on the new QD mount

Concrete pump working at SoLS

Construction work outside the launch site main gate

Booster QD removed from structural test stand at OLS

EDOME test tank still waiting for test

FAA released final PEA: Mitigated FONSI (finding of no significant impact) with around 75 mitigations

NSF

Mary

Nic

LabPadre

[131]
12.06.2022 Umbilicals on structural test stand disassembled, where B7 was cryo tested

OLM work continued

Cladding work on the new structure/building

B7.1 being welded

Starship starlink loader / mystery box worked on

LN2 delivereis to OLS tank farm

Tanker truck deliveries to SoLS tank farm

Dome spotted on welding rig

FAA announcement expected on June 13

Houses moved at the SoLS tank farm

Booster QD on OLM tested

QD arm moved and chopsticks rose as part of a booster lift simulation: Chopsticks simulated grabbing a booster, stabilizer arms and engineering cameras moved closer to monitor the procedure, then moved down again

Two objects moved into the mystery box (vid 13)

NSF

Mary

LabPadre

[132]
11.06.2022 Raptor 2 engine delivered to production site

New building near production site: wall being added

B8 methane tank in high bay

B7 has all 33 engines installed according to Elon Musk; at least one HPU (hydraulic pressure unit) cover installed

White mystery structure spotted in tent 1

High bay 2 work continued

Ballast loaded onto an SPMT

S24 in high bay 1

OLM Booster QD rear hood reinstalled; crane detached

Cape: First parts for chopsticks spotted at roberts road facility Zack Golden

NASA: NASA and SpaceX leadership recently met for an update on Starship, the human landing system (Raptor engines visible)

NSF

Nic

LabPadre

[133]
10.06.2022 B7.1 test tank fwd section moved into high bay 1, stacked onto aft section

I-beams deliverd to production site

Starfactory work continued [Why is there a wall towards the tents?]

S24 worked on in high bay 1

PPS plant worked on, antenna installed [?]

Earth work at PPS

S25 tank section in mid bay

Chopsticks worked on as well as OLM

Concrete work near SoLS pad A: Berm work to SoLS tank farm

Concrete broken up outside fence at launch site main entrance

EDOME test tank at launch site

S27 aft dome barrel section moved to tent 1 (quad)

Parts lifted into white mystery box (possibly a Starlink loader)

Chopsticks tested: lifted

FAA, Cape: Aeronautical study on high bay at the Cape concluded: "determination of no hazard to air navigation"; hight according to document is 325 feet (99m) AGL and 333 feet AMSL FAA

NSF

Mary

Nic

LabPadre

[134]
09.06.2022 High bay 2/megabay cladding work; half of the roof seems to be installed

Starfactory work continued

S25 tank section moved to mid bay (cmn dome and midlox sections)

Booster aft section moved around

Ground work for future expansion

B7.1 aft section moved into high bay 1

S24 lifted off SoLS pad A by LR11000X, put on transport stand; moved back to production site, entered high bay 1

NSF

Mary

Nic

LabPadre

[135]
08.06.2022 Raptor 2 engine moved into mega bay

Beams delivered to production site Quad barrel sleeve moved between fence and tent 1; worked on near tent 1; moved into tent 1

B7.1 cmn dome section as booster fwd dome for a test tank

High bay 2 work continued

Starfactory work continued

New building near production site work continued

EDOME test tank moved to the launch site

LR11000X moved towards S24 at pad A, connected to it; Ship QD panel detached

SoLS pad B worked on, possibly installing a new QD

Cape: SpaceX submitted updated plans for roberts road production area; main factory now 648000 sqft, 136000 sqft larger than in previous plans; confirmation of two high bays, each 32138 sqft Harry Stranger

NSF

Mary

Nic

LabPadre

[136]
07.06.2022 SoLS tank farm LN2? delivery

OLS tank farm many deliveries of LOX/LN2

Boston dynamics dog ZEUS and APOLLO spotted

SoLS earth work continued

B7 in high bay 2: at least one of the chines have been removed

Mystery structure (black column with 4 feet) lifted onto a truck

B7.1 cmn section spotted, being used as a booster fwd dome of a new test tank; crews work on it; later moved

Raptor installation truck spotted

Booster load spreader moved at production site

Starfactory work continued

Structural test stand cap worked on (the one with a tank on top)

S24 cryo proof test #3 at SoLS Pad A, possibly with thrust ram tests; LOX tank fully frosted; CH4 only started later; huge depress vent before loading CH4 continued to top

OLM QD hood extension (rear part) moved back to launch site

NSF Cape Update #9:

-Roberts Road Complex:

--OLIT: No new sections built, but additional work on previous segments; segment 5 (third built, level of QD arm) gets hardware for QD arm; raceway installed on the columns that will be opposite the OLM [couldn't they also be rails for chopsticks??]

--Megabay: concrete poured over rebar; cross bracings seen near tents area—Starfactory: More pile drilling work—Elon Musk render: Megabay entrance will be to the north; starfactory will have two different roof hights

-Pad 29-A:

--OLM: all legs in place—Crane base spotted for crane that will stack OLIT—OLIT: Remaining concrete work appears to be done; work continues on future location for drawworks on opposite side of OLM—GSE line covers spotted near the pad—Octagonal pad work continued; purpose still unknown

NSF

Mary

Nic

LabPadre

[137]
06.06.2022 Mystery box moved in front of tent 3

S25? payload section / nc barrel in front of tents

HVAC systems delivered on a flatbet

Starfactory work continued, more beams added towards southwest

Old test tanks and SN16 aft section at PPS

White mystery box moved again; according to NSF it might be a Starlink Block 2 satellite loader

More beams delivered to production site

LR11000X moved away from pad A ahead of S24 test

S24 cryo proof test #2 at SoLS pad A, possibly including the thurst rams to simulate structural loads on aft dome during lift off (force by engines); LOX tank frosted up to half, followed by CH4 and second half of LOX tanks

NSF

Mary

Nic

LabPadre

[138]
05.06.2022 B8 LOX tank moved from high bay 1 to high bay 2

Video released by Elon Musk:

-B7 and S24 still planned to complete orbital flight test

-Starlink Block 2 will be deployed in pairs of 2 satellites each

-Picture of B7 engine section with Raptor 2 engines and shielding

-Renders of Starbase and Cape production facilities

S24 some TPS tiles replaced (those who fell off during first ambient test)

OLM worked on

SoLS pad B work continued

CH4 delivery to OLS tank farm

SoLS grass vent

New building structure work continued near production site

S25 cmn dome and mid LOX sections in high bay 1

NSF

Mary

LabPadre

[139]
04.06.2022 Nice sunrise

Pad A closed for S24 lifting operations at 07:40 am

S24 aft flaps folded; ship lifted by LR11000X onto SoLS pad A for thrust ram tests; work around aft section; later detached from crane

Starfactory and high bay 2 work continued

S25? Payload bay/nc barrel section spotted; no tiles yet

Work on new building structure continued facing hwy 4 at production site

S25 mid-LOX and common dome sections moved into high bay 1; common dome section stacked onto mid-LOX section

NSF

Mary

Nic

LabPadre

[140]
03.06.2022 Two ring flat dome sleeve lifted into mid bay and stacked onto EDOME section

B7 last grid fin installed

Dome jig spotted in tent

S25 nosecone both fwd flaps installed

Booster QD hood extension at production site

New building structure beginning to be built at production site, columns lifted

OLM booster QD vented as crews were working near it

New booster transport stand work continued

High bay 2 work continued; 3 levels of side wall panneling still missing; roof work has progressed

S25 sections staged outside high bay 1

B8 LOX tank section rotated in high bay

LR11000X picked up a load spreader at SoLS

Ship barrel sleeves in front of tents with TPS tile attachment points

EDOME test tank worked on in mid bay

S24 disconnected from OLS cryo station QD; QD adapter installed [?]

S24 moved to SoLS pad A, attached to LR11000X load spreader

SoLS pad A: Last main Fill/Drain LOX and CH4 pipes attached to QD panel, now complete

Cape: All 6 legs of OLM at 39A now vertical, base completed (William Harwood)

B8 transport stand moved to the build site

B8 LOX tank moved inside high bay 1; placed on new booster transport stand [vid 04]

NSF

Mary

LabPadre

W. Harwood

[141]
02.06.2022 Mystery structure still in tent 1

Two Raptor 2 engines delivered

SN16 scrapping continued

S25 nosecone TPS tiles work continued; fwd flaps installed

Stage assembled for a meeting

Development double barrel sleeve spotted ("This is likely a development section for welding the new dome design")

B7 second grid fin installed, third later this day

OLM booster QD hood extension moved to production site storage area, unknown reason

OLMo work continued

SoLS pad A preparations continued

Starhopper meintenance work

S24 cryo proof test at OLS cryo station; CH4 tank frosted, followed by LOX tank, both tanks fully frosted, detanked, depressed; passed the test according to Elon Musk

FAA: Section 4f of the Environmental Assessment completed today as last big milestone; release still target for June 13

NSF

Mary

Nic

LabPadre

[142]
01.06.2022 Road closed at 17:24, pad cleared at 17:56 for potential testing; farm venting at 17:57; road opened at around 22:00

OLS tank farm: several deliveries of LOX/LN2 and CH4; work continued SoLS tank farm: LN2 delivered

OLM work continued; work on booster QD hood

S24 repair work continued and completed

High bay 2 work continued

B8 LOX tank stacked on engine section in high bay 1; after being stacked and destacked twice

SN16 disassembly continued; aft section rolled to scrap yard

Booster methane barrel section (triple) spotted

S25 nosecone TPS tiles work continued

Mystery box work continued

Ship transfer tube loaded onto a truck near gate B3

Starfactory work continued

B7 raptor engine installation continued; first grid fin installed

NSF

Mary

Nic

LabPadre

[143]

May 2022[]

Date Description Source Link
31.05.2022 S25 nosecone TPS tiles work in tent 3 continued

Mystery box worked on

SN16 worked on at top of tank section; scrapping

Fwd dome (flat design) moved into tent

Old booster header tank repurposed as some sort of horizontal storage tank [?]

Starfactory work continued

B8 engine section moved from tent to high bay (header tank visible)

S25 nosecone moved out of tent 3, tiles work continued

S24 pressurized, dents visibly disappeared

OLM work continued; inside of legs have received new shielding; work on booster QD and hood continued

SoLS Pad B upgrade work continued

S25? fwd dome section (sleeved) spotted

B7 disconnected from bridge crane in high bay 2 ahead of a potential roll out; engine installation continued

Standard TFR updated for June

Faa: Release of EA delayed; intended new date of issuing now June 13 (Christian Davenport)

NSF

Mary

Nic

LabPadre

[144]
30.05.2022 [No video]

S24 new pipe with expansion loops lifted into payload bay hatch; additional parts of raceway aerocover added

29.05.2022 OLM and booster QD work continued

S24: crews worked on raceway; reparations continued; fwd aerocover not yet installed at aft flap

SoLS Pad B old ship QD has been removed

Ship common dome spotted with TPS tiles installed

Ship flap aerocover spotted

Dome with new design spotted in front of tents next to a ship transfer tube (still wraped up)

S25 nosecone TPS tiles work continued in tent 3

LCH4 delivered to OLS tank farm

NSF

Mary

LabPadre

[145]
28.05.2022 High bay 2/Megabay roof contstruction continued

Booster aft dome section has been sleeved recently [?]

Mystery structure spotted in tent 1

S25? nosecone TPS tiles work in tent 3 continued

Raptor engines SN62 and SN77 delivered to production site

Booster fwd tank #2 spotted [B8/B9, barely readable]

S24 reparation works continued throughout the day on the section around the fwd at OLS cryo site

OLM work continued; modifications on QD hood

NSF

Nic

LabPadre

[146]
27.05.2022 QD arm rotated

OLS tank farm venting a lot

S25 nosecone in tent 3 work has progressed

EDOME barrel outside tents, hooked to crane

SN16 aft flap removed

Booster methane sump delivered at gate B3; also a ship thrust puck

High bay 2 roof work continued

S24 ambient proof test, tanks didn't frost up; OLS tank farm and OLM were venting; S24 lost several tiles from nosecone barrel during the test after a loud boom was heard; fwd dome and cmn dome depress vents (new venting locations compared to older ships; ullage vents)

S24 damaged pipe (bent) removed after the testing

Stand moved

Roadway kit for challenging terrain and SPMTs moved (SPMT on SPMT)

Ship QD (on QD arm) retraction test in the evening

NSF

Mary

LabPadre

[147]
26.05.2022 [OLM booster QD hood backside removed during the night]

S24 rolled from high bay 1 to the launch site on SpaceX's SPMTs

S24: three areas of TPS tiles around the stacking welds still missing; six unusual hexagonal tiles on nose's leeward side

S24 moved to OLS cryo station, attached to QD; first ever ambient venting at 16:26 CDT

LOX delivery to OLS tank farm

SoLS tank farm beam work continued

Earth work at the launch site main entrance (Gate D2)

SPMT moved to launch site

Temporary buildings from roof of OLS power bay/comms building relocated and installed near the SoLS tank farm and pads

Work on popellant production plant

Booster transfer pipe section spotted

Crane sections continued to leave the site

High bay 2 roof work continued

Raptor 2 engine SN70 moved into high bay 2/mega bay for installation on B7; R center or R boost equipment still missing

Everyday Astronaut: Release of the second part of Starbase tour (OLS):

-Orbital flight will follow same trajectory as originally released by FCC exhibit

-Booster has a 250t catch weight, goal is 200t; mach 0.5 at start of landing burn; chines will be facing perpendicular to catch arms

-HLS mostly digital work currently; focus is orbital test flight

-Starlink 2.0: 7m size, some already on site, 1.25t weight, only fit in Starship, has higher throughput and useful bits

NSF Cape update #8:

-Roberts Road:

--East end: Hangar X booster transporter empty—Area for upcoming parking space cleared in the north of hangar X

--OLIT 2 segments: 5th and 6th segments (according to construction order which doesn't correspond levels) now structurally complete; 5th segment has an additional floor; legs for 7th sement ready on concrete pad, together with some small beams; legs for 8th and 9th segments onsite

---Cryogenic pipes delivered to the tents area, being prepared for installation on OLIT segments ahead of stacking

---Segments numbered 1-2-5-3-4 (from oldest to newest)

--Mega bay foundations now complete; pile driller moved away—Starfactory foundation work continued; slower than expected—Trees and bushes removed

-Pad 39-A:

--OLM leg installation has started: 3 out of 6 already installed, no elbows yet—OLIT base not progressed; likely teams are waiting for the concrete to cure before pouring the next level

NSF

Mary

Nic

LabPadre

[148]
25.05.2022 High bay 2 stair parts delivered

Stiffener ring rmoved from a stand

Edome barrel (triple) spotted for the first time, likely as part of a new test tank, near gate B3/tent 1; stiffeners and lead-ins

Ship fwd dome cleaned

Jackhammer broke up concrete at production site

B8 worked on in high bay 1, while still being connected to high bay bridge crane

Mystery box work continued

High bay 2 work continued; new kind of roof beams lifted

Starfactory work continued

In place machiening equipment set up in high tent next to high bay 2

More crane and SPMT parts left the site

S25 fwd dome lifted on sleeving stand; sleeved with corresponding triple with circular hole

Scrap coils of stainless steel left production site

OLS tank farm LN2 tank venting

CH4 deliveries to OLS tank farm continued

OLM: work on the QD hoood

Ship cryo station at OLS: QD work continued

EDOME sleeve spotted (aft assembly for new stretch formed dome test tank) Kevin Randolph

OLM booster QD hood backside removed at 11pm

NSF

Mary

Nic

LabPadre

[149]
24.05.2022 Methane deliveries to OLS tank farm; also LN2 and LOX delivered

OLS tank farm GSE plumbing work continued; strainer removed at CH4 site

OLM minor work continued

SoLS pad A: Work and access platform installed at the ship QD

S25 nosecone TPS tiles installation nearly complete in tent 3

B7 work in high bay 2/megabay continued

SN16 aft flaps moved in the wind outside the tents

Triple barrel section with a circular hole (ship fwd dome sleeve) moved into tent 1; moved out again

Raptor 2 engine SN74 delivered

Water pumped away after morning rain

Fagioli SPMT parts left starbase on trucks

NSF

Mary

Nic

LabPadre

[150]
23.05.2022 High bay 2 more roof beams lifted; looks finished now

PPS venting

Starfactory work continued

B8 LOX tank work continued in high bay 1

Crawler crane disassembly started at high bay 2

Mystery box white painting continued

Scrap ring moved

Aft cap transport stand loaded onto a truck

Construction work near the production site; work on a new concrete foundation

SPMT loaded onto a truck (Old red Fagioli)

Structural test stand work continued

Raptor installation platform for OLM is currently next to SoLS pad B

Chopstick work continued

OLM work continued; new black back part [cover extension] of the booster QD cover spotted earlier now installed in the afternoon

NSF

Mary

Nic

LabPadre

[151]
22.05.2022 High bay 2: installation of roof beams continued, soon to be finished

RC scheduled for Monday

Hardware "Tooling" column spotted at production site

New booster transfer stand work continued

OLM booster QD cover attached to crane and moved at launch site; but not yet installed

CH4 deliveries continued to OLS tank farm

Raptor 2 engine SN63 converted into Rboost, moved into mega bay for installation on B7

NSF

Mary

LabPadre

[152]
21.05.2022 OLS tank farm venting as LN2 was delivered

OLS tank farm work continued

Mystery box that has been painted white recently attached to a crane

Office building looking like LC-39A's crew access arm spotted outside after years in Ground Fabrication building

High bay 2 construction continued

SPMTs moved at production site

S24 second aft flap has been installed recently [RGV aerial]

Cape: 3 OLM legs are vertical, 6th OLIT segment under construction Greg Scott

NSF

Mary

Nic

LabPadre

[153]
20.05.2022 OLM work continued; OLS CH4 subcoolers and OLM venting [line cleaning?]

SoLS Pad A preparation work continued; ground work near the pad continued as well

LN2 delivered to SoLS tank farm ahead of possible S24 testing; suborbital tank farm worked on

Starfactory work continued, crews worked on roof beams

B8 still connected to bridge crane in high bay 1

Mystery box being painted white

High bay 2 work continued, e.g. on work platform installation near the top

New booster transport stand work continued

Tent 3: Ship nosecone TPS tiles work continued (possibly S25?)

FAA/SpaceX: Plans for LNG processing plant at launch site cancelled to mitigate impact on local wildlife Bloomberg

NSF

Mary

LabPadre

[154]
19.05.2022 Deliveries to launch site

CH4 delivered to OLS tank farm

Chopsticks work continued

SoLS Pad A preparation work continued

Two new Raptor 2 engines delivered: SN63 identified

B8 methane transfer tube lifted into LOX tank

New stand parts delivered to production site

B7 work in high bay 2 continued

Starfactory work continued, more wall panels added

High bay 2 [megabay/widebay] work continued; work platform constructed near the top

NSF

Mary

Nic

LabPadre

[155]
18.05.2022 OLM, OLIT, chopsticks worked on a lot

LOX, CH4 deliveries to OLS tank farm; resumption of CH4 delivery might indicate static fire testing to start soon (first delivery since installation of the new CH4 tanks)

Concrete work at LOX offload station at OLS tank farm

SoLS tank farm berm worked on

OLS ship cryo station QD work continued

LR11000X inspected

Ship transfer tube delivered to production site

Ship mid-LOX section spotted with installed TPS tiles

Raptor engine moved into high bay for installation on B7; antoher one moved from the high bay 2 to tent 1

High bay 2 construction work continued

Starfactory work continued; work on the roof

Intermodal container moved

High bay 1 bridge crane connected to B8 LOX tank section

Load spreader moved to production site

Tank failed at McGregor NSF

NSF

Mary

Nic

LabPadre

[156]
17.05.2022 High bay 2: roofing panels/beams lifted; wall work continued

Booster common dome lifted

SN16 tank section left high bay 2, moved towards mid bay

S24 and B8 worked on in high bay 1

Starfactory work continued

Raptor 2 engines SN21, SN24, SN46, moved into high bay 2 for installation on B7

New parts for OLM delivered to launch site; booster QD-backside cover (covering the flexible cryo lines), other angular parts

OLIT and chopsticks work continued

OLS Cryo station ship QD worked on

NASA, HLS: Cryo propellant transfer test slated for no later than fiscal year 2023

NSF

Mary

Nic

LabPadre

[157]
16.05.2022 Chopsticks worked on

New SPMT delivered

Structural test stand work continued

Ship cryo station at OLS,work on QD

QD arm work continued

OLM work continued

Repair work at gate D2 (Launch site main entrance), concrete opened up

New gate installed at launch site (next to the tank farm wall and offloading station)

High bay 2 work continued

Rvac engine boxes spotted at the production site

SN16 flaps removed, quite ruggedly, nosecone scrapping continued; flaps loaded onto a flatbed

S24 aft flap installed

B7 worked on in high bay 2/mega bay

Raptor vacuum engine boxes left Boca Chica (one labelled SN 1)

Fuel storage tanks delivered (Enviro Cube)

High bay 1/mega bay: more roof beams lifted

Work on nosecones in tent 3, likely for S25 and S26 [vid 17]

Cape: First OLM leg vertical at LC-39A

NSF

Mary

Nic

LabPadre

[158]
15.05.2022 Raptor engines visible unter SN20/S20

S25 or S26 Mid-LOX section spotted

Stiffener ring removed from a 5-ring barrel section

S24 worked on in high bay 1

B8 LOX section (16 rings tall) moved into high bay 1, attached to bridge crane to resume stacking operations; stacked onto another 4-ring section (LOX tank now 20 out of 24 rings tall)

SN16 nosecone still sitting in front of bays

Counterweights removed from an SPMT

Chopsticks and OLM work continued

NSF

Mary

LabPadre

[159]
14.05.2022 B7 rolled back to the production site, entered gate B2 and then high bay 2 [filmed from gate B6], possibly for Raptor engine installation; later attached to bridge crane

SN16 nosecone sitting in front of bays, moved to the scrapyard

High bay 2 [megabay according to Musk/widebay] wall panelling work continued

Raptor 2 engines delivered from McGregor, SN66 identified

OLM worked on

Elon Musk Starbase tour with Everyday Astronaut, Part 1 released; key take aways:

-First orbital flight by B7 and S24, likely with Starlink satellites in an electrically actuated dispenser

-Ullage gas thrusters on both ship and booster

-Thrust to weight ratio of full stack will be around 1.5 at lift off

-Ship fwd flaps will need to be improved massively, possibly even removing them or moving them more to the leeward side

-No more suborbital flights

-B7 120 degrees chines layout make sense due to pressure [?]; B7 will have lighter grid fins

-Future boosters will have less grid fins, not more than 3

-Megabay [high bay 2] supports up to 12 work stations, is 30–40 ft taller than high bay 1 and has 4x usable area

NSF

Mary

Nic

LabPadre

[160]
13.05.2022 Booster QD on OLM is retracted

B7 lifted from OLM onto transport stand by LR11000X

SoLS Pad A: Ship QD added

SoLS tank farm vented slightly

SN16 tank section still in high bay 2

Starfactory wall installation continued

New booster transport stand work continued

S25 flaps spotted

Booster load spreader picked up by high bay 2 bridge crane for first time

NSF

Mary

LabPadre

[161]
12.05.2022 Chopsticks work continued

OLM/B7 work on "engine" section

B7 inspection

LN2 delivery to OLS tank farm

Structural test stand worked on

SoLS Pad A preparation work continued

Ground work at SoLS

LR11000X moved to OLS, OLM, connected to B7 via loadspreader

OLM booster QD hood painted black

SN20/S20 has replaced SN16 at the rocket garden

Work on mystery structure at production site

Stafactory siding installation continued, move beams added

S24 worked on in high bay 1

High bay 2 work continued, small roof beams installation began (roof frames)

Raptor 2 delivered (unknown serial number)

Delivery, packed in white sheets and labelled "UTF 12CCJ/F/E", to production site

Booster transport stand moved to OLM

SN16 nosecone has been removed from rest in high bay 2, sits now in front of tent [vid 13]

NSF

Mary

Nic

LabPadre

[162]
11.05.2022 SN20/S20 rolled back from launch site to production site, to rocket garden; lifting eyes have been removed last night

S21 aft section scrapped, parts cut off

Starfactory work continued, wall panels installation continued

S24 has been unhooked from bridge crane in high bay 1, scaffolding for payload bay stacking has been removed, work continued

High bay 2 work continued, more wall panels installed, back side now fully covered; rooftop beams installed (for the upper roof, lower roof has been fully installed)

SN16 attached to high bay 2 bridge crane, while its stand rolled back to rocket garden through gate A3

Delivery in black boxes (labelled with SN4 and SN1 ?) to production site

S26 aft dome spotted in front of tents; S26 quad for payload bay/nosecone barrel section spotted (it's still a quad, extra ring will be welded on top inside the high bay), moved into high bay 1; S26 aft dome sleeve (4-ring) spotted outside the tents, flipped

Nosecone in tent 3 TPS tile installation picking up pace

S26 aft dome lifted onto sleeving stand

Ground work at PPS continued

B7/OLM QD reconnected after it has been disconnected

B7 cryo proof test on OLM, both tanks fully frosted up; first ever booster/OLM QD retraction test under cryogenic conditions

NSF Cape Update #7:

-Roberts road:

--Hangar X: New B1064 Falcon heavy rocket side booster spotted; fairing delivered for refurbishment; new parking area north of it; concrete pathways construction started on the east side, indicating no further extension of the building—Starfactory: Two new tents assembled to support construction; concrete spread footings nearly completed—High bays: Pile drillers began to work on the foundations, rebar already being added—OLIT: Fifth section assembly began, three columns added; sixth section starting soon with feet placed, seventh section might start soon as well—Entrance road completed

Pad 39A:

--Second tent now completed—OLIT base is being expanded with walls coming out to the west and away from the OLM, possibly for draw works, however, the design is certainly different to Starbase where the extension is made of steel beams instead of concrete walls—OLM: Rebars coming out of ground for the legs, the six legs have been spotted north of it—Octagonal clearing of a new foundation spotted west of the OLIT and OLM, unknown purpose

NSF

Mary

Nic

LabPadre

[163]
10.05.2022 B7 LOX hatch reopened, worked inside tank; work on OLM/booster QD

Chopsticks work continued

OLIT plumbing lifted and installed

SoLS Pad A preparation work continued (likely

for S24 test campaign)

Work on booster transport stand

Starfactory first two side covering panels installed

SN16 moved to high bay 2 [NSF called it megabay] by two SPMTs after lifting eyes have been installed last night; potentially for som testing; later connected to bridge crane (fiirst heavy lift in mega bay)

B8 LOX tank worked on

S24 still hooked to bridge crane in high bay 1; welding work continued

High bay work continued on top levels

New nosecone in tent 3: Thermal blankets applied

Black boxes delivered to production site

S24 removed from turntable in high bay, welding complete

Elon Musk: hopes for first orbital attempt in the summer and an uncrewed mission to Mars in 3 to 5 years

Raptor 2 engine RUD on horizontal stand at McGregor NFS

NSF

Mary

Nic

LabPadre

Sheetz

[164]
09.05.2022 Construction work at PPS near rocket garden, with excavators

B8 aft tank worked on the outside

S24 worked on in high bay 1, rotated on turntable for welding; payload door visible

Starfactory work continued

High bay 2: work continued, more wall panels added at the back side

Ship leg skirt section with can cursher cap on top of it spotted at PPS

SPMTs moved under SN16 at rocket garden

B5 stand worked on

Raptor installation platform near the OLM

B7 cryo proof test on OLM; both tank fully frosted up befor detanking

Raptor 2 engine RUD at McGregor vertical test stand NSF

NSF

Mary

Nic

LabPadre

[165]
08.05.2022 B7 work on OLM continued through LOX tank access hole; work on a raceway

QD arm work continued

B8 LOX tank section still waiting outside bay area

Nosecone and barrel section worked on in tent 3

S24 tank section worked on in high bay, Nosecone (with barrel section and fwd dome section) stacked onto tank section

FCC approval for communication for orbital test renewed (May 21 - November 21)

Raptor installation platform moved to OLM [vid 09]

NSF

Mary

LabPadre

[166]
07.05.2022 S24 tank section moved from mid bay into high bay 1 [enough space now as B7 has left]

B7 worked on at OLM; work through LOX access hatch while still hooked to LR11000X; OLM QD hood opened, extended, QD connected; later crane disconnected from B7 (16:30)

Pump truck worked at SoLS [vacuum truck, "hydroexcavation" truck, normally used to remove loose dirt, gravel... according to Graves/Pearson]

LR11000X moved away from OLS

S24 tank section lifted in high bay 1; moved around

Starfactory construction work continued

Part of a nosecone spotted outside tent 3

NSF

Nic

LabPadre

[167]
06.05.2022 B7 moved out high bay 1, prepared for roll out (delayed a bit due to lighning); rolled back shortly

SoLS preparation work continued

Starfactory work continued

S24 nosecone (stacked on barrel section) seen high bay 1

High bay 2 construction work continued

B7 rolled out to the launch site for the second time [despite speculation after transfer tube failure] (no grid fins installed yet)

B7 lifted onto OLM by LR11000X, after chopsticks moved out of the way

FAA: Section 106 review completed today

Florida: All six legs for OLM delivered to pad, assembly of 5th OLIT section began, new concrete base under construction at LC39-A (Stranger)

NSF

Mary

Nic

LabPadre

Stranger

[168]
05.05.2022 High bay 2 construction continued, more beams lifted and installed

Stairs production behind high bay 1 continued

B7 repair work in high bay 1 continued

New flat dome design shown

Booster aft cap assembly lifted and moved into tent 1

New booster transport stand work continued

Front end loader worked at PPS

Drone flight at rocket garden/ PPS (inspections/drone test?)

Starfactory work continued, more roof beams installed

S24 tank section still waiting in mid bay

Mystery box (the rusty one near Gate B4) attached to crane and lifted

Counterweights moved to production site by SPMT, possibly for B7 roll out in the near future

LR11000X moved with load spreader, likely for future B7 lift

Booster QD on OLM worked on

Chopsticks worked on

Unknown item lifted over launch site wall at SoLS

OLM vented, possibly Raptor QD vents [?]

NSF

Mary

Nic

LabPadre

[169]
04.05.2022 OLM work continued; work with a special load spreader

Ship QD arm work continued

SoLS Pad A: all 6 thrust rams have been installed

SoLS concrete work continued

Wide bay 2 work continued

Mystery box work continued; another mystery box shown as well

Starfactory work continued

Air conditioner unit delivered

SPMTs being rearranged

NSF

Mary

Nic

LabPadre

2UA
03.05.2022 Work at the top of high bay 2 during night

B7 work in high bay 1 continued

High bay 2: wall panels missing on two levels at the back and north side, 5 levels missing on the south side; work continued

Starfactory work continued

New booster transport stand work continued, securing clamps being added

OLM work continued

Rvac thrust rams/simulators installation on SoLS pad A

LN2 delivery to OLS tank farm

Structural test stand work continued

US Fish & Wildlife Service documents sent to CNBC via FOIA request, biological and conference opinion based on the review of the effects of the proposed Starship program

NSF

Mary

Nic

LabPadre

[170]
02.05.2022 SoLS Pad A work continued to prepare it for testing; concrete work near it

New Ship QD plate added to the new QD stand at Starship cryo station next to OLIT

Structural test stand welding work

GSE plumbing cleaned

Excavator working at SoLS

GSE plumbing moved on flatbed at launch site

Ship QD arm work continued

New GSE hoses delivered to launch site

Starfactroy construction work continued, more beams added

Faro vantage laser tracker for precise construction spotted

More Appleton crane parts moved to PPS

Delivery of new unknown structure to production site

New scissor lifts spotted at production site

NSF

Mary

Nic

LabPadre

[171]
01.05.2022 Chopsticks worked on

Helium containers are at the OLS tank farm

S24 and B7 worked on in high bay 1

Appleton Marine crane parts moved to PPS; possibly to leave Starbase

LN2 and LOX deliveries to OLS tank farm

OLM work continued

NSF

Mary

LabPadre

[172]

April 2022[]

Date Description Source Link
30.04.2022 Ship QD arm work continued after the new QD has been installed

S24 still attached to high bay bridge crane

Booster aft cap assembly shown

High bay 2 [ex widebay] work continued

S21 scrapping continued

Starfactory work continued

NSF

Nic

LabPadre

[173]
29.04.2022 QD arm, new ship QD installation continued; detached from LR11000X

B7 work in high bay 1 continued

S24 stacking preparations continued; nosecone stacked on 3-ring fwd section (first time in this order)

Starfactory work continued

Large hardware delivered to production site near the new tent

Astro pak machine (for metal surface treatment) delivered

Transport stand moved on SPMT

Rvac thrust simulators have now been assembled

OLS tank farm venting from LN2 tank

Air conditioners delivered to production site

Road closed at 17:14 for unknown reason, opened at 17:52

Chopsticks: diagonal braces at the stabilisation extensions added again

First OLM water deluge system test at 09:00:33 pm [vid 30]

FAA: PEA Endangered species act consultation completed, Section 106 review pushed back to May 6; PEA delayed to NET May 31

Regular ground TFR updated for May 2022

NSF

Mary

LabPadre

Starship Gazer

[174]
28.04.2022 Ship Raptor vacuum thrust rams preparation work at launch site

Ship QD with updated design arrived at launch site; installation on QD arm

Workers on beam sculpture at PPS

High bay 2 [ex wide bay] work continued

S24 nosecone attached to bridge crane in high bay 1

Starfactory work continued

S21 scrapped section at PPS

Booster aft cap assembly

Dome parts delivered

Raptor 2 engine SN45 delivered

NSF

Mary

Nic

LabPadre

[175]
27.04.2022 Tent 3: several nosecones worked on; polished

High bay 2 [ex wide bay] work continued, more beams lifted; bridge crane shown

B7 work continued in high bay 1

Starfactory work continued

S21 remains moved to PPS

Road work next to rocket garden continued

Mystery box work continued

New booster transport stand work continued

Field machining equipment arrived at production site "In-Place Machining"

Stairs and other parts delivered

SoLS Pad A work continued, e.g. on additional structure

B4 with old Raptor 1 engines shown

QD arm overhaul continued; LR11000X moved to it, parts lifted onto it

OLM work continued

Redesigned grid fins spotted [RGV]

High bay 2 bridge cranes tested for first time at 22:55

NSF

Mary

Nic

LabPadre

[176]
26.04.2022 Chopsticks: part of stabilizer arms removed

SoLS Pad A installation of thrust simulation equipment continued; Rvac thrust simulators and stands near it OLS tank farm: more plumbing being installed at the CH4 pump site; LOX and LN2 deliveries

Raptor van arrived at Starbase, delivered one new lego themed engine, two trucked away, one missing its head

High bay 2 [wide bay] work continued

S24 fwd dome section (fully tiled) moved from tent 3 to high bay for future stacking; lifted [likely placed on a new stand]

Smooth fwd dome outside dome

B8 fwd section seen in mid bay

High bay 2 [wide bay]; stairs lifted into it

Elon Musk: Raptor 2 engines assembled in tent at starbase, 230 tons of force each

McGregor: Long duration Raptor 2 test on vertical test stand [NSF]

NSF

Mary

Nic

LabPadre

[177]
25.04.2022 OLM and chopsticks worked on

SoLS Pad A work continued

Structural test stand worked on

OLS tank farm plumbing work continued at pumping area

CH4 deliveries to OLS tank farm

High bay 2 (wide bay) work continued, work platform removed

Starfactory work continued, more beams added

Curved stand parts delivered

B7 disconnected from bridge crane in high bay; moved into the corner

B8 LOX tank worked outside

Groundwork near the Rocket Garden

High bay 1: Work on some supporting beams

S24 nosecone spotted in high bay

OLM raptor QD tested at 18:06

Cylindrical bases of RVac thrust simulators delivered to launch site for S24 testing?

NSF

Mary

Nic

LabPadre

[178]
24.04.2022 SoLS Pad A work continued for preparing testing; new ship QD frame installed at around 10:45

QD arm work continued

OLS tank farm work continued, plumbing installed

New transfer tubes for booster spotted

B7 worked on at high bay; transfer tube possibly being repaired; hydraulic power unit shown; at 17:16, replacement downcomer segments lifted into B7

Mystery box at production site

Deliveries to production site, unknown parts, dome segments

Work on new booster stand

FAA: PEA Section 106 review pushed back to 29 April

NSF

Mary

Nic LabPadre

[179]
23.04.2022 B7 worked on in high bay; leaked picture from inside LOX tank shows transfer tube scrunched

New transfer tube for unknown booster delivered

Old cargo door prototype shown

Work on new ship nosecone in tent 3

OLM work continued

SoLS pad A work continued, brown metal part lifted and installed

Chopsticks tested, raised and lowered [vid 24]

NSF

Nic

LabPadre

[180]
22.04.2022 Two smooth? nosecones in tent 3

Scrap dome in front of tents

Booster aft section (sleeved) prepared to flip; later flipped; great views from the inside of aft section with plumbing

New transport stand [again not much shown]

B7 in high bay: chine has been opened up

Road work in front of prdouction site

StarFactory work continued

Wide bay: Work platform lowered

Black Mystery box spotted at production site, connected to a crane

S24 tank section worked on in mid bay

Load spreader disconnected from S24 nosecone

SoLS concrete work

OLS: Work continued on GSE piping

Bystronic laser cutter delivered to production site

Parts for a new stand? delivered

B8? thrust section flipped

NSF

Mary

LabPadre

[181]
21.04.2022 Three new Raptor 2 engines delivered, lego themed; RSN51 identified

FCC document: Wide bay called "High Bay 2"

Booster common dome sleeve moved

Ship load spreader moved at production site

Booster transport stand work continued at launch? site

Concrete work at production site entrance (Gate B2)

S21 at scrap yard; TPS tiles and white blanket torn off

Work on new stand continued

Starfactory production building work continued [name has been confirmed by label spotted on beams]

Grey turbine like parts delivered

SPMT moved weights to production site

Three Rvac thrust simulators moved to launch site, offloaded near SoLS Pad A and installed in the pad

SoLS: Berm under construction!

OLM work continued

OLIT: Work on Chopsticks rail

NSF

Mary

Nic

LabPadre

[182]
20.04.2022 LN2 tanker trucks at PPS, venting

Ground fabrication building shown

Smooth nosecone spotted in tent

B7 worked on in high bay

Starship factory starfactory girders installed

Old cargo door prototype still around at production site

Starship thrust simulator moved to SoLS; fit checks on Pad A; removed again

Grove GMK 1550 boom element delivered

New booster thrust puck delivered

Ship thrust simulator lifted again into Pad A [vid 21]

NSF Cape Update #6:

-Roberts road:

--Hangar X: New Fence splitting the offload area into two parts, one likely for fairing half delivery/refurbishment/roll out; More material for interior—Road to north paved for increase in activity—4 OLIT segments prepared, 3rd and 4th segment received parts for central elevator truss; feet for 5th segment prepared; more feet ready—Starfactory: Construction starting, cut-outs for concretes spread footings visible—Clearing for high bays continued, access road construction started between bay area and starfactory area—Retention pond being filled

-Pad 39A:

--Cocnrete work on OLIT base continued, first stage complete; work on the two back walls, that will hold the draw work system; panels removed—Foundations for the six OLM legs appear to being built up to ground level after earth work last week—New white tent added in the south; frame for a second tent next to it—Work on upgrading hydrogen sphere continued

FCC: Official name for wide/mega bay is high bay 2

NSF

Nic

LabPadre

[183]
19.04.2022 B7 worked on in high bay, especially aft section

Wide bay work continued [according to new official documents called wide bay 2]

New production tent work continued

Starfactory work continued, first horizontal beam installed

Raptor 2s engine SN42 delivered

Structural test stand QD worked on

OLIT new plumbing lifted by LR11000X

NSF

Mary

Nic

LabPadre

[184]
18.04.2022 B7 prepared for lifting, transport stand prepared, lifted by LR11000X and placed onto transport stand (alignment pin not used); load spreader and crane disconnected from B7; rolled back to production site (reason yet unknown)

B8 LOX tank moved within high bay by bridge crane; then moved out of high bay, likely to make place for B7

Construction of new factory building that will replace the production tents (often referred to as "Starfactory") continued with first beams being placed

Dismantling of a container back wall at production site near gate B3

Wide bay work continued

New production tent work continued; first awnings added

B7 moved into high bay; attached to bridge crane

NSF

Mary

Nic

LabPadre

[185]
17.04.2022 OLM raceway covers installation continued

B7 umbilical disconnected ahead of possibly lifting it off the structural test stand

New mystery structure [spotted yesterday] now delivered to launch site

Nosecone in tent 3 has alignment jig attached [S25?]

B8 aft #4 tank section (4-ring, part of LOX tank) prepared for lifting in front of high bay; lifted and placed on a stand; LOX tank moved within high bay, lifted by bridge crane and stacked onto aft #4 section (LOX tank now 16 rings tall)

Cape: OLM foundations visible on satellite imagery Harry Stranger

NSF

Mary

LabPadre

[186]
16.04.2022 Crane counterweighs transported by SPMT

S21 scrapping continued

New tent construction continued

B7 connected to LR11000X

Tank trucks deliveries to OLS tank farm

Rusty mystery structure delivered

Ground work for possible future starfactory shown

Old methane theader tank design for booster spotted at PPS

Nosecone in tent 3 being prepared for aerosurfaces

NSF

Nic

Mary

LabPadre

[187]
15.04.2022 B8 LOX tank stacked: cmn dome and aft #2 sections stacked onto aft #3 section (now 12/24 rings tall)

New booster stand workded on

Wide bay work during the night (welding?)

S21 tank section finally being scrapped; tank section cut off thrust section

Coil of stainless steel delivered

Work on new tent behind wide bay continued

LR11000X moved to B7, load spreader still attached

B4 transport stand worked on

B7 aft section worked on with an unknown orange part of equipment

Columns for starfactory have gone up

NSF

Mary

LabPadre

[188]
14.04.2022 B8 methane tank section rolled out and moved into mid bay again; B8 LOX section moved out of mid bay

PPS earth and concrete work near entrance to rocket garden

B5 stand and aft section worked on

Unknown part transported by SPMT

Wide bay work continued

B8 common dome and aft #2 section outside high bay (8 rings tall stack); moved into high bay later

Old COPV aerocover seen at production site

S24 tank section worked on in mid bay

New flat dome placed on sleeving stand (the third one made overall, according to NSF still a pathfinder); 2-ring sleeve sleeved on dome

New tent going up at production site

Coil of stainless steel moved

B7 work on QD area

B7 transport stand (with alignment pins) placed on two SPMTs

B7 cryo proof test on structural test stand, possibly also hydraulic thrust test; ice formed on both tanks; in the second round, LOX tank got fully frosty; during this test, the CH4 transfer tube likely collapsed or was damaged

NSF

Nic

LabPadre

[189]
13.04.2022 Nosecone in tent 3 shown

Workers on high bay bar balcony

High bay construction elevator dismantling continued

Beams delivered to production site, as well as other parts, possibly for wide bay

Original cargo door pathfinder (5-ring nc barrel) shown

Mystery parts (curved boxes with SpaceX logo and windows) delivered to production site, unknown purpose, interior yet to be finished

Tanker trucks deliveries to OLS tank farm, some ventings

B7 some sort of white felt near its aft section

Chopsticks worked on, especially on the stabilisation pin arms

B7 ambient proof test (pneumatic test) on structural test stand late night [vid 14]

NSF

Mary

LabPadre

[190]
12.04.2022 Tanker truck deliveries to OLS tank farm

B5 worked on at PPS, especially near stand and aft section plumbing

S25 5-ring nosecone barrel section spotted in frotn of tent

New flat dome got rectangular section cut out [pahtfinder?], then moved away (for scrapping); according to NSF it was the second flat dome that was built

New structure beginning to be assembled (rings on pistons?) at build site, unknown purpose

S25 nosecone barrel stiffener removed, then moved into wind break (low bay)

Old cargo door pathfinder (5-ring nosecone barrel) with cut in dispenser hole seen at high bay

S24 nosecone still attached to crane in high bay

Third flat dome shown in front tent

S25 aft section spotted in tent

Wide bay work continued, more beams lifted into place on top level

High bay elevator removal work continued

Hwy 4 work next to production stie continued

Deliveries to production site

Wall building work at production site next to cate B3 continued

Payload bay pathfinder rolled into high bay (spotted after a long time)

B7 ambient pressure test, (inspected by bird), tank farm active; pressure release through all vents at common and fwd dome

NSF

Mary

LabPadre

[191]
11.04.2022 OLM work continued, parts lifted onto it

B7 work around QD as preparation for testing

OLS tank farm deliveries by tanker trucks

B4 transport stand worked on

Earth work at SoLS pad B near SN20/S20

Hwy 4 road work next to production site continued

Wide bay work continued

Wall building work continued at production! site with sun pannel installation

NSF Cape update #5:

-Roberts road—Hangar X: exterior walls to extensions completed, concrete work progressed; northern wall now completely pannelled with glass; delivery area complete with large concrete pad; door possibly for fairing halves—OLIT progression: third and fourth sections being built deep dive into this by Zack Golden, concrete foundations for four more sections nearly complete—Starship Factory: Pile drilling operations likely complete; ground clearing underway for possible high/wide bay—Retention pond excavations continued on western side

-Pad 39 A:

--Concrete work on OLIT base has begun, still some rebar seen—Work on old hydrogen storage sphere, possibly for use with LCH4, subcoolers have been installed next to it [2 out of 4!!]

--LOX subcoolers spotted on the opposite side of the complex (where previous starship OLM was planned and partially built in 2019 and removed in October 2020)

NSF

Mary

LabPadre

[192]
10.04.2022 Tank trucker deliveries to OLS tank farm

B7 testing preparation work continued via work platform and access hole, GSE lines connected to QD plate

Booster methane transfer tube delivered, unloaded

Wide bay work continued

New smaller dome spotted (flat dome)

NSF

Mary

LabPadre

[193]
09.04.2022 S24 nosecone attached to high bay bridge crane, stacked onto payload section [nc barrel section]

B7 detached from LR11000X, preparations for testing on structural test stand, hooked up to GSE; work platform erected near it

SN20/S20 all 4 flight recorders removed, two before the move to SoLS pad B, two after the move

NSF

Mary

LabPadre

see below
08.04.2022 S24 lifted in high bay by bridge crane [stacking?], later tank section left high bay towards mid bay

S24 nosecone detached from crane in front of ten 3, later moved to high bay

Booster load spreader attached to LR11000X

B7 attached to LR11000X, QD retracted, destacked from OLM and placed onto structural test stand [ex can crusher]

Tracking station tracked the Ax-1 mission [Axiom]

High bay construction elevator removed as a permanent elevator has been installed inside the high bay

S24 worked on in mid bay, CH4 transfer tube lifted and installed; payload section [nosecone barrel section] moved to high bay via hwy 4

McGregor: Raptor Vacuum Test

NSF

Mary

LabPadre

[194]
07.04.2022 OLM work continued, new lines added

Hydraulic gantry assembled over structural test stand at OLS to lift it off the steel legs; after lift taken down

Launch site wall work continued, new wall panels added

S24 nosecone work continued

Ship transfer tube spotted at launch site

New crane tracks delivered to production site/PPS, old ones moved away

Domes moved to scrap yard [one with new design?]

Wide bay construction work continued

QD arm retracted and chopsticks lifted during a test, rotated at the top

SN20/S20 moved next to SoLS pad B, reason unknown

LR11000X picked up load spreader, moved to OLM for potential B7 lift

Cape: Three columns of third OLIT segment for LC-39A now vertical Kyle Montgomery

NSF

Mary

LabPadre

[195]
06.04.2022 B7/OLM worked on; LOX tank hatch installed on B7

S20 worked on [small aerocovers removed]

Deliveries to launch site

[B7] Booster transport stand work continued, especially on alignment pin

Launch site wall work continued, see through panels and some beams removed

GSE plumbing removed and lowered from OLIT, new GSE plumbing delivered and lifted on OLIT

Hydraulig gantry parts delivered to launch site [what for?]

Booster header tank loaded onto a truck

Ship thrust puck hoisted (pipes already installed)

Robotic wielder spotted in high bay

Wide bay work continued, more beams lifted, roof construction has started (not on the very top)

Hwy 4 road work next to starbase sign

Ship QD arm disconnect moved back to the launch site, close up showing the details of pins, connections, and cameras on the QD plate

Foundation work at rocket garden

S24 nosecone TPS tiles work continued

Tent 3 S24 fwd dome section

B8 LOX tank has been moved into mid bay recently [RGV aerial]

US Army corps of engineers: Boca Chica site expansion plan application from 2021 has been withdrawn due to lack of documentation from SpaceX

NSF

Mary

Nic

LabPadre

[196]
05.04.2022 S24 aft section removed from B8 aft section after fit check of stage separation system

Fwd dome section spotted in tent 3, likely for S24 [??]

Raptor engine delivered to production site

S24 LOX tank section (midlox and cmn dome) moved from mid bay to high bay, attached to crane

Wide bay construction work continued, more beams lifted into place

Booster header tank domes spotted at production site

Booster aft dome sleeve moved out of tent 1; flipped

Booster aft dome with cap moved onto sleeving stand

[B7] transport stand worked on, especially on the alignment pins; Pins have been removed from B4 stand to B7 stand

Ship QD arm: Ship QD plate and piping attached to LR11000X and removed

Launch site wall building work continued

Chopsticks worked on

S24 sections stacked and welded together in high bay (midlox and cmn dome onto thrust section)

NSF

Mary

Nic

LabPadre

[197]
04.04.2020 Ship aft section moved into tent 3 by a crane (likely S25 aft section)

B7 has been disconnected form LR11000X; briefly hooked to it again and unhooked shortly after; B7 connected to booster QD on OLM

SoLS tank farm LN2 deliveries [Can we expect testing at SoLS to restart soon?]

OLS tank farm: subcoolers active

Alignment pins from B4 transport stand removed and installed on B7 transport stand

LR11000X moved away from OLM and B7

B7 vented from fwd dome vents ahead of cryo proof test

B7 first cryo proof test, both tanks fully frosted up at the nearly same pace (CH4 tank frost reaching the top faster); during the filling process, the cmn dome vents constantly vented for short periods; venting stopped for ~1min, then LOX tank filling continued and reached top after some time; detanking started soon after that; later in the night, RCS cmn dome vents and fwd dome vents depress vented and frost/condensation started to reappear shortly after decreasing fully and final full depress vents

Wide bay construction work continued, more beams lifted; second bridge crane has been installed as well

S24 aft section moved to high bay, and stacked onto B8 fwd section

SPMT rolled down hwy 4

Starship methane transfer tube delivered (with anti-vortex device)

Booster header tank domes delivered to production site

NSF

Mary

Nic

LabPadre

[198]
03.04.2022 OLS tank farm: GSE piping worked on at CH4 site, LN2 tank vented; heat exchanger moved

Common dome section (Scrap, see vid 04) spotted on a transport stand in front of tent 1

S24 nosecone moved out of tent 3; two-three nosecone barrel sections being worked on in tent 3 with TPS tiles being installed [S25, S26... ?]

Booster header tank spotted in tents

B8 work in high bay continued, weld cleaned while the tank got rotated

Wide bay: Bridge crane lifted into place and installed on girders

B7 attached to booster QD on OLM

NSF

Mary

LabPadre

[199]
02.04.2022 Wide bay: Work continued; bridge crane part (white) moved; first bridge crane girder lifted and installed; second bridge crane girder lifted onto the rail and installed, followed by third, SpaceX custom design; fourth girder lifted

B8 common dome section moved in front of high bay, LOX tank vents seen; lifted onto aft #2 section (LOX tank now 8/24 rings tall)

Raptor engine nr 59 spotted in storage

B7 attached to LR11000X, QD hood on OLM closed, B7 lifted onto OLM by LR11000X (not by chopstics as some have expected, and not on structural test stand as others expected), a lot of engine attachment point hardware visible; chopsticks slightly rotated towards booster

B7 transport stand moved from OLP to booster storage area

NSF

Mary

Nic

LabPadre

[200]
01.04.2022 OLIT work continued

Wide bay: More beams lifted into place for roof level; wall work on level 6&7 continued

S24 nosecone TPS tile installation nearing completion

B8 aft tank #2 section (4-ring, no lead-ins) attached to crane and moved into high bay

OLS tank farm LN2 loudspeaker tank vented

B7 work on aft section/transport stand; detached from LR11000X and load spreader (reason unknown)

B7 rolled over to OLM, LR11000X rotated towards B7; Chopsticks turned out of the way; LR11000X attached to B7 at 20:38

NSF

Mary

LabPadre

[201]

March 2022[]

Date Description Source Link
31.03.2022 OLS tank farm deliveries (propellant / LN2)

OLM work continued

B7 rolled out from high bay to launch site during early morning road closure, followed by a flood light car; later attached to LR11000X

B7 work continued around aft section/transport stand ahead of possible lift; according to NSF, the "chines are aerodynamic surfaces that increase the Booster's crossrange when returning to the launch site", they also cover COPVs

SPMT returned to production site

Part of a new booster transport stand delivered to production site

S24 nosecone TPS tiles work continued

Common dome section placed on sleeving stand (already sleeved with a 1.5 ring sleeve!)

Building work next to high bay continued

NSF update on design changes as part of the continues iterative approach on Starship:

-S20 (first complete heat shield) is functionally out of date as it can only be launched on B4 and possibly B5

-B4 first booster with 29 engines, engine shields, aerocovers, grid fins...; but out of date as well

-Naming conventions for barrel sections: Quint, Quad, Triple, Double, Single (according to number of rings, each 6 ft tall)

-Starship (old/new layout): 20 rings + nosecone; aft section (5/4), mid LOX section (4/4), cmn some section (3/4), fwd dome section (4/3), nc barrel section (4/5)

--Aft: ship QD moved from second to third ring, possibly for shorter plumbing or more space for 3 additional Rvac engines; nobs and holes for booster/ship integration reversed: since S22 and B7, holes are on booster (negative side) and nobs on ship (positive side); new aft domes with redesigned thrust puck for Raptor 2s—Mid LOX: same but sits one ring lower—Common dome section: Methane header tank removed (to nosecone); new main LOX tank vents to be the same as ullage thruster vents on booster, possibly also for attitude control and possibly nosecone RCS thruster—Fwd dome section: Shortened, giving one ring to nosecone [tank sizes remain the same, as dome is now welded higher]

--Nc barrel: now quint, possibly to facilitate cargo door manufacturing, first one seen on S24, including dispenser mechanism—Nosecone: 4 to 2 rows of panels; methane header tank to be included; S24 nosecone under construction has two header tank vents and no RCS thrusters—Domes with flatter design—Not yet seen but announced: Fwd flap design, streched tank section, increased raptor engine numbers

-Booster: improvements in order to optimize the dry mass, as well as reduction of landing propellant amount—Thrust section: B3, B4, B5 had three standard 1.8m/6 ft ring; B7 thrust section has four 1.4m/4.5 ft rings, stringers now extended all the way down; B7+ will support Raptor 2 engines (vs B4 V1.5 engines)

--Header tanks: B5 had a long tube tank on the side of the LOX tank; B7 has new design that is located in the middle and encloses the transfer tube (coaxial tank); new transfer tubes with plate that has three holes (likely for providing landing LOX for center 3 engines)

--Pressurization lines: B4, B5 had 4 lines for each tank; B7 only two per tank—Aerosurfaces: B7 has new COPVs arrangement (2 vertical columns instead of horizontal ring); covered by "nominal" sections, forming chines (dual purpose: protect COPVs, additional cross sectional surface area - additional cross range, extra drag and reduced approach velocity

NSF

Mary

Nic

LabPadre

[202]
30.03.2022 OLS tank farm work continued; wall work continued

Three Raptor 2 engines delivered and moved into a production tent

OLS: work on the new fence building continued

OLM work on booster QD

New nosecone barrel section (5-ring) spotted outside tents

Haas VM-6-High-Performance VMC delivered ("This can be used to machine metal parts on site")

3-ring barrel section moved in front of tent 1

B8 CH4 tank stacking continued in high bay; stacked onto fwd section #4, now 13/13 rings tall

NSF

Mary

Nic

LabPadre

[203]
29.03.2022 B7 moved inside high bay, now at its entrance

OLM work continued, also on booster QD

OLS tank farm: LOX delivery; work on new tank farm wall continued rapidly, top covers added at the western segment

SPMT power back transported at launch site

Structural test stand (can cursher) work continued at launch site, more parts added; configured for 33 engine booster [B7]

B7 work continued around aft section

S24 payload bay section / nc barrel section near the entrance of tent 3; downcomers for LOX and CH4 header tanks spotted

S24 nosecone work continued on TPS tiles

PPS work on propellant production plant

NSF

Mary

Nic

LabPadre

[204]
28.03.2022 Ship QD panel worked on on QD arm

OLS tank farm: work behind the wall

Structural test stand worked on at launch site

Zeus (boston dynamics spot dog robot) spotted at launch site

B7 work at fwd dome, as well as around COPV cover

Wide bay work continued

Tent 3: work on a nosecone barrel section

S24 tank section waiting in mid bay; nc barrel section TPS tile installation continued

Construction work outside production site between tent 1 and hwy 4

PPS: Crane counterweight tray and weights loaded onto an SPMT

NSF

Mary

Nic

see below
27.03.2022 OLS tank farm: LOX delivered

Cape: OLIT base rebar and concrete panels installed at LC-39A; second OLIT segment completed at roberts roads Pete Carstens

NSF

Mary

Nic

LabPadre

[205]
26.03.2022 Wide bay construction work continued, first additional wall panel for level 7 has been added (likely yesterday)

S24 nosecone TPS tiles got tape around flap

OLS tank farm: loudspeeker tank venting

Launch site fence section got removed (the one at the main entrance with Gate D2 sign)

Yellow and red crane parts transported away from launch site

NSF

Nic

LabPadre

[206]
25.03.2022 OLS tank farm: wall construction progressed rapidly

B4 transport stand alignment pins not engaged

New booster QD plate delivered and unloaded at launch site for booster QD; B7's QD design is different from B4

Structural test stand worked on at launch site

LR11000X moved away from OLM

B7 disconnected from high bay crane, moved out of high bay and rolled back in later, moved out again

B8 fwd tank section #4 moved into high bay (4-ring)

B7 moved back into high bay again

Wide bay work continued, wall panels on level 6 being added

Chopstick rotated south and lowered

FAA: "The FAA intends to issue the Final Programmatic Environmental Assessment (PEA) for the SpaceX Starship / Super Heavy project on April 29, 2022." Michael Baylor

NSF

Mary

Nic

LabPadre

[207]
24.03.2022 B4 lifted off OLM by LR11000X and placed onto transport stand

Wide bay: wall panels installation continued on level 6

S24 nc barrel TPS installation progress shown including cut out for potential cargo door, lifted by a crane and moved; work on nosecone

B4 disconnected from LR11000X crane and moved away towards Landing pad / SoLS [vid 25]

NSF

Mary

Nic

LabPadre

[208]
23.03.2022 B4 attached to LR11000X ahead of possible lift from OLM; transport stand being prepared; booster QD retracted slowly

OLM: new steel side parts welded to a leg, likely for future plumbing covers

Chopsticks worked on

Launch site: flexible pipes being worked on

S24 nosecone barrel section TPS work contineud, as well as on nosecone in tent 3

Wide bay work continued, construction elevator in use inside wide bay

Air conditioning unit lifted into place at PPS

Dome segments (new design) outside tents on a cart

New booster thrust puck at production site (delivered recently)

NASA: NASA has selected Starship for an additional mission to the Moon with astronauts as part of the Artemis program

NSF

Mary

Nic

LabPadre

[209]
22.03.2022 S24 nosecone barrel: TPS blankets and its black net covering being workded on, first TPS tiles being added

Booster fwd dome lifted onto sleeving stand [B9/B10/B11?, same as on March 20?], sleeved with flipped fwd dome sleeve (likely the one from March 20, 3-ring) after it rolled out of tent 1 again

B7.1 barrel sleeve "Aft dome barrel assy" (4-ring) moved towards sleeving stand, apparently for a new test tank

Production site concrete work

Wide bay: level 5 and 6 wall panel work continued

Thrust puck for future booster delivered

Booster test stand with hydraulics moved to launch site by two SPMTs (lower part of can crusher/structural test stand); moved to cryo station, possibly for B4 testing

Booster load spreader bar attached to LR11000X, possibly to lift B4 off OLM; crane moved towards B4

OLS tank farm: new plumbing prepared

Booster transport stand worked on and prepared at launch site (the one with the alignment pins), moved to OLS next to B4 by new SpaceX SPMTs

Chopsticks opened

NSF

Mary

Nic

LabPadre

[210]
21.03.2022 B7 grid fins in front of S25 mid-LOX barrel section

S24 in mid bay

Booster aft section with header tank spotted in tents [B?]

B7: crew work on platform at cmn dome, chine moved

B9 fwd dome flipped

B4 propellant load test with CH4 [?]

NSF

Nic

LabPadre

[211]
20.03.2022 B7: chines installed: aerocovers for the vertical COPVs

New booster fwd dome spotted in tent [B9?]

New ship common dome in front of tents [new design]

New booster comn dome section moved out of tent 1 (4-ring, sleeved), ullage vents preinstalled [B8/B9?]; attached to flipping jig, flipped

Wide bay: more beams lifted onto top level (roof level), second half of the roof structure beginning to be built

SN20/S20 detached and moved away from chopsticks

OLS tank farm: LOX deliveries

New booster fwd dome [B9/B10?] lifted onto sleeving stand

New booster fwd dome sleeve [B9/B10?] moved outside tent 1, prepared for flipping

NSF

Mary

LabPadre

[212]
19.03.2022 OLM work continued

OLS tank farm: LOX and LN2 deliveries; GSE piping work continued at landing pad loading area; wall construction continued westwards

Production sit consturction

S24? nosecone barrel section with payload dispenser: white thermal blankets being installed

Scrap ship common dome in front tent 1

Booster header tank lifted [B8/B9?] and moved into tent 2?

QD arm: ship QD retracted from SN20/S20, then arm retracted away from ship ahead of destacking

Starship 4/20: S20 destacked from B4 by chopsticks, road remained open for the first time

Cape: OLIT segment 2 nearly finished [Ryan Bale]

NSF

Mary

Nic

LabPadre

[213]
18.03.2022 Booster header tank still outside tents (for LOX) [B8/B9?]

Wide bay construction work continued: level 5 walls, top level beams

4-ring nosecone barrel section in front of tent 3 as well

Booster COPV aerocover at production site

Starship 4/20 [B4/S20] propellant load testing; OLS tank fram active; unlike a cryo proof test, wher only LN2 is used, here the tanks got filled with propellant (CH4/LOX); B4 LOX and CH4 tanks got frosty, followed by S20 tanks, only partially filled (0.5-2 rings); drone observed the test

SPMT moved around rocket garden / PPS

NSF

Mary

LabPadre

[214]
17.03.2022 Starship 4/20 cryo proof test continued

OLS tank farm: some venting from vent stack; work on plumbing in front 5 CH4 tanks; LN2 delivery

Work on one of the tracking dishes near Gate C2

OLM work continued, new metal part has been added on top of the coverings, welding work

Booster header tank outside tents [B8/B9?]

Entrance building work continued behind high bay and Stargate [?]

SpaceX SPMTs being assembled

Booster fwd dome sleeve in a tent

SN8 forward flap spotted at Brownsville Airport being displayed

Cape: Second OLIT segment two columns installed at roberts road

FAA: PEA endangered species act consultation and section 106 review pushed to March 27 Michael Baylor

NSF

Mary

Nic

LabPAdre

[215]
16.03.2022 Crane moved into tent 1

Ship aft section flipped (4-ring) [inside visible, new design], moved into tent 2 [add: S25]

New flatter dome design visible again

Wide bay: more preassembled roof beams lifted and installed; z-beams lifted as well; First of 2 upper floor and roof main support trusses installed

Tracking station: dishes lowered

S22: red tape added on TPS tiles around aft flap

Work on structural test stand at PPS

Launch site: hydraulic rams moved

Cargo door prototype and S24 nosecone still outside tent 3

Ship QD/SN20/S20 work on QD arm

OLM and OLIT work continued

Starship 4/20 [B4, S20] cryo test [with liquid nitrogen], much venting from OLS tank farm (all areas), OLIT vent indicating cryo flow through OLIT, OLM vent, frost on B4 tanks and S20 condensation, first time ship QD active with cryo [vid 17]

NSF

Mary

Nic

LabPadre

[216]
15.03.2022 SN20/S20 prepared for lifting between chopsticks

OLM work continued, wooden parts removed

Ship QD lines being cleaned

OLS tank farm: work on GSE piping around new CH4 tanks

Red crane parts delivered earlier this month now identified as Liebherr LTM 1300–6.2, at gate A2

Wide bay: New beams for roof level lifted and installed, wall levels being installed up to level 5 (of 11)

New dome design outside tents

SN20/S20 lifted by chopsticks onto B4 for second time, much faster than previously; third full stack; Ship QD arm extended to S20 [cont. vid 16]

NSF Cape update #4:

-Roberts Road:

--Hangar X: Extension roof complete, side walls worked on, loading ramp along the wall under construction (facing parking location); expansion seems to have reached its limit; east side: wall painted black, large door entrance; Falcon 9 transporter spotted—Water tower: Hooked up to ground pipes and closed off—Berm being built to separate the Starship yard and the rest of the facility—Retention pond began to be constructed at the west end of facility—OLIT: First segment being constructed, 3 columns are up on construction stand, cross beams added; 5th beam ready for second segment; 5th foundation for segment now complete [add: NSF speculation that this would be enough turned out to be incorrect]

--Starship yard/factory: Progress on ground work, especially on pile drilling (holes filled with rebar and concrete); 6 east to west rows of piles (12 per row) have already been completed on northern side; half way done with seventh row; concrete yet missing

-Pad 39 A:

--OLIT base: concrete poured around the base of four support pillars; large crane next to it—Two propellant tanks (spotted on NSF fleet cam on March 7) now placed at new fuel farm next to the Falcon ramp (old 2019 Starship foundation)

--Hydrogene sphere work continued; potentially for CH4 storage (usable storage capacity: 3218m3, compared to 2395m3 full stack Starship CH4 volume)

NSF

Mary

Nic

LabPadre

[217]
14.03.2022 SN20/S20 now at chopsticks, chopsticks closed in later

Ship QD vented early morning at 5:32 Ship QD extended (although SN20/S20 not yet stacked)

Launch site weather station work continued

Wide bay construction continued: first level 11 beams preassembled and lifted by LR11000 (for final roof level, no wall panels installed yet); followed by second one; more beams added on lower levels for outside support structure

Booster barrel section (3-ring) moved

Deliveries to production site

Production site: Concrete work

New black SPMTs delivered!

S24 nosecone now outside tent!; fwd flaps have been installed

Road closed at 14:13, sheriff left at 14:54 again

NSF

Mary

Nic

LabPadre

[218]
13.03.2022 B4 transport stand moved from under chopsticks to landing pad

Chopsticks raised early morning, lowered afterwards Ship common dome scrap, booster aft section prepared for flipping

Booster aft section (4-ring) flipped; header tank part visible (with three-engine pipe outlets!) [B8/B9?]

OLM work contineud

LN2 delivered to OLS tank farm

GSE piping delivered to OLS tank farm

New booster transport stand shown at launch site

Crew worked on a weather station

SN20/S20 moved away from cryo pad and OLIT

SPMT counterweights adjusted

SN20/S20 moved to chopsticks [vid 14]

NSF

Mary

LabPadre

[219]
12.03.2022 B8 stacking started: fwd dome section lifted and stacked on another 3-ring section (LCH4 tank now 6/13 rings)

B4 one grid fin has moved/turned a bit

New building work along launch site wall continued, more beams installed

LR11000X moved towards OLS

QD arm, more parts removed by LR11000X; crane moved away from OLS after that

Unknown parts spotted at launch site

Starship factory: Foundation work next to tent 3 continued, concrete being poured

S24 Nosecone tent 3: TPS tiles installation nearly complete

Chopsticks lifted; ship QD arm retracted from B4

NSF

Mary

Nic

LabPadre

[220]
11.03.2022 QD arm: parts of second claw uninstalled as well and lowered by LR11000X

B8 fwd section moved into high bay to start with stacking

B7 work through access hole near the weld

Wide bay: construction continued, wall panels being fixed, some level 5 panels have been installed

S24 still in mid bay

S24 nosecone barrel with payload dispenser: work continued on TPS blanket

LR11000X moved at OLS

Chopsticks connector bar delivered to OLS

Booster transport stand (new one) moved to launch site, concrete pad next to the circular tank; OLIT two beams erected and cross beams installed; new tower pads nearly complete; HangarX building extension towards pond nearly covered; Starship factory foundation work continued

LabPadre Florida update: Water storage near completion at Roberts road

NASA document: Artemis HLS mission plan updated, new images; depot Starship is shown to be 6 rings longer than regular tanker Starship (687m3 extra volume)

HLS: NASA has released images of astronauts training on a HLS Starship elevator for future Artemis Moon landings. Toby Li

NSF

Mary

LabPadre

Scuba

Toby Li

[221]
10.03.2022 B7 CH4 tank section moved into high bay, stacked onto LOX section at 12:47 am; grid fins still missing

S25 aft dome spotted, lifted onto sleeving stand; sleeved with 4-ring sleeve [flipped yesterday]; lifted of stand

Wide bay: Staircase consturction behind high bay continued; bracing installed (connection above the future entrance)

Payload bay pathfinder (not same as S24 nosecone barrel section?!)

B9 common dome sleeve (4-ring, RCS/ullage vents upside down) moved out of tent

S24 nosecone barrel section: TPS tile blankets added; another 5-ring section behind it

B9 common dome lifted onto sleeving stand, sleeved with common dome sleeve, lifted off sleeving stand and moved back into tent

Transfer tubes moved to scrapyard

Hwy4 road work continued

OLS, OLIT: rails inspected on movable work platform

QD arm work, one of the claws (stabilization arm) removed and lowered by LR11000X

Beam structure has been erected next to launch site entrance (behind the new entrance building)

SN20/S20 work through access hole, fan used

Work on loudspeaker tank at OLS tank farm

NSF

Mary

Nic

LabPadre

[222]
09.03.2022 Chopsticks work continued

QD arm work continued

SpaceX LR11000X fitted with new rigging, connected to one of the QD stabilization arms

Booster transport stand (old) moved towards production site

S25 aft dome sleeve prepared for flipping (4-ring), flipped

B4 vented (fwd dome depress vents)

B7 LOX tank lifted onto booster transport sand

McGregor: Raptor Vac engine test on horizontal test stand for about 0m02s?; first time with water deluge system

NSF

Nic

LabPadre

Cuker

[223]
08.03.2022 Chopsticks tested (went to the top, opened, closed, moved, went down again, accompanied by drone)

B8 common dome section (4-ring) at scrap yard

LOX truck to lunch site

More red Liebherr crane parts delivered

Wide bay work continued on lower levels, wall panels being added, elevator installation continued, stair construction continued behind high bay

Dome sleeving stand modifications continued: New and differently shaped alignment jigs, possibly for differently shaped domes

B6? header tank scrapped

Booster fwd dome worked on at production site outside tents

New booster transport stand underwent testing (pins lifted and lowered by hydraulics)

OLS, OLIT: tower rails being worked on

Road work on hwy4 in front of OLS

Ship common dome section spotted in a tent

New nosecone spotted in tent 3

NSF

Mary

Nic

LabPadre

[224]
07.03.2022 B7 rotated in high bay

OLM work continued

Road work on hwy4 continued

Potential payload dispenser installed in nosecone barrel section believed to be S24

OLS tank farm: work around CH4 tanks

QD arm moved (retracted away from B4)

Wide bay: stair section lifted into it

B7 in high bay: arrangement of COPVs has changed from a ring around aft section to two vertical columns

Absorption columns that left Sanchez 2 weeks ago have arrived at Port Canaveral at 9:42am EST

NSF

Mary

Nic

LabPadre

WLAnimal

[225]
06.03.2022 S24 noseceone, fwd dome section, thrust section in tent; S25 common dome section/segment and another nosecone spotted in same tent

5-ring nosecone barrel section work continued

S22 work continued at PPS

Red crane parts delivered to production site

Work on new booster transport stand; old booster transport stand moved outside bay area by SPMT

B8 fwd tank #2 (3-ring) spotted ("goes directly underneath the forward dome section")

Dome cap delivered to production site

Wide bay work continued; installation of a construction lift

B8? fwd dome section spotted

LCH4 delivered to OLS tank farm, as well as LOX

OLM work continued

Deimos oil rig arrived at Port Pascagoula, Mississippi

NSF

Mary

LabPadre

[226]
05.03.2022 Booster fwd section spotted near other sections, another one in a tent

B7 aft section with a new design spotted at tent entrance: different QD plate and addition of a header tank!!, rolled out and moved towards high bay

Counterweights moved by SPTM

New booster transport stand still at PPS

Utility work next to Starbase sign / hwy4

S25? common dome section in tent

B7 tank section (which one?) lifted and moved in high bay; LOX section stacked onto thrust section, both tanks now fully stacked

OLM work continued; work on booster QD

NSF

Mary

Nic

LabPadre

[227]
04.03.2022 Ship cmn and aft dome, booster fwd and cmn dome lying around outside tents

Parts for structural test stand lifted into place

Wide bay: construction continued, more z-beams lifted into place

Dome sleeving stand being modified

B7 grid fins spotted, not painted black (yet?)

Work on GSE7 outside cable

OLM work

SN20/S20 work through access hole

Flexible pipe near methane offloading site at OLS tank farm; CH4 delivery

Parts delivered to OLS

B7 work in high bay

Damaged CH4 tank (truck) towed away (Stabilis)

Florida; Cape: First section for OLM at LC-39A at KSC spotted![228]

Elon Musk: "SpaceX reprioritized to cyber defense & overcoming signal jamming. Will cause slight delays in Starship & Starlink Block 2."[229]

McGregor: Raptor 2 engine test on horizontal test stand for about 0m33s?; multiple very bright flashes at the end

NSF

Mary

LabPadre

Cuker

[230]
03.03.2022 Tracking station: one dish used for Starlink 4–9

S22 single TPS tile attached

Wide bay: Work continued (more beams lifted)

LR11000 (Buckner) modifications continued, has now a double jib mast

Ship aft dome with new design spotted along with booster fwd and common dome

Stainless steel tube (possibly methane transfer) spotted

OLS tank farm: work around CH4 site continued; LOX deliveries

LR11000 lifted its boom and jib partially; followed by complete lift later

Masey's Gun Range [Massey's gun range]: First structure (a tent) began construction

SN20/S20 cryo proof test, LOX tank fully filled, followed by CH4 tank (likely fully as well)

Cape: OLIT tower jigs assembled, new tank spotted at roberts road facility Farrielle

NSF

Nic

LabPadre

[231]
02.03.2022 B4 cryo test continued, LOX tank fully filled, CH4 partially, huge depress vents; loudspeaker vertical LN2 vent continued long in the morning; OLIT vented again

Chopsticks lowered

SoLS pad A upgrading work

Booster aft dome sleeve (4-ring) in front of tents, aft dome on sleeving stand, workers wrap up extending pipes for engines with plastic bags; aft dome sleeved [B8/B9?]

S24 nosecone TPS tiles work continued

S22 work at rocket garden/PPS continued around aft flaps

Wide bay work continued (wall panels being added on level 3&4)

Buckner LR11000 upgrade work continued

Ship wfd dome moved away from tents, ship aft dome moved into tents

Booster fwd section near high bay [B8?]

SPMT transported ballast from PPS

LR11000X laid down at 11:25 and gone back up later, reason unknown

Star Factory at Boca Chica: Foundatiion work looking very far in progress; building is expected to be over 300'ooo sq ft by 60' tall and will replace all the large production tents [RGV]

Cape update #3 (NSF):

-Roberts road: Expansion continued, including the area for possible new Starship construction yard; two rusted feet spotted for building and transporting the OLIT segments, first pillar already delivered, together with some cross beams; ground pipes built that end near the tower construction area, ending in three concret squares (similar to PPS for data connections); large white tank, possibly for water, added onto circular gravel pad next to tower construction pad; hangar X work continued, roof beams in place, roof beginning to be added, parking space complete; levelling and drilling of holes for future Starship production buildings

-LC39A: Earth work continued near OLIT area, different lines being worked on

McGregor: Raptor 2 engine tests:

-on tripod test stand for about 0m07?s;

-on horizontal test stand for about 0m30s

-on horizontal test stand for about 0m01s

NSF

Mary

Nic

LabPadre

RGV

Cuker

[232]
01.03.2022 OLS tank farm: LOX delivery

Booster aft dome, ship common dome and booster fwd dome at tent area

S22 aft flap work continued

Wide bay work continued, more beams lifted to top levels

LR11000 main boom reassembled

Chopsticks moved

B4 cryo test, both tanks frosted up, whole OLS tank farm active; OLIT was venting as well (although ship QD not active) [cont. vid 02]

NSF

Mary

Nic

LabPadre

[233]

February 2022[]

Date Description Source Link
28.02.2022 S24 tank section [cmn + midlox stack] in high bay; moved to mid bay early morning

Wide bay: level 2-4 wall segments completion continued; more beams lifted into place at the top

LR11000 parts delivered; derrick installed; counterweights loaded onto a SPMT, moved to production site

Booster fwd dome section spotted in a tent

S22 work through fwd hatch continued at PPS

Load spreader that has been used for lifting wide bay segments loaded onto truck for departure

Dirt work outside production site

Ship aft flap waiting to be offloaded at production sit

Booster fwd section moved out of tent

Pedestals delivered

OLM work continued

OLS tank farm: CH4 wall work continued; concrete pumped into forms

Deimos left port of Brownsville for Pascagoula, Mississippi, possibly for transformation work

Florida KSC: First OLIT parts (columns) spotted to be delivered

McGregor: Raptor 2 engine test on horizontal test stand for about 0m10s [captured live as well]

NSF

Mary

Nic

LabPadre

Trevor Mahlmann

Cuker

[234]
27.02.2022 Buckner LR11000 modification work underway; complete boom reconfigured

B8 common dome seen

OLS tank farm: Wall work completion continued; CH4 truck waited at production site for delivery

New booster transport stand spotted at PPS; new guiding pins have been installed on both sides

SoLS: compressed nitrogen truck; LN2 delivery

NSF

Mary

LabPadre

[235]
26.02.2022 S22 work through access hole

Wide bay: more beams being added

LR11000 boom lowered, possibly for extension, new crane parts moved to production site

OLS tank farm: work at CH4 recondenser, concrete work at the brick and concrete wall that surrounds the CH4 site

NSF

Nic

LabPadre

[236]
25.02.2022 Crane mats removed from under LR11000X

OLS tank farm: Wall work around CH4 tanks continued (briks); LN2 delivery

OLM work continued

Crane parts delivered for LR11000 which is likely to get an upgrade

Wide bay work continued on level 2 and level 3 wall panels

Build rig, likely for domes, delivered

CH4 truck at production site

S24 common dome section stacked and welded on LOX section in high bay

NSF

Mary

LabPadre

[237]
24.02.2022 OLS tank farm: Methane tanks delivered yesterday now lifted into place next to the other larger two; third smaller (fifth in total) white horizontal tank moved to OLS tank farm by SPMT, followed by fourth and fifth (total seven); all five smaller CH4 tanks lfted into place

QD arm rapid retractio test at 15:04:30

More new LR11000 parts delivered

Wide bay: fourth corner segment lifted to level 9&10

Cape update #2 (NSF):

-Roberts road: 67 acres large site; Hangar X expansion continued, second expansion started towards ponds; circular pad poured and filled with gravel next to OLIT construction foundations, purpose unclear; six new pad foundations for OLIT construction being worked on, and rusty steel parts spotted for building the segments; large rectangular pad now levelled for proposed 32000 ft2 facility for Starship construction (192000 ft2 expansion also proposed in phase 2), piles prepared for foundation

-LC39A: 4 large propellant tanks delivered for Starship pad, last week they were at the turn basin; no work on mobile service tower yet for Falcon payload integration; possible cut-outs in liquid hydrogen sphere; some earth work near future OLM pad

-LC49: No work yet, environmental review in progress

HLS: NASA's Mark Kirasich: All three HLS teams assembled low fidelity mockups during the last 10 months. SpaceX also assembled and demonstrated their Starship elevator concept “in a very short period of time." Stephen Clark

NSF

Mary

LabPadre

Stephen Clark

[238]
23.02.2022 S22 wor continued (especially TPS tiles) during the night

OLS tank farm work continued (e.g. around new CH4 foundations, concrete work beginning at 02:28 am); LN2 and CH4 deliveries

LR11000X crane moved towards OLS; parts delivered; Two long white horizontal methane (CH4) tanks moved from PPS to OLS

OLIT and chopsticks work continued; as well as on OLM

S24? nosecone TPS tiles work continued in tent 3

Wide bay: Fourth and last segment of level 9&10(5) connected to LR11000, disconnected again; more beams lifted

SN15, S22 and SN16 at rocket garden

NSF

Mary

Nic

LabPadre

[239]
22.02.2022 Booster transport stand moved to build site on SPMT

LN2 delivery to OLS tank farm

OLS tank farm: wall construction work continued around CH4 tanks

OLS, IT (OLIT): work on movable platforms

Wide bay: more beams and parts delivered

New crane parts for LR11000 (Buckner owned crane, possibly reconfiguration)

S22 TPS tile work on aft flap at PPS, received aft aerocaps

New ship fwd flap delivered to production site

Ship nosecone barrel section assembled in high bay

S24 nosecone TPS tile work continued in tent 3

Bridge crane hook blocks mixed with some LR11000 parts

SN20/S20 and OLS tank farm cryo proof test, CH4 heat exchangers frosty, as well as LOX and partly CH4 tanks on Ship

McGregor: Two Raptor 2 engine tests on tripod test stand for about 0m09s and one for about 0m2.5s

NSF

Mary

Nic

LabPadre

Cuker

[240]
21.02.2022 LOX deliveries continued

S24 nosecone work continued, especially on TPS tiles

B6 test tank disconnected

Transport stand moved at PPS by SPMT

Nosecone barrel section moved outside tent 3, possibly for a new cargo door prototype

4-ring section outside high bay; moved into high bay

Booster methane transfer tube delivered; new transfer tube design than previously seen on other boosters

Pedestals delivered to build site

Wide bay work on lower levels; LR11000 still attached to third top level segment; new beams delivered

S24 nosecone in tent 3 TPS tile work continued; a ship thrust section next to it

OLS: earth work continued for CH4 extension

NSF

Mary

Nic

LabPadre

[241]
20.02.2022 Wide bay: Second corner segment of level 9/10 lifted by LR11000 and installed, rigging uninstalled; connected to third segment, lifted

S22 outside high bay; moved to rocket garden (PPS) between SN15 and SN16

LCH4 deliveries to OLS tank farm

OLM work continued

B8 common dome section moved out of high bay (destacked, likely to be scrapped [see: [242])

NSF

Mary

LabPadre

[243]
19.02.2022 Chopstick test continued; lowered later that day

B8 common dome section lifted in high bay and stacked

OLS tank farm work continued; concrete work next to CH4 tanks (completing new foundations for new CH4 tanks); vertical cryogenic process pump installed at LOX side of OLS tank farm, more have been delivered

LN2 deliveries to OLS tank farm

Ship flap deliviered to build site

S22 moved out of high bay; flap installed; moved into high bay and out again

B6 test tank lifted at PPS

Wide bay: Staircase construction continued behind high bay

LNG (Liquid natural gas) purification stack removed from Boca Chica

Entrance building behind high bay construction continued, roof added

Booster aft caps spotted on a stand

Absorption column (second one) left Starbase at 09:02

NSF

Mary

Nic

LabPadre

[244]
18.02.2022 B4 cryo proof testing on OLM, LOX tank fully filled (frosty); methane subcoolers frosted up

B8 stacking began in high bay; 4-ring section lifted by bridge crane; aft tank #2 (4-ring section) moved into high bay, lifted and stacked; B8 common dome section (4-ring with ullage vents below stringers) outside high bay

Wide bay: second level 9/10(5) corner segment attached to LR11000; more beams delivered

LCH4 deliveries continued

First of several smaller LCH4 tanks moved from PPS to OLS tank farm [looks like half]

QD arm moved away from B4 (retracted)

First absorption column left Starbase at 9:35am

Chopsticks raised to the top of OLIT

McGregor: Raptor 2 engine test on horizontal test stand for about 1m42s

McGregor: Raptor 2 engine test on tripod test stand, duration unknown, only picture available

NSF

Mary

LabPadre

Cuker

Cuker

[245]
17.02.2022 OLS tank farm: LCH4 (liquid methane) deliveries; venting

OLM work continued; most of the gap covers have been painted grey as well

Ship section (4-ring) test fit with a booster fwd section, possibly B8 and S24; then removed again; another fit check followed [stage separation / clamp system tests]

Wide bay: First segment of level 9/10(5) lifted by LR11000 and installed, there's no outside supporting structure on level 10 as this is going to be the top level; crane detached from segment; second segment attached to LR11000

B8 aft #2 section (4-ring) spotted outside high bay; being cleaned

Ship load spreader moved at production site

S22 has been disconnected from high bay bridge crane

SN20/S20 cryo proof test at OLS cryo pad; full frost on LOX tank; venting from engine chill vents

Vertical LN2 tank near bunker now called heat exchanger by NSF [the loudspeaker tank]; vented

S24 nosecone TPS tiles installation continued in tent 3 [nosecone shown previous vids also S24!]

Entry building next to high bay: Sidings installed

Mid bay: Maintenance work on roof

NSF

Mary

Nic

LabPadre

[246]
16.02.2022 SN20/S20: transport stand QD connected to S20; cryo proof test on OLS cryo pad, frost on both tanks, engine chill vents inside flaps; possibly testing the full OLS tank farm system including LCH4 side

S22 welding work continued, still connected to high bay crane

Wide bay construction work continued, wall panels added to level 9/10(5) segments; first connected to LR11000

B7 [?] aft section (4-ring) spotted [possibly the number is B9, difficult to read]

B2.1 and BN2.1 next to each other at PPS

Foundation work next to S16 possibly for another display/storage pad [add: for S22]

Nosecone in tent 3: TPS tiles applied; booster fwd dome section outside the tent

S24 thrust section hooked to crane inside tent 3

S25 common dome section spotted

FCC: approved SpaceX for vehicle communications for orbital test flight

McGregor: Raptor 2 engine test on horizontal test stand for about 0m10s; loud sonic-like boom at the start

NSF

Mary

Nic

LabPadre

Cuker

[247]
15.02.2022 SN20/S20 moved away from chopsticks to its cryo stand at south of the OLS tank farm

OLS tank farm: LCH4 (red label) deliveries continued, as well as LN2 (blue/green) and LOX (yellow)

S22 nosecone (ex S21) welded to its tank section

QD arm plumbing work continued

Wathervane and anemometer (wind speed measurement) on Starhopper

LR11000 lowered near wide bay for jib extension (for lifting final wide bay segments); raised again with 12m extension

S21 tanks section work remains paused

Wide bay level 9/10 segments preassembly continued, first wall panels being added; last parts of two wide bay bridge cranes have been spotted

S25 nosecone barrel section spotted (5-ring)

B8 aft #2 and aft #3 sections spotted (4-ring)

Unknown parts spotted at production site (small diameter tubes?)

B2.1 and B6 test tanks, as well as cargo door pathfinder shown

S24 mid LOX section (4-rings with tiles) and common dome section (with tiles) and an unknown 4-ring sleeve (untiled) seen in front tents

Entrance building next to (behind) high bay work continued

"Nominal segments" delivered, yet unknown purpose

Ship QD arm venting spotted at 19:47:10

Cape Update NSF #1 [NSF planning weekly updates from now on, covering not only SpaceX]:

-Roberts Road Operations Area: Hangar X used for storage and refurbishment of Falcon 9 boosters; Hangar X is currently undergoing an extension; large amount of land being cleared as well as foundations prepared - likely for a new Starship build site 320'000 ft2 or 29'728 m2 building proposed; loading dock construction, as well as a circular structure with 9m diameter, possibly a foundation; 12 square concrete pads with the same layout at PPS for launch tower segments construction (3 segments at a time); road extension north towards Schwartz Rd, possibly for Falcon/Starship transportation

-Kennedy Space Center, LC-39A: Holes visible in an old spherical liquid hydrogen tank, possibly for LCH4; 4 horizontal LCH4 tanks visible below it (bought in 2019); yellow piling crane dismantled, foundation work for Starship launch pad possibly complete

-Cidco Road Facility: Today likely part of heat shield production process (not to be confused with bakery)

NSF

Mary

Nic

LabPadre

Starship Gazer

[248]
14.02.2022 Polaris program news: Jared Isaacman scheduled two flights on Crew Dragon but also one on Crewed Starship

OLS tank farm: First time venting from "mystery brown tank" at methane side

Starship 4/22: SN20/S20 destacked from B4 by chopsticks during road closure (RC 10:27am, pad cleared 10:52am, road opened 2:01pm, QD arm back into position at 2:15 8:09pm detached from chopsticks); some OLS tank farm ventig ahead of destacking and ship transport stand moved into position; ship QD arm retracted for operation S21 and S22: S22 tank section moved to high bay; S21 nosecone reassigned to S22; nosecone lifted and stacked onto S22 tank section in high bay

Wide bay: Work on level 9/10(5) segments (all) continued

S25 fwd dome sleeve outside tents (3-ring)

FAA: New target date for issuing final PEA is March 28

McGregor: Raptor 2 engine test on tripod test stand for about 0m05s; smooth quieter sound

NSF

Mary

Nic

LabPadre

FAA

Cuker

[249]
13.02.2022 OLM work, some scaffolding reinstalled after presentation

OLS tank farm: First methane (LCH4, red truck sign) delivery! In total three trucks via landing pad

Controlled access area sign: Pre requirements: "FR clothing, 4-Gas monitor, hard hat, safety glasses, safety work shoes. Pad site work permit is required for all work in orbital tank farm"

Ship common dome [S24?] flipped (4-ring, access hole at top ring), moved into tent 1

Deliveries to production site (wrapped up)

B7 methane section moved from high by into mid bay, LOX section moved inside high bay, relocated

4-ring section moved into tent 2

NSF

Mary

LabPadre

[250]
12.02.2022 Workers on QD arm

OLM/B4 work on QD

Booster transport stand next to SoLS pad B

Jared Isaacman's Alpha Jet flew over Boca Chica

NSF

Nic

LabPadre

[251]
11.02.2022 Nosecone, ship fwd dome and nc barel section seen in tent 3

Wide bay: Wall panels continued to being added; level 3&4 nearly complete, some still missing on level 2; more beams added [add: z-girder according to RGV]; assembly of two level 9&10/5 corner segments continued (other two begun as well [vid 12]); more staircase assembly work behind high bay

Bigge LR1300 crane lowered in front wide bay

S22 tank section: work platform added at fwd dome section ahead of potential nosecone stacking

New building at the side/behind high bay work continued, taking form; likely to be some sort of entrance building from parking space

Chopsticks closed and lifted towards SN20/S20 lifting points; not yet attached

Jared Isaacman's Alpha Jet flew over starbase Boca Chica

OLS tank farm: Cryo proof test [see SN20 for timeline]

McGregor: Three Raptor 2 engine tests:

-horizontal test stand, duration unknown

-tripod test stand, for about 0m05s

-tripod test stand, for about 0m04s?

NSF

Mary

Nic

Jack

LabPadre

Cuker

[252]
10.02.2022 SN20/S20 stacking operations by chopsticks; second full starship stack

Ship QD extended and attached to SN20/S20

Work around S20/B4 interface; chopsticks stabilization arms removed from S20

Landing pad: Workers prepared stage and equipment for Elon Musk's Starship presentation

Chopsticks disconnected from SN20/S20 and opened up [seen in vid 11]

Elon Musk Starship presentation:

-Plan to produce one Starship every 3 days

-Will be capable of 100-150 tons to LEO

-Tanker variant 200 tons to LEO; orbital refuelling in side-to-side configuration, expected optimistically end of 2023

-Pumps designed to fill a booster in 30 mins

-TPS tiles designed to be robust and cheap

-Booster thrust of 17 mio pounds of thrust

-Raptor 1 185 tons of thrust, Raptor 2 230 tons, goal 250 tons; cost reduced to half and simplyfied design, flanges replaced with welds, shrouds could be removed at some point; achieved 247 tons on test stand; nominal chamber pressure of 330 bars eventually; 700 seconds burn time over multiple restarts on a single engine; one engine per day expected next month

-OLIT 13 months from design to completion

-FONSI expected in March

-Starship could possibly be cheapest means of transport for long distance cargo transport on earth

-Orbit hopefully this year

-If no FONSI, delay of 6–8 months to begin launch at Cape, where they have approval to launch

-Vehicle losses expected during testing

-Price per launch expected less than $10 mio

-Starbase as R&D hub, Cape for operational launches

-Floating spaceports planned near cities

-No independent abort mode on Starship, but abort may be possible in event of booster failure; Crew launches possibly underfueled for additional TWR during abort

-Phobos and Deimos are low priority, plan to complete one by the end of the year

NSF

Mary

Nic

Jack

LabPadre

[253]
09.02.2022 Intermittent RC for today from 1am to 9:30am

SN20/S20 has moved between the chopsticks; chopsticks moved up to lifting points, later lowered again; S20 opened aft flaps (fwd flaps already opened)

QD arm work continued

OLS tank farm vertical LN2 tank venting

SoLS tank farm unusual venting from black tanks

RSN27 (Raptor 1) and RSN88 (Raptor 1.5) in tents

B9 comm dome (4-rings with ullage vents, stringers (less than one ring high) spotted outside tents

Wide bay work continued

Smooth nosecone (the one outside tent 3) being scrapped

SN20/S20 stacking operations by chopsticks [vid 10]

McGregor: Raptor 2 engine test on tripod test stand for about 0m51s; smooth sound

NSF

Mary

Nic

LabPadre

Cuker

[254]
08.02.2022 LR11000X crane rotated

QD arm: curved part (bumpers) lowered down by LR11000X; preparation work continued

OLIT scaffolding being removed, so chopsticks could move

B4 grabbed by QD arm claws; work on the claws connectors

SN20/S20 work on QD; took them very long to disconnect the ship from the stand QD

Chopsticks: Scaffolding being removed, new lifting pins spotted Starship Gazer

Excavator trying to remove water from landing pad near entrance

B6 test tank moved at PPS by SPMT

B2.1 test tank moved at PPS

Wide bay: LR11000 still connected to last level 7&8 segment, work on several areas continued; two spars for bridge cranes arrived

S22 work continued in mid bay; aft flap aerocover moved into mid bay

New tent spotted in tent 3

Berm tunnel on landing pad painted black, likely to prepare for presentation

Raptor 2 SN10 spotted at McGregor [NSF]

SN20/S20 moved into position for stacking

NSF

Mary

Nic

LabPadre

[255]
07.02.2022 B4 disconnected from LR11000X load spreader 2:54 am

SPMT Coupler lifted; one of the two SPMTs moved away from under the B4 transport stand; stand moved away

New launch site fence painting work continued

QD arm work continued

OLIT work continued on movable work platforms

OLM/B4: booster QD work

Wide bay: last level 2 wall panels being installed; beams delivered

Ship transfer tube with anti-vortex device delivered ("The anti-vortex device prevents methane from cavitating and damaging Raptor engines")

5-ring nosecone barrel section scrapped

Long pipe lifted inside the high bay

Coil of stainless steel delivered

COPVs and potential vehicle parts delivered

OLS tank farm: work platforms erected around the two horizontal large CH4 tanks, possibly for building a wall; insulated GSE pipe moved on landing pad

McGregor: Raptor 2 engine test on tripod test stand for about 1m18s; Mach Diamonds visible, started with yellow and green exhaust

NSF

Mary

Nic

LabPadre

Cuker

[256]
06.02.2022 B4 work inside LOX tank; hatch closed at 5:30am

Wide bay: Fourth corner section of level 7&8/4 lifted at 8:20 am and installed

B4 prepared for lifting (ropes attached), lifted off transport stand and onto OLM for the fourth time, by LR11000X without the help of the chopsticks; transport stand removed

B4 secured on OLM, booster QD connected [great closeup]

Ship QD arm work continued; rotated away from B4 after stacking

Bridge crane girder delivered to production site, possibly for new wide bay

NSF

Mary

Nic

LabPadre

[257]
05.02.2022 B4 unhooked from LR11000X at 9:56am

Earth work between OLS tank farm and landing pad continued

OLM work continued

LR11000X moved towards OLS, load spreader lowered and unhooked

Crane load test bag storage boxes shown

Road work on hwy 4 near launch site continued

GSE4 scrapping continued

B4 moved slightly with transport stand

Two jets owned by Jared Isaacman (from Inspiration 4) flew over starbase several times

Wide bay: more beams lifted into place; more beams, likely for final level 9&10 (5), delivered; stair assembly continued next to high bay

Ship aft section flipped (4-ring)

Smooth nosecone with lifting jigs outside tent 3

B7 work on fwd section (still attached to bridge crane)

Chopsticks raised and lowered again; moved out of the way

B4 moved to OLS after LR11000X on an SPMT (the one from yesterday); attached

OLIT: work on rails via movable work platforms "window washers"

NSF

Mary

Nic

LabPadre

[258]
04.02.2022 Testing at OLS tank farm (possibly vertical CH4 tanks): road closure: road closed at around 6:52am; dish has been lowered; pad clear 1:37 pm; at the end a bit venting from the small vertical LN2 tank (with loudspeakers); road opened at 4:01pm

Power outages at shipyard in the morning

Nosecone moved in tent 3

B8 LCH4 sump next to transfer tube

Work on the building like structure (with redish beams) next to high bay continued

High bay: workers using the high bay balcony

Crane load test bag storage boxes shown

OLS tank farm: LN2 deliveries

Wide bay beams delivered

SPMT delivered ballast to launch site, possibly for B4 transport

NSF

Mary

LabPadre

[259]
03.02.2022 B3 methane manifold lying around at launch site

GSE4 stand moved to production site by SPMT

Wide bay third segment of level 7&8 still attached to LR11000

PPS: Ship leg skirt with can crusher top shown close up; work on the bottom part of the structural test stand; trench work near booster 5

B8 LCH4 tank sump [connecting the main LCH4 tank with the transfer tube/downcomer] delivered to production site

High bay load spreader connected to B7 methane tank section (no grid fins installed yet to fwd section)

Beams assembled next to high bay forming the framework of a small building

SpaceX cat spotted

B5 at PPS: hydraulic power unit removed

Elon Musk announced Starship presentation with full stack on Thursday, February 10, 8pm CT (2am UTC)

NSF

Mary

Nic

LabPadre

[260]
02.02.2022 Can crusher top (top of structural test stand) put on aft skirt at PPS

OLM work continued; gaps between the shieldings covered

LR11000X moved to B4, load spreader picked up, hooked up

B4 engine bells have been painted grey [not today]

OLS tank farm work at the vertical CH4 tanks; earth work continued; consumables delivered

GSE4 remains (aft dome) removed from stand, scrapping continued

Starhopper maintenace work

Wide bay work on lower levels continued; some small wall panels installed

PPS: Earth work next to SN15 and SN16

S22 tank section work in mid bay continued, raceway has been installed, some of the TPS tile covering visible; work through access hole

Tiles applied on a barrel section in a tent

B7 methane section has moved in high bay

NSF

Mary

Nic

LabPadre

[261]
01.02.2022 S22 raceway (preassembled) lifted into mid bay for installation, installed; work through access hole

Wide bay construction continued; LR11000 detached from second level 7&8 segment, attached to third segment, lifted at 2:35pm and installed; workers climbing on beams

Old ship leg skirt (2-ring) lifted onto a transport stand at PPS

B7: jig has been installed on its side

Domes cut up at scrapyard

Sleeving stand worked on

Dirt work continued at launch site

B4 grid fins unstrapped

FAA: EA is now at 2 out of 5, endangered species act consultation was finished on 31 January 2022 cms.permits

Roberts road update: OLIT assembly fixture pieces spotted, along with new foundations for assembling the OLIT sections

NSF

Mary

Nic

LabPadre

The Denks, Farrielle

[262]

January 2022[]

Date Description Source Link
31.01.2022 Chopsticks: water bags removed

B3 some remnants still lying around

OLM work continued

Crane ballast and counterweight cradle moved by SPMT

B8? fwd dome section/segment spotted in tent

S24? noseceone (smooth) spotted in tent 3; fwd flap mounting jig attached

S22 flap attachment jigs installed

Wide bay: installation of small vertical cross beams

B4 raptor nozzles have been painted grey [RGV]

RC for today canceled

New RCs for February 3–7 (10am-10pm), February 4 (6am-4pm)

NSF

Mary

Nic

LabPadre

RGV

[263]
30.01.2022 Ship aft section from yesterday removed from sleeving stand

Cargo door prototype still next to smooth nosecone

High bay bar looking finished from outside; work platforms being removed

Ship aft skirt (2-ring) spotted

OLM work continued

Crane water bags loaded onto chopsticks via cross bar

Chopsticks load testing: raised slightly, bags filled water, chopsticks lifted about 1/3 of tower and lowered again

NSF

Mary

LabPadre

[264]
29.01.2022 B4 work on an aerocover

B8 common dome section flipped at 10:57am

Launch site wall construction work continued

OLM: Booster QD work continued

OLS tank farm: LN2 deliveries

Crane ballast bags for chopsticks moved at launch site

Wide bay: First section of level 7&8 (4) lifted by LR11000 at 10:00am and installed, work platforms have been installed on top of level 6; LR11000 attached to second segment, lifted at 3:27pm and installed

Ship aft barrel [S22, S24?] spotted outside tents, ship QD panel has moved upwards by one ring

Crane prepared for flipping rig

NSF

Mary

Nic

LabPadre

[265]
28.01.2022 S21 production appearing to have paused

LR11000 attached to first segment of level 7&8(4) of wide bay

Crane detached from nosecone in front of tent 3

Tracking site: one dish pointed towards launch site

OLS tank farm venting: both subcooler areas, near SN20/S20 stand, south berm; OLM vented for a long time (vent below QD lines); subcoolers frosted up after testing

McGregor: Raptor 2 engine test on vertical tripod test stand for the first time, for about 0m40s; mach diamonds visible

NSF

Mary

LabPadre

Cuker

[266]
27.01.2022 OLS: Excavators work around SN20/S20 base

OLS: GSE piping readied on carts, laid out before being buried; OLM work continued

SoLS: concrete work around pad B

OLS tank farm: cryo deliveries; work on horizontal LCH4 tanks

Ship QD work continued, lines and cables being installed, work on the QD plate and lines

Chopsticks work on the downward extensions

OLS, IT: welding work, work on platform that moves up and down column

B7 moved moved around in the high bay

Nosecone hooked to crane outside tent 3

High bay rooftop bar work continued

13 engine booster aft cap aka "thrust puck" in front of tents

Odd shaped tank spotted in an earlier video speculated to potentially be a new booster header tank design (dome with smalle top ring)

Booster fwd section in production tent

S21 outside mid bay

Wide bay: stair section (produced next to high bay) lowered into it

New RCs for January 31 - February 2 (10am-10pm)

S22 disconnected from crane in mid bay at 20:03

NASA Aerospace Saety Advisory Panel: SpaceX provided the agency with "an integrated master schedule" on HLS Starship development this month. Also gave a "good understanding of some of the challenges" the company is having with Raptor engine production. NASA conducted some site visits to Boca Chica and Hawthorne. Landing technologies accuracy /stability / hazard avoicance identified as top risk to HLS Starship; mitigations include the fact that there will be uncrewed test landings [Sheetz]

McGregor: Raptor 2 engine test on horizontal test stand for about 0m25s; multiple very bright flashes at the end

McGregor: Raptor 2 engine test on vertical test stand for about 0m09s; green flash at the end; similar to test on January 14

NSF

Mary

Nic

LabPadre

Cuker

Cuker

Sheetz

[267]
26,01.2022 Smooth nosecone attached to crane outside tents, next to cargo door prototype

Booster fwd dome lifted onto sleeving stand; dome cleaned [?]; 3-ring sleeve with 2-ring stringers moved out of tent

Wide bay work continued; preassembly of level 7&8 under way

S22 tank section in mid bay (now full height, 16 rings)

Booster [B8] fwd dome sleeve rolled out of tent 1 again after being rolled back in; attached to crane, lifted and flipped; attached to another crane, sleeved

OLM work continued

OLS tank farm: klemm drill rig used again

OLS, IT; Ship QD arm's claw tested

SN20/S20 work around and on quick disconnect

Chopsticks work continued, white part has been added to lower extensions

Standard TFR renewed for February

RC for January 27–28 canceled

McGregor: Raptor 2 engine test on horizontal test stand for about 2m05s

McGregor: Raptor 2 engine test on horizontal test stand for about 1m45s

NSF

Mary

Nic

LabPadre

Cuker

Cuker

[268]
25.01.2022 OLS IT, OLM and Chopsticks worked on; IT with scaffolding on rail columns, working on rails

B4 work continued

Earth work on SoLS, near pad

B3 remains cut into smaller sections

PPS: Work on destillery tower

B2.1 connected to crane for lifting; lifted from structural test stand (lower part of can crusher)

Wide bay: more beams added

Unusual tank structure (dome-like with a small top ring) spotted in tents

Booster common dome and its sleeve next to sleeving stand

S22 thrust section (5-ring with lead-ins) spotted in mid bay

RC for tomorrow canceled

McGregor: Raptor 2 engine test on horizontal test stand for about 2m25s; longest yet

NSF

Mary

Nic

LabPadre

Cuker

[269]
24.01.2022 McGregor: Raptor 2 engine test on horizontal test stand for about 1m54s; dense fog, very loud

Ship and booster stabilization arms folded and extended from 11:36pm to midnight

Cuker

LabPadre

no
23.01.2022 OLM work continued

OLS IT work continued

SN20/S20 rigging and LR11000X disconnected; moved next to OLM

B7 CH4 section being welded by a robotic welder in high bay

Raptor 2 sighted for first time; testing started [270]

RC for January 24–25 canceled

NSF

Mary

LabPadre

[271]
22.01.2022 Wide bay construction work continued, beams added

S22 thrust section moved from high bay into mid bay (moved in and out several times)

B7 aft tank section #4 moved near high bay [?]

B7 LCH4 section stacked on another 4-ring section at 1:30am, now 13 out of 13 rings tall

Crane rigging from LR11000X detached and reattached from/to SN20/S20

SN20/S20 disconnected (8:19am) and reconnected to LR11000X at 10:31am, lifted from pad B on to transport stand with QD at 11:42-57am

OLS IT work continued

Ship QD worked on

NSF

Nic

LabPadre

[272]
21.01.2022 McGregor: Raptor 2 engine test at ?:?? pm on horizontal test stand for about 1m58s

McGregor: Raptor 2 engine test at ?:?? pm on vertical test stand for about 1m10s

Cuker

Cuker

no
20.01.2022 LOX deliveries to OLS tank farm

SN20/S20 still hooked to LR11000X on Pad B; transport stand next to it

GSE4 remains still laying around

Berm removal continued

Ship nosecone barrel section in high bay

S21 tank section still outside mid bay

Oilfield workers and equipment from FESCO arrived at Boca Chica

B2.1 work on outside

Earth and concrete work behind high bay and wide bay looks like foundation for some new building/construction

New RCs for January 26–27 (10am-10pm) and 28 (6am-4pm)

NSF

Mary

LabPadre

[273]
19.01.2022 Ship QD transport stand positioned next to S20/SN20 at 9:37am

Production tent moving continued

High bay rooftop bar work continued

Single 3.6mm ring moved into high bay

Smooth nosecones in tent 3; first one with TPS pins [Randolph]

Ship common dome spotted

Booster fwd dome moved

High bay: ship nosecone barrel section attached to crane (3.6mm!)

Smooth nosecone moved out of tent 3, next to S22 nc barrel section (cargo door prototype)

Wide bay work continued on all current levels; assembly of level 7&8 has begun

GSE4 remains at launch site

OLM work continued

Chopsticks worked on

Concrete forms constructed at launch site

Perimeter fence being welded at launch site

Cryogenic deliveries to OLS tank farm

RCs for January 20 and 21 canceled

Elon Musk catching simulation video on Twitter

McGregor: Raptor 2 engine test at ?:?? pm on horizontal test stand for about 1m46s; throttling of engine

NSF

Mary

Nic

LabPadre

Cuker

[274]
18.01.2022 Chopsticks worked on

Commodities delivered to OLS tank farm

GSE4 test tank cryo proof tested to failure (popping)

Wide bay construction work continued on lower levels; concrete work behind wide bay

S22 nosecone barrel section (5-ring) as payload door prototype closeup; work continued, more of the door has been cut

High bay rooftop bar work continued

B7 CH4 section stacked on a 3-ring section; now 9 of 13 rings tall

RC for tomorrow canceled

NSF

Mary

LabPadre

Randolph

[275]
17.01.2022 LR11000X moved towards SN20/S20

SN20/S20 lifting squid attached; work on QD area on Pad B (disconnected from GSE connections); connected to LR11000X

OLS, IT: Roof installation has begun

OLM: Painting work

B4 work on QD area; aerocover for QD panel installed

Concrete mixer moved by crane at OLS tank farm

Wide bay construction work continued; cross beams added for level 5&6

Concrete work behind wide bay

B7 fwd section #3 (3-ring) in high bay; stacked, now 6/13 rings tall

S21 tank section moved out of mid bay once again

Nosecone scrapping work continued

Tent moved at production site (again?)

NSF

Mary

Nic

LabPadre

[276]
16,01.2022 B7 Ch4 tank sections ready for stacking

OLS tank farm work, parts lifted

NSF

Mary

LabPadre

[277]
15.01.2022 Wide bay: 4th corner segment of level 5&6 has been lifted

LR11000X turned

OLS tank farm: Klemm KR702-2R Drill rig in action

B7 3-ring CH4 tank section (with lead-ins) and fwd dome section moved into high bay

OLM QD: several full speed hood tests (05:21am

NSF

Mary

Nic

LabPadre

[278]
14.01.2022 OLS tank farm: Large number of trucks delivered LOX/LN2; some venting

Ship QD work continued

Berm removal continue

B4 work on engine section (work on aerocovers): engines have received side covers; three aerocovers are now installed

B7 fwd dome section (sleeved) spotted outside highbay

Wide bay: work continued; level 7&8 preassembly has begun; LR11000 disconnected from segment; fourth section lifted at 3:15pm and installed

Load spreader moved away from production site

Crane connected to a 2-ring leg skirt

Crane with huge load spreader (delivered on January 9) relocating a tent at production site (the one next to tent 3)

McGregor: Raptor 2 engine test at ?:?? pm on vertical test stand for about 0m26s; green flash at shut off

NSF

Mary

Nic

LabPadre

Cuker

[279]
13.01.2022 B2.1 work through access hole

SoLS Pad A: Booster adaptor removed Wide bay: third level 5&6 (3) segment attached to crane and lifted; more beams added

Unused nosecone attached to crane, scrapped, cut in half

Groundwork behind high and wide bays continued

B4 work continued; first aerocovers finally being added

B3 engine section removed from Pad A

Chopsticks: Beam and water bags remvoed

RC for tomorrow canceled

NSF

Mary

Nic

LabPadre

[280]
12.01.2022 Wide bay: Preassembly of remaining level 5&6 segments continued

LR11000 ("Buucky") lifted and lowereed again; raised again

Parts for a construction elevator delivered

B2.1 test stand cap removed

Mobile offices delivered to production site

Choptsticks: worked on; ballast bags filled with water (canflex crane test water bags for 100 tons); tested (moved upwards a bit; sideways as well)

Berm removal continued

LN2 and LOX deliveries to OLS tank farm

B3 scrapping continued

B4 covers worked on

B7 downcomer installed into LOX section beginning at around 19:55

RC for tomorrow canceled

New RCs for January 18–20 (10am-10pm)

McGregor: Raptor 2 engine test at 8:43 pm on vertical test stand for about 1m20s

NSF

Mary

Nic

LabPadre

Cuker

[281]
11.01.2022 Wide bay: ramaining two level 5&6 segments preassembly continued; cross beams added on level 5&6

Hydraulic rams loaded onto truck

Booster fwd dome sleeve and dome in front of tents

B3 scrapping continued

B2.1 hatch opened by force

Ship aft flap with tiles waitung for installation

LR11000 lowered boom at production site

PPS: new structure (black stand?) spotted

Chopsticks: Cross bar with ballast bags (re-)attached; moved to the top (not filled, fastest yet); drone inspected; moved down

OLS, IT (OLIT): workers started adding roof tiles

Tank farm/launch pad berm continued to be removed

Ship QD: grab arms moved; full arm moved

B4 work continued around QD area

GSE4 test tank worked on

SN20/S20 work continued

RC for tomorrow canceled

NSF

Mary

Nic

LabPadre

[282]
10.01.2022 Wide bay: LR11000 still connected to corner segment; work other two segments of level 5&6

Crane work at production site

Ship stand with disconnect moved to launch site

OLS tank farm/landing pad berm continued to be removed

LN2 and LOX deliveries to OLS tank farm

B3 scrapping continued

Chopsticks tested: fastes move yet (stayed relatively low)

NSF

Mary

Nic

LabPadre

[283]
09.01.2022 Crane weights transported on SPMT

Mystery column still at production site

Leg skirt barrel segment spotted in tent

S22 5-ring nosecone barrel; possibly payload door prototype

S24 common dome (4-ring, with new types of lead-ins) spotted

Load spreader delivered

OLM work continued; raptor disconnect vent [?] tested twice

Chopsticks work continued; bar lifted onto it to connect both arms, installed; chopsticks tested; rose very slowly to the top; arm movement on the top; slowly lowered down again

Ship QD arm work continued; tested (extended and retracted)

B3 scrapping continued

SN20/S20 worked on

McGregor: Raptor 2 engine test at 2:00 pm on horizontal test stand for about 0m40s

NSF

Mary

Nic

LabPadre

Cuker

[284]
08.01.2022 Ship QD and chopsticks being tested [see below]

OLS/landing pad earth work continued

Nilgai spotted

Wide bay work continued

B2.1 test tank: Ropes continued to being disconnected from structural test stand

B3 LOX section scrapping began on pad A; tank section cut off from aft section an lifted away; scrapping of tank section continued

OLM: Work on booster QD

Booster fwd dome outside tents

B7 rotated in tent

NSF

Mary

Nic

LabPadre

[285]
07.01.2022 OLM work continued with last shieldings continued to being added

Power bay: Stair added

OLS/landing pad berm continued to be removed

Ship transport stand and ballast transported to production site

Earth work behind high and wide bay continued (levelling)

Wide bay: New beams delivered; beams added between corner sections of level 5&6, preassembly of level 5&6, as well as of 7&8 continued

B7 aft LOX tank segment #5 (4-ring) moved into high bay

B2.1 test tank: ropes have been detached from lower attachment points; crews removing one of the ropes

OLS tank farm testing with activity from CH4 subcoolers and LN2 tanks; green blinking lights spotted [vid 08]

LR11000X moved towards B3 and attached to it [vid 08]

Chopsticks extensively tested, especially horizontal arm movement; observed by a SpaceX drone [vid 08]

Ship QD arm movement tested [vid 08]

B7 LOX tank section lifted in high bay; stacked onto another LOX tank section (now 20 out of 23 rings tall) [vid 08]

B3 attached to LR11000X at 8:53pm

McGregor: Raptor 2 engine test at 7:19 pm on horizontal test stand for about 0m34sec

NSF

Mary

Nic

LabPadre

Cuker

[286]
06.01.2022 New RCs for January 12 (10am-8pm), 13-14 (6am-4pm)

B4 attached to LR11000X

OLS/landing pad berm earth continued to be removed

Wall construction between landing pad and hwy 4 continued

SoLS: Ground repair work began near pad B

OLM: Awning/shieldings added

Chopsticks work continued Wide bay: Second corner segment of level 5&6 lifted by LR11000 and installed

Work on ship QD: New panels added, some curved (soft?) plates added (bumpers)

LOX and LN2 deliveries to OLS tank farm

SN20/S20 work on fwd flaps

B4 work through access hole

Construction elevator moved away from launch site

Wide bay: Work continued, second corner segment for level 5&6 lifted by LR11000 and installed

Foundation work next to stargate building

High bay rooftop bar work continued

S24 mid LOX section has tiles attached

New ship section spotted outside tents (4-ring, no lead-ins)

New RCs for January 12 (10am-10pm) and 13-14 (6am-4pm)

McGregor: Raptor 2 engine test at ?:?? pm on vertical test stand for about 1m00sec

NSF

Mary

Nic

LabPadre

Cuker

[287]
05.01.2022 Fast booster QD retraction test at 12:55 am, another one, fastest yet, at 4:16 pm

Chopsticks work continued

Wide bay: First segment of level 5&6 lifted slowly, put down again, LR11000 moved forward into the bay, lifted and installed; work on finishing level 2 continued

Earth work south-west of wide bay

SN2 lifted from concrete stand at production site, lowered onto transport stand, moved to PPS

5-ring nosecone barrel section at scrap yard; scrapped flaps spotted

Rotating fabrication mount from tent 2 moved ("These spin a barrel section so a robotic welder can access the seam between two rings")

B4 work continued

OLM awning installation continued, one has a hole; some other work

GSE4 worked on

OLS tank farm venting next to horizontal CH4 tanks and CH4 subcoolers

NSF

Mary

Nic LabPadre

[288]
04.01.2022 Wide bay construction work continued with cross beams and wall plates being added; more beams delivered;

Chopsticks (Mechazilla) tested

Possible cargo door pathfinder shown

B4 work continued on several areas

Fence with semi-transparent plates being added between landing pad and hwy 4

LN2 delivery to OLS tank farm

OLS bearm towards landing pad being removed

OLM work continued, first three awnings installed to protect pipes equipment on the side of the OLT

Chopsticks work; testesd very slowly: risen up several meters, right arm opened up, left arm tested, moved down, rose again, arms tested in several angles, moved down to original position [per part vid 05]

PLS, IT scaffolding continued to be removed

McGregor: Raptor 2 engine test at 8:53 pm on horizontal test stand for about 1m32sec

NSF

Mary

Nic

LabPadre

Cuker

[289]
03.01.2022 LOX and LN2 deliveres to launch site

SN20/S20 Tiles being removed again at the nosecone lift points after the static fire

OLS, IT: Scaffold continued to being removed

OLS berm: earth work continued; some earth being removed

Booster QD on OLM: Insulation being wrapped around main QD pipes

"Dog house" covers have been painted grey

Wide bay: LR11000 connected to first level 5&6 corner segment; work on lower levels continued

S24 common dome sleeve waiting to be sleeved; load spreader attached to S24 common dome, lifted onto sleeving stand; no header tank installed, Elon Musk confirmed that CH4 header tank would be moved to nosecone [!]; load spreader connected to common dome sleeve, sleeved on dome

Stair construction near high bay continued

Deliveries (bround half rings, McDonough machine)

Chopsticks work continued

LR11000X moved to landing pad and attached to B4 via loadspreader

Elon Musk: "Raptor 2 now operates routinely at 300 bar main chamber pressure"

SN20/S20 Liftting points reinstalled

NSF

Mary

LabPadre

[290]
02.01.2022 Ship QD arm still waiting for its completion

B4 on landing pad

Minor work began again

Wind damage at Tent 1 (roll-up door)

Chopsticks short move upwards

NSF

Mary

LabPadre

[291]